ODOT letting results, March 30, 2023
30 contracts let by Ohio DOT on March 30, 2023, $40,736,433 in low bids, a median of 3 bidders per contract. On the 30 with an engineer's estimate, the low bid came in under it 15 times; median low bid -1.0% against the estimate.
- Owner
- Ohio DOT
- Contracts
- 30
- Low bids, total
- $40,736,433
- Data through
- 12 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 230192 | MRG-SR 377-00.00 and Various (TWO LANE RESURFACING) | MRG | 1 | Shelly & Sands Inc | $5,825,256 | +5.0% | ODOT | ||
| 230178 | CUY-SR 14-10.05 (MINOR RECONSTRUCTION) | CUY | 3 of 4 | Shelly Company | $3,047,273 | $3,302,606 | +8.0% | 0.0% | ODOT |
| 230167 | D03-PM FY2023 (PAVEMENT MARKING) | District 3 | 2 | Oglesby Construction Inc | $2,850,485 | $2,882,229 | +1.0% | +4.0% | ODOT |
| 230179 | CUY-SR 17-12.16 Major Rehab (MINOR RECONSTRUCTION) | CUY | 4 | Anthony Allega Cement Contractor Inc | $2,840,698 | $3,408,666 | +20% | -14% | ODOT |
| 230120 | HAM-CR 23-01.42 (BRIDGE REPAIR) | HAM | 2 | Sunesis Construction Co | $2,670,680 | $3,142,066 | +18% | +26% | ODOT |
| 230176 | BUT-US 27-00.80 (BRIDGE REPAIR) | BUT | 6 | John R Jurgensen Company | $2,576,601 | $2,885,773 | +12% | +13% | ODOT |
| 230182 | D08-Bridge Maintenance FY2023 (BRIDGE REPAIR) | District 8 | 3 | Becdir Construction Company | $2,341,108 | $2,497,302 | +7.0% | -42% | ODOT |
| 230198 | D04-PM FY2023 (West) (PAVEMENT MARKING) | District 4 | 2 | Dura Mark Inc | $2,240,000 | $2,943,809 | +31% | -3.0% | ODOT |
| 230201 | D08-TSG-FY2023/FY2024 (SIGNALIZATION) | District 8 | 2 | Bansal Construction Inc | $1,938,761 | $2,104,390 | +9.0% | +2.0% | ODOT |
| 230188 | JEF-SR 7-15.74 (BRIDGE REPLACEMENT (1 BRIDGE)) | JEF | 1 | Shelly & Sands Inc | $1,839,093 | +16% | ODOT | ||
| 230187 | JEF-Alexander Street Bridge (BRIDGE REPLACEMENT (1 BRIDGE)) | JEF | 3 | Apbn Inc | $1,154,600 | $1,272,864 | +10% | +17% | ODOT |
| 230199 | D04-SIGN FY2023 (Systematic) (SIGNING) | District 4 | 2 | Lake Erie Construction Company | $1,075,350 | $1,108,552 | +3.0% | -14% | ODOT |
| 230189 | MIA-East Main St Resurfacing (TWO LANE RESURFACING) | MIA | 1 | Walls Bros Asphalt Co Inc | $979,235 | +6.0% | ODOT | ||
| 230183 | GRE-SR 725-01.91 (BRIDGE REPAIR) | GRE | 5 | Double Z Construction Company | $949,981 | $969,914 | +2.0% | +18% | ODOT |
| 234012 | CAR-SR 43-03.91 (BRIDGE REPLACEMENT (1 BRIDGE)) | CAR | 3 | BCC Ohio Inc | $828,133 | $886,522 | +7.0% | +3.0% | ODOT |
| 230177 | CUY-Monticello Blvd Signals (SIGNALIZATION) | CUY | 4 | Miller Cable Company | $827,000 | $875,500 | +6.0% | +8.0% | ODOT |
| 230181 | D07-CHIP-FY23 (B) (CHIP SEAL) | District 7 | 5 | Henry W Bergman Inc | $717,721 | $744,826 | +4.0% | -14% | ODOT |
| 230185 | HIG-SR 41-07.67 (TWO LANE RESURFACING) | HIG | 2 | Cox Paving LLC | $710,519 | $728,580 | +3.0% | +1.0% | ODOT |
| 230190 | MOE-TR 307-00.72 (BRIDGE REPLACEMENT (1 BRIDGE)) | MOE | 4 | Black Horse Bridge Construction Inc | $704,854 | $809,228 | +15% | +5.0% | ODOT |
| 230194 | RIC-US 30-18.10 (MISCELLANEOUS) | RIC | 2 | Shelly & Sands Inc | $695,116 | $799,254 | +15% | +6.0% | ODOT |
| 230205 | WAS-SR 676-02.50 (SLIDE REPAIR) | WAS | 4 | Alan Stone Co Inc | $579,896 | $608,419 | +5.0% | -15% | ODOT |
| 230184 | HIG-SR 134-07.82 (CULVERT REPLACEMENT) | HIG | 7 | Axis Civil Construction LLC | $497,105 | $544,427 | +10% | -22% | ODOT |
| 230196 | WAR-SR 123-30.65 (MINOR RECONSTRUCTION) | WAR | 2 | Barrett Paving Materials Inc | $489,584 | $548,165 | +12% | -6.0% | ODOT |
| 230193 | PIK-SR 772-02.09 (CHIP SEAL) | PIK | 4 | SC Construction & Materials LLC | $484,589 | $510,963 | +5.0% | -1.0% | ODOT |
| 230186 | HIG-SR 753-12.00 (CULVERT REPLACEMENT) | HIG | 7 | D G M Inc | $474,520 | $482,388 | +2.0% | -8.0% | ODOT |
| 230202 | MED-SR 606-00.00 (CHIP SEAL) | MED | 3 | Henry W Bergman Inc | $358,811 | $397,665 | +11% | -10% | ODOT |
| 230195 | TRU-Ellsworth-Bailey Rd (TWO LANE RESURFACING) | TRU | 6 | Shelly & Sands Inc | $356,251 | $359,183 | +1.0% | -21% | ODOT |
| 230200 | D05-FY 2023 School Flasher (SIGNALIZATION) | District 5 | 4 | Miller Cable Company | $302,500 | $311,550 | +3.0% | -3.0% | ODOT |
| 230204 | WAS-SR 530-05.04 (CULVERT REPLACEMENT) | WAS | 5 | MC Connell Contracting Inc | $291,974 | $340,493 | +17% | -12% | ODOT |
| 230197 | CLA-US 68-11.47 (BRIDGE REPAIR) | CLA | 1 | Evers Steel Construction LLC | $88,740 | -23% | ODOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out.