ODOT letting results, May 12, 2022
43 contracts let by Ohio DOT on May 12, 2022, $167,638,279 in low bids, a median of 3 bidders per contract. On the 43 with an engineer's estimate, the low bid came in under it 17 times; median low bid +2.0% against the estimate.
- Owner
- Ohio DOT
- Contracts
- 43
- Low bids, total
- $167,638,279
- Data through
- 12 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 220256 | LUC-IR 475-01.85 @20A Interchnge (PART 1, PART 2, PART 3) (MAJOR RECONSTRUCTION) | LUC | 3 | Kokosing Construction Company Inc | $101,983,274 | $103,707,607 | +2.0% | -8.0% | ODOT |
| 223005 | MAD-IR 70-10.27 Phase 2 (INTERCHANGE) | MAD | 4 | Eagle Bridge Co | $13,174,360 | $13,509,639 | +3.0% | 0.0% | ODOT |
| 220290 | CLI-IR 71-12.13/13.99 (BRIDGE REPLACEMENT (2 BRIDGES)) | CLI | 4 | Shelly & Sands Inc | $10,351,991 | $10,377,359 | 0.0% | +18% | ODOT |
| 220322 | GUE-/MUS/COS-SR 662-00.00/00.00/00.00 (MAJOR RECONSTRUCTION) | GUE | 2 | Shelly & Sands Inc | $6,832,488 | $7,165,843 | +5.0% | +10% | ODOT |
| 220304 | TRU-SR 5/SR 82-13.94/13.88 (PART 1 AND PART 2) (FOUR LANE RESURFACING) | TRU | 2 | Shelly & Sands Inc | $3,509,499 | $4,675,252 | +33% | +6.0% | ODOT |
| 220300 | MAR-SR 98-06.22 (at SR 529) (INTERSECTION) | MAR | 3 | Miller Bros Const Inc | $2,546,283 | $3,324,687 | +31% | -13% | ODOT |
| 220298 | LOR-US 6-00.00 (FOUR LANE RESURFACING) | LOR | 3 | Kokosing Construction Company Inc | $2,360,142 | $2,505,298 | +6.0% | -6.0% | ODOT |
| 220302 | OTT-SR 163-33.85 Roundabout (INTERSECTION) | OTT | 1 | Great Lakes Demolition Company | $2,035,827 | +2.0% | ODOT | ||
| 220307 | ASD-/MED-IR 71/IR 76 Truck Parking (PARKING AREAS) | ASD | 3 | Shelly & Sands Inc | $2,006,926 | $2,147,929 | +7.0% | -1.0% | ODOT |
| 220295 | HAM-US 22/SR 3-09.66 Silverton (SIGNALIZATION) | HAM | 3 | Complete General Construction Company | $1,949,591 | $2,139,086 | +10% | +4.0% | ODOT |
| 220314 | D04-SP FY2022 (West) (SPOT PATCHING / PAVEMENT REPAIR) | District 4 | 3 | Karvo Companies Inc | $1,888,000 | $2,758,700 | +46% | +44% | ODOT |
| 220324 | LAW-SR 378-06.56 Landslide (SLIDE REPAIR) | LAW | 3 | Alan Stone Co Inc | $1,325,261 | $1,393,044 | +5.0% | -9.0% | ODOT |
| 220313 | D04-SP FY2022 (East) (SPOT PATCHING / PAVEMENT REPAIR) | District 4 | 3 | Shelly Company | $1,324,544 | $1,488,000 | +12% | +2.0% | ODOT |
| 220305 | WAS-Start Westward Phase 1 (LIGHTING) | WAS | 2 | Complete General Construction Company | $1,301,556 | $1,324,339 | +2.0% | +22% | ODOT |
| 220319 | D09-GR-FY2022 (GUARDRAIL REBUILDING) | District 9 | 2 | Lake Erie Construction Company | $1,186,725 | $1,269,715 | +7.0% | +9.0% | ODOT |
| 220297 | LOG-SR 347-03.63 (FOUR LANE RESURFACING) | LOG | 1 | Shelly Company | $1,132,004 | +2.0% | ODOT | ||
| 220303 | SUM-CR 17-23.27 Brecksville Rd (TWO LANE RESURFACING) | SUM | 6 | Shelly Company | $1,078,757 | $1,119,000 | +4.0% | -6.0% | ODOT |
| 220301 | MED-SR 3-17.05 (CULVERT REPLACEMENT) | MED | 1 | Great Lakes Construction Co | $1,068,788 | +9.0% | ODOT | ||
| 220317 | D05-FY 2022 Signal Upgrade (SIGNALIZATION) | District 5 | 4 | Perram Electric Inc | $1,057,975 | $1,079,066 | +2.0% | +4.0% | ODOT |
| 220321 | FAY-/MAD-SP FY22 Gen (SPOT PATCHING / PAVEMENT REPAIR) | FAY | 2 | Kokosing Construction Company Inc | $836,324 | $999,592 | +20% | +8.0% | ODOT |
| 220315 | D04-CS FY2022 (CRACK SEALING) | District 4 | 2 of 4 | $831,417 | $835,094 | 0.0% | -25% | ODOT | |
| 220308 | D03-/RIC-SR 95/SR 603-01.46/00.00 (CHIP SEAL) | District 3 | 3 | Henry W Bergman Inc | $629,065 | $653,009 | +4.0% | 0.0% | ODOT |
| 220326 | MEG-SR 681-04.78 (SLIDE REPAIR) | MEG | 10 | Allard Excavation LLC | $595,484 | $613,862 | +3.0% | -12% | ODOT |
| 220323 | JEF-SR 7-04.00 Truck Parking Area (PARKING AREAS) | JEF | 5 | Ohio-West Virginia Excavating Co | $594,091 | $646,616 | +9.0% | -13% | ODOT |
| 220291 | COL-SR 45-03.36 (CULVERT REPLACEMENT) | COL | 6 | Bog Construction Inc | $556,775 | $615,384 | +11% | -27% | ODOT |
| 220263 | BEL-SR 149-13.63 (SLIDE REPAIR) | BEL | 4 | Litman Excavating Inc | $507,901 | $547,325 | +8.0% | -20% | ODOT |
| 224015 | ATH-SR 691-05.17 (CULVERT REPLACEMENT) | ATH | 5 | Parker Corporation | $408,462 | $488,036 | +19% | 0.0% | ODOT |
| 220310 | BEL-SR 26-06.92 (SLIDE REPAIR) | BEL | 4 | Alan Stone Co Inc | $390,924 | $398,219 | +2.0% | -13% | ODOT |
| 220320 | D10-RPM FY2022 (RAISED PAVEMENT MARKERS) | District 10 | 2 | W L Markers Inc | $347,727 | $378,131 | +9.0% | +37% | ODOT |
| 220299 | MAH-McGaffney St Extension Ph 2 (NEW CONSTRUCTION) | MAH | 7 | Shelly & Sands Inc | $344,314 | $383,000 | +11% | -22% | ODOT |
| 224017 | LOR-SR 57-06.58 (CULVERT REPLACEMENT) | LOR | 2 | Eclipse Co LLC | $342,654 | $382,570 | +12% | +14% | ODOT |
| 220312 | D02-TSG FY2022 (SIGNALIZATION) | District 2 | 4 | Miller Cable Company | $322,000 | $327,500 | +2.0% | -1.0% | ODOT |
| 220318 | D06-RPM FY22 (RAISED PAVEMENT MARKERS) | District 6 | 2 | W L Markers Inc | $309,011 | $392,052 | +27% | +29% | ODOT |
| 220329 | WAS-Belpre Resurfacing FY2022 (TWO LANE RESURFACING) | WAS | 1 | Shelly & Sands Inc | $308,033 | +1.0% | ODOT | ||
| 220309 | BEL-IR 70-VARIOUS (BRIDGE REPAIR) | BEL | 5 | Ram Construction Services of Michigan, Inc | $297,247 | $309,284 | +4.0% | +12% | ODOT |
| 220294 | GRE-Yellow Springs SRTS 2019 (SIDEWALK) | GRE | 2 | Fillmore Construction | $296,876 | $384,825 | +30% | +35% | ODOT |
| 220330 | WAY-US 30/SR 57-(06.63)(06.98)/01.80 (CULVERT REPLACEMENT) | WAY | 2 | Eclipse Co LLC | $293,510 | $232,737 | -21% | +47% | ODOT |
| 220306 | ADA-SR 125-01.34 Slide Repair (SLIDE REPAIR) | ADA | 6 | Allard Excavation LLC | $278,592 | $296,618 | +6.0% | -13% | ODOT |
| 220328 | SCI-SR 335-09.38 Slide Repair (SLIDE REPAIR) | SCI | 4 | Allard Excavation LLC | $248,874 | $286,896 | +15% | -16% | ODOT |
| 220316 | D04-LOOP FY2022 (SIGNALIZATION) | District 4 | 2 | Miller Cable Company | $212,500 | $229,150 | +8.0% | +8.0% | ODOT |
| 220327 | OTT-SR 105-04.90 Clvt replace (CULVERT REPLACEMENT) | OTT | 3 | Geo Gradel Co | $203,298 | $265,928 | +31% | -33% | ODOT |
| 220292 | CUY-SRTS FY2022 Cleveland Hts (SIDEWALK) | CUY | 3 | Cook Paving & Construction Co Inc | $199,468 | $178,000 | -11% | +19% | ODOT |
| 220289 | BRO-US 52-03.63 Geotech/Landslide (SLIDE REPAIR) | BRO | 5 | Coopers Excavating LLC | $169,741 | $179,885 | +6.0% | +4.0% | ODOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.