ODOT contract 250599 bid tabulation
TRU-US 62-04.56 (FOUR LANE RESURFACING). Let by Ohio DOT on December 18, 2025, TRU. 4 bids received; low bid $4,111,119 by Kirila Contractors Inc, -7.2% against the engineer's estimate of $4,430,000.
- Owner
- Ohio DOT
- Letting
- 18 DEC 2025
- Pay items
- 122
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Kirila Contractors Inc | $4,111,119 | Low | -7.0% |
| 2 | Shelly & Sands Inc | $4,119,251 | 0.0% | -7.0% |
| 3 | Shelly Company | $4,667,687 | +14% | +5.0% |
| 4 | Karvo Companies Inc | $4,872,551 | +19% | +10% |
Engineer's estimate: $4,430,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Kirila Contractors Inc | 2. Shelly & Sands Inc | 3. Shelly Company | 4. Karvo Companies Inc |
|---|---|---|---|---|---|---|---|
| 1 | Headwall removed (202E20010) | EACH | 2 | $250.00 | $500.00 | $700.00 | $500.00 |
| 2 | Pavement removed (202E23000) | SY | 1,040 | $15.00 | $7.50 | $26.50 | $25.00 |
| 3 | Pipe removed, 24" and under (202E35100) | FT | 197 | $15.00 | $3.00 | $28.00 | $27.00 |
| 4 | Catch basin removed (202E58100) | EACH | 3 | $300.00 | $250.00 | $1,500.00 | $700.00 |
| 5 | Monument assembly removed (202E60010) | EACH | 1 | $350.00 | $500.00 | $1,000.00 | $95.00 |
| 6 | Special - fill and plug existing conduit (202E70000) | FT | 421 | $25.00 | $5.00 | $50.00 | $30.00 |
| 7 | Removal misc.:barrier reflector (202E98100) | EACH | 24 | $5.00 | $5.00 | $5.00 | $5.00 |
| 8 | Excavation (203E10000) | CY | 740 | $18.00 | $26.00 | $48.00 | $41.00 |
| 9 | Excavation (203E10000) | CY | 117 | $25.00 | $26.00 | $28.00 | $85.00 |
| 10 | Embankment (203E20000) | CY | 126 | $20.00 | $65.00 | $75.00 | $35.00 |
| 11 | Subgrade compaction (204E10000) | SY | 1,973 | $1.50 | $3.00 | $1.25 | $2.00 |
| 12 | Proof rolling (204E45000) | HR | 1 | $200.00 | $100.00 | $135.00 | $350.00 |
| 13 | Linear grading (209E60200) | STA | 469 | $70.00 | $65.00 | $70.00 | $30.00 |
| 14 | Monument assembly, type C (623E38500) | EACH | 1 | $1,500.00 | $750.00 | $3,250.00 | $1,200.00 |
| 15 | Special - pavement overlay fabric composite (690E12060) | SY | 643 | $46.00 | $45.75 | $45.75 | $45.75 |
| 16 | Special - as-built construction plans (690E91000) | LS | 1 | $750.00 | $3,000.00 | $10,000 | $1,200.00 |
| 17 | Longitudinal channelizing device, as per plan (831E00101) | FT | 38 | $150.00 | $150.00 | $150.00 | $150.00 |
| 18 | Longitudinal channelizing device, as per plan (831E00101) | FT | 38 | $42.50 | $42.50 | $42.50 | $42.50 |
| 19 | Removal of longitudinal channelizing device (831E00500) | FT | 38 | $15.00 | $15.00 | $15.00 | $15.00 |
| 20 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 12 | $200.00 | $200.00 | $220.00 | $375.00 |
| 21 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 2 | $250.00 | $125.00 | $1,200.00 | $870.00 |
| 22 | Topsoil (659E00300) | CY | 177 | $60.00 | $75.00 | $72.00 | $65.00 |
| 23 | Seeding and mulching (659E10000) | SY | 1,591 | $4.00 | $5.00 | $1.30 | $1.50 |
| 24 | Commercial fertilizer (659E20000) | TON | 0.22 | $885.00 | $910.00 | $1,500.00 | $800.00 |
| 25 | Lime (659E31000) | ACRE | 0.33 | $161.00 | $607.00 | $1.00 | $180.00 |
| 26 | Water (659E35000) | MGAL | 9 | $1.00 | $2.00 | $60.00 | $1.00 |
| 27 | Ditch erosion protection (670E00700) | SY | 338 | $1.50 | $3.00 | $4.00 | $1.50 |
| 28 | Storm water pollution prevention plan (832E15000) | LS | 1 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 |
| 29 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $6,420.00 | $12,840 | $5,350.00 | $9,630.00 |
| 30 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $1,075.00 | $1,140.00 | $1,100.00 | $1,073.61 |
| 31 | Erosion control (832E30000) | EACH | 3,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 32 | Concrete masonry (602E20000) | CY | 1.14 | $4,450.00 | $350.00 | $5,250.00 | $4,950.00 |
| 33 | 6" unclassified pipe underdrains (605E13300) | FT | 20 | $25.00 | $20.00 | $28.00 | $35.00 |
| 34 | 6" base pipe underdrains with geotextile fabric (605E14020) | FT | 1,174 | $15.00 | $32.00 | $26.50 | $24.50 |
| 35 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 68 | $28.00 | $30.00 | $40.00 | $39.00 |
| 36 | 6" conduit, type F for underdrain outlets, as per plan (611E00511) | FT | 30 | $32.00 | $30.00 | $90.00 | $90.00 |
| 37 | 6" conduit, type F, as per plan (611E01501) | FT | 90 | $32.00 | $32.00 | $30.00 | $31.00 |
| 38 | 12" conduit, type B (611E04400) | FT | 432 | $71.00 | $65.00 | $145.00 | $115.00 |
| 39 | 15" conduit, type B (611E05900) | FT | 220 | $110.00 | $75.00 | $155.00 | $120.00 |
| 40 | 15" conduit, type B (611E05900) | FT | 11 | $174.00 | $175.00 | $300.00 | $268.00 |
| 41 | 18" conduit, type B (611E07400) | FT | 71 | $98.00 | $100.00 | $160.00 | $130.00 |
| 42 | Catch basin, no. 3A (611E98180) | EACH | 3 | $3,650.00 | $5,200.00 | $4,300.00 | $5,200.00 |
| 43 | Catch basin, no. 5 (611E98300) | EACH | 3 | $4,375.00 | $4,900.00 | $5,250.00 | $4,000.00 |
| 44 | Catch basin, no. 6 (611E98370) | EACH | 1 | $4,525.00 | $4,500.00 | $4,800.00 | $3,600.00 |
| 45 | Catch basin, no. 2-2B (611E98470) | EACH | 1 | $2,075.00 | $3,500.00 | $3,800.00 | $3,200.00 |
| 46 | Precast reinforced concrete outlet (611E99710) | EACH | 5 | $1,000.00 | $1,500.00 | $600.00 | $160.00 |
| 47 | Partial depth pavement repair (441) (251E01000) | SY | 1,800 | $48.25 | $50.00 | $50.00 | $37.00 |
| 48 | Full depth pavement sawing (252E01500) | FT | 1,459 | $2.75 | $4.00 | $2.50 | $2.50 |
| 49 | Pavement planing, asphalt concrete (T=1.5") (254E01000) | SY | 171,822 | $1.50 | $1.20 | $1.80 | $1.80 |
| 50 | Pavement planing, asphalt concrete, as per plan (T (254E01001) | SY | 31,356 | $0.75 | $1.20 | $1.85 | $1.65 |
| 51 | Full depth pavement removal and rigid replacement, type 2, class QC1 (255E12000) | SY | 900 | $263.00 | $275.00 | $270.00 | $241.00 |
| 52 | Full depth pavement removal and rigid replacement, type 2, class QC RS (255E19100) | SY | 106 | $317.00 | $300.00 | $350.00 | $350.00 |
| 53 | Full depth pavement sawing (255E20000) | FT | 4,291 | $3.00 | $3.00 | $2.50 | $2.50 |
| 54 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 404 | $205.00 | $200.00 | $220.00 | $230.00 |
| 55 | Aggregate base (304E20000) | CY | 334 | $72.00 | $65.00 | $100.00 | $93.00 |
| 56 | Aggregate base (304E20000) | CY | 117 | $85.00 | $75.00 | $55.00 | $65.00 |
| 57 | Non-tracking tack coat (407E20000) | GAL | 18,615 | $3.50 | $3.05 | $2.50 | $2.35 |
| 58 | Prime coat, as per plan (408E10001) | GAL | 7,867 | $3.25 | $3.50 | $5.00 | $4.70 |
| 59 | Anti-segregation equipment (441E00100) | CY | 5,845 | $15.35 | $10.00 | $6.00 | $7.85 |
| 60 | Asphalt concrete surface course, 12.5 MM, type A (446) (442E10000) | CY | 8,542 | $236.00 | $220.00 | $245.00 | $270.00 |
| 61 | Asphalt concrete intermediate course, 19 MM, type A (449) (442E22400) | CY | 126 | $270.00 | $300.00 | $325.00 | $340.00 |
| 62 | 6" non-reinforced concrete pavement, class QC 1P (452E10010) | SY | 115 | $85.00 | $83.00 | $135.00 | $130.00 |
| 63 | Curb, type 6 (609E26000) | FT | 528 | $40.00 | $28.00 | $36.00 | $45.00 |
| 64 | Compacted aggregate, as per plan (617E10101) | CY | 547 | $139.00 | $90.00 | $120.00 | $131.00 |
| 65 | Rumble strips, shoulder (asphalt concrete) (618E40600) | MI | 14 | $1,200.00 | $975.00 | $975.00 | $975.00 |
| 66 | RPM (621E00100) | EACH | 160 | $42.60 | $42.60 | $42.60 | $39.00 |
| 67 | RPM, as per plan (621E00101) | EACH | 884 | $38.50 | $38.50 | $38.50 | $39.00 |
| 68 | Raised pavement marker removed (621E54000) | EACH | 519 | $5.00 | $5.00 | $7.00 | $5.50 |
| 69 | Barrier reflector, type 1 (one way) (626E00102) | EACH | 40 | $17.25 | $17.25 | $17.25 | $17.25 |
| 70 | Barrier reflector, type 2 (one way) (626E00110) | EACH | 90 | $30.00 | $30.00 | $30.00 | $30.00 |
| 71 | Ground mounted support, no. 3 post, as per plan (630E03101) | FT | 132 | $16.50 | $16.50 | $16.50 | $16.50 |
| 72 | Sign post reflector (630E08600) | EACH | 1 | $45.00 | $45.00 | $45.00 | $45.00 |
| 73 | Sign post reflector (630E08600) | EACH | 6 | $45.00 | $45.00 | $45.00 | $45.00 |
| 74 | Sign post reflector (630E08600) | EACH | 2 | $45.00 | $45.00 | $45.00 | $45.00 |
| 75 | Sign, flat sheet (630E80100) | SF | 35 | $20.00 | $20.00 | $20.00 | $20.00 |
| 76 | Removal of ground mounted sign and disposal (630E84900) | EACH | 3 | $25.00 | $25.00 | $25.00 | $25.00 |
| 77 | Removal of ground mounted sign and reerection (630E85100) | EACH | 4 | $125.00 | $125.00 | $125.00 | $125.00 |
| 78 | Removal of ground mounted post support and disposal (630E86002) | EACH | 7 | $15.00 | $15.00 | $15.00 | $15.00 |
| 79 | Edge line, 6" (646E10010) | MI | 4.52 | $2,900.00 | $2,900.00 | $2,900.00 | $2,900.00 |
| 80 | Lane line, 6" (646E10110) | MI | 2.34 | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 81 | Center line (646E10200) | MI | 0.22 | $3,750.00 | $3,750.00 | $3,750.00 | $3,750.00 |
| 82 | Channelizing line, 12" (646E10310) | FT | 4,598 | $1.85 | $1.85 | $1.85 | $1.85 |
| 83 | Stop line (646E10400) | FT | 509 | $10.00 | $10.00 | $10.00 | $10.00 |
| 84 | Transverse/diagonal line (646E10600) | FT | 1,055 | $10.00 | $10.00 | $10.00 | $10.00 |
| 85 | Chevron marking (646E10620) | FT | 534 | $10.00 | $10.00 | $10.00 | $10.00 |
| 86 | Island marking (646E10800) | SF | 523 | $7.50 | $7.50 | $7.50 | $7.50 |
| 87 | Lane arrow (646E20300) | EACH | 54 | $135.00 | $135.00 | $135.00 | $135.00 |
| 88 | Dotted line, 6" (646E20504) | FT | 1,390 | $1.50 | $1.50 | $1.50 | $1.50 |
| 89 | Wet reflective epoxy pavement marking, edge line, 6" (807E12010) | MI | 13.20 | $3,250.00 | $3,250.00 | $3,250.00 | $3,250.00 |
| 90 | Wet reflective epoxy pavement marking, lane line, 6" (807E12110) | MI | 6.60 | $1,625.00 | $1,625.00 | $1,625.00 | $1,625.00 |
| 91 | Wet reflective epoxy pavement marking, center line (807E12200) | MI | 0.29 | $4,000.00 | $4,000.00 | $4,000.00 | $4,000.00 |
| 92 | Wet reflective epoxy pavement marking, channelizing line, 12" (807E12310) | FT | 4,150 | $2.25 | $2.25 | $2.25 | $2.25 |
| 93 | Wet reflective epoxy pavement marking, dotted line, 6" (807E12410) | FT | 3,030 | $1.25 | $1.25 | $1.25 | $1.25 |
| 94 | Grooving for 6" recessed pavement marking, (asphalt) (850E10010) | MI | 19.89 | $1,100.00 | $1,100.00 | $1,100.00 | $1,100.00 |
| 95 | Grooving for 6" recessed pavement marking, (asphalt) (850E10110) | FT | 3,030 | $1.00 | $1.00 | $1.00 | $1.00 |
| 96 | Grooving for 12" recessed pavement marking, (asphalt) (850E10130) | FT | 4,150 | $2.00 | $2.00 | $2.00 | $2.00 |
| 97 | Grooving for 6" recessed pavement marking, (concrete) (850E20010) | MI | 0.20 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 |
| 98 | Advance radar detection, as per plan (809E69001) | EACH | 2 | $9,250.00 | $9,250.00 | $9,250.00 | $9,000.00 |
| 99 | Stop line radar detection, as per plan (809E69101) | EACH | 8 | $8,950.00 | $8,950.00 | $8,950.00 | $8,600.00 |
| 100 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 100 | $75.00 | $95.00 | $120.00 | $110.00 |
| 101 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 7 | $2,320.00 | $2,320.00 | $2,750.00 | $1,739.42 |
| 102 | Detour signing (614E12420) | LS | 1 | $3,250.00 | $3,250.00 | $3,250.00 | $3,250.00 |
| 103 | Work zone marking sign (614E12460) | EACH | 12 | $85.00 | $85.00 | $85.00 | $85.00 |
| 104 | Object marker, one way (614E13350) | EACH | 35 | $22.50 | $22.50 | $22.50 | $22.50 |
| 105 | Portable changeable message sign, as per plan (614E18601) | SNMT | 16 | $900.00 | $850.00 | $850.00 | $850.00 |
| 106 | Work zone lane line, class I, 6" (614E20010) | MI | 8.94 | $750.00 | $750.00 | $500.00 | $750.00 |
| 107 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 8.94 | $750.00 | $750.00 | $500.00 | $750.00 |
| 108 | Work zone center line, class I (614E21000) | MI | 0.51 | $1,100.00 | $1,100.00 | $2,000.00 | $1,100.00 |
| 109 | Work zone center line, class III, 642 paint (614E21550) | MI | 0.51 | $1,100.00 | $1,100.00 | $2,000.00 | $1,100.00 |
| 110 | Work zone edge line, class I, 6" (614E22010) | MI | 1.28 | $2,250.00 | $2,250.00 | $1,000.00 | $2,250.00 |
| 111 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 17.72 | $500.00 | $500.00 | $650.00 | $500.00 |
| 112 | Work zone channelizing line, class I, 12" (614E23010) | FT | 9,795 | $1.25 | $1.25 | $0.75 | $1.25 |
| 113 | Work zone channelizing line, class III, 12", 642 paint (614E23690) | FT | 8,748 | $1.25 | $1.25 | $0.75 | $1.25 |
| 114 | Work zone dotted line, class I (614E24000) | FT | 2,407 | $1.00 | $1.00 | $0.75 | $1.00 |
| 115 | Work zone stop line, class I (614E26000) | FT | 509 | $3.50 | $3.50 | $4.00 | $3.50 |
| 116 | Work zone stop line, class III, 642 paint (614E26610) | FT | 509 | $3.50 | $3.50 | $3.50 | $3.50 |
| 117 | Portable barrier, unanchored (622E41100) | FT | 1,644 | $20.00 | $29.50 | $20.00 | $37.00 |
| 118 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $17,578 | $15,000 | $20,000 | $65,000 |
| 119 | Maintaining traffic (614E11000) | LS | 1 | $136,186 | $278,796 | $380,000 | $240,000 |
| 120 | Field office, type B (619E16010) | MNTH | 12 | $3,500.00 | $3,500.00 | $3,500.00 | $2,200.00 |
| 121 | Construction layout stakes and surveying (623E10000) | LS | 1 | $13,670 | $33,000 | $20,000 | $2,300.00 |
| 122 | Mobilization (624E10000) | LS | 1 | $53,836 | $100,000 | $100,000 | $300,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of December 18, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.