ODOT contract 250588 bid tabulation

LAK-US 20-17.13 (FOUR LANE RESURFACING). Let by Ohio DOT on December 18, 2025, LAK. 6 bids received; low bid $900,574 by Ronyak Paving Inc, +0.8% against the engineer's estimate of $893,000.

Owner
Ohio DOT
Letting
18 DEC 2025
Pay items
62
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Ronyak Paving Inc$900,574Low+1.0%
2Geauga Highway Co$970,902+8.0%+9.0%
3Phillips Paving LLC$1,041,792+16%+17%
4Karvo Companies Inc$1,094,578+22%+23%
5Shelly Company$1,115,641+24%+25%
6Barbicas Construction Company Inc$1,196,476+33%+34%
ODOT contract 250588: bids by rank

Engineer's estimate: $893,000.

Bid tabulation

LinePay itemUnitQuantity1. Ronyak Paving Inc2. Geauga Highway Co3. Phillips Paving LLC4. Karvo Companies Inc5. Shelly Company6. Barbicas Construction Company Inc
1Walk removed (202E30000)SF1,736$5.00$2.50$10.00$10.00$10.00$3.00
2Curb removed (202E32000)FT196$8.00$12.50$15.00$35.00$20.00$7.50
34" concrete walk (608E10000)SF307$12.00$12.50$20.00$12.00$35.00$22.00
4Curb ramp, as per plan (608E52001)SF1,408$25.00$20.00$20.00$15.00$25.00$30.00
5Monument assembly adjusted to grade, as per plan (623E39501)EACH2$1,585.00$650.00$1,000.00$1,000.00$1,300.00$900.00
6Monument assembly reconstructed to grade, as per plan (623E39601)EACH1$2,000.00$800.00$2,500.00$2,000.00$1,500.00$1,100.00
7Erosion control (832E30000)EACH1,000$1.00$1.00$1.00$1.00$1.00$1.00
8Catch basin adjusted to grade, as per plan (611E98631)EACH4$1,600.00$1,250.00$1,500.00$1,500.00$2,000.00$1,800.00
9Catch basin reconstructed to grade (611E98634)EACH1$2,050.00$1,800.00$3,000.00$2,000.00$2,200.00$2,300.00
10Inlet adjusted to grade, as per plan (611E99151)EACH2$1,600.00$1,150.00$1,500.00$2,500.00$1,300.00$3,500.00
11Inlet reconstructed to grade (611E99154)EACH1$2,050.00$1,800.00$3,000.00$3,000.00$1,500.00$4,500.00
12Manhole adjusted to grade, as per plan (611E99655)EACH2$1,600.00$1,150.00$1,500.00$1,500.00$2,000.00$1,300.00
13Special - miscellaneous metal (611E99820)LB2,000$5.00$2.50$5.00$3.00$5.75$2.80
14Partial depth pavement repair (441) (251E01000)SY550$135.00$67.00$80.00$85.00$75.00$44.00
15Pavement repair, as per plan (253E02001)CY25$500.00$450.00$1,000.00$700.00$375.00$420.00
16Non-tracking tack coat (407E20000)GAL5,119$2.00$3.75$2.00$2.25$3.00$3.10
17Fine graded polymer asphalt concrete, type B, (448) (424E14000)CY1,540$240.00$274.00$250.00$265.00$285.00$321.00
18Asphalt concrete surface course, type 1, (449), as per plan (441E70101)CY41$500.00$240.00$600.00$575.00$700.00$492.00
19Curb, type 6 (609E26000)FT210$60.00$60.00$30.00$55.00$65.00$45.00
20Longitudinal joint adhesive (875E10000)LB3,589$3.00$2.30$2.00$1.00$2.50$3.80
21Pavement planing, asphalt concrete, class A, (1.0" (897E01010)SY56,882$1.50$3.15$2.00$1.60$2.00$3.20
22Valve box adjusted to grade, as per plan (638E10801)EACH3$825.00$650.00$1,000.00$1,000.00$1,000.00$880.85
23RPM (621E00100)EACH420$40.00$60.00$36.00$39.98$40.00$51.50
24Raised pavement marker removed (621E54000)EACH315$1.00$15.00$1.00$1.00$6.00$12.00
25Edge line, 6" (646E10010)MI0.22$3,760.00$3,750.00$3,050.00$3,760.00$3,760.00$3,750.00
26Lane line, 6" (646E10110)MI3.52$2,100.00$1,650.00$1,625.00$2,100.00$2,100.00$1,650.00
27Center line (646E10200)MI2.61$4,300.00$4,000.00$3,750.00$4,300.00$4,300.00$4,000.00
28Channelizing line, 8" (646E10300)FT595$1.66$2.25$1.65$1.66$1.70$2.25
29Stop line (646E10400)FT387$12.50$10.00$12.50$12.50$12.50$10.00
30Crosswalk line, 12" (646E10510)FT910$5.85$4.50$6.50$5.85$5.85$4.50
31Transverse/diagonal line (646E10600)FT962$8.00$8.00$9.35$8.00$8.00$8.00
32Island marking (646E10800)SF105$8.00$7.50$6.00$8.00$8.00$7.50
33Lane arrow (646E20300)EACH16$160.00$175.00$160.00$160.00$160.00$175.00
34Special - inventory existing pavement markings (690E98400)LS1$1,000.00$2,000.00$2,645.00$1,000.00$1,000.00$250.00
35Detector loop, as per plan (632E26501)EACH20$1,450.00$1,550.00$1,450.00$1,450.00$1,450.00$1,450.00
36Law enforcement officer with patrol car for assistance (614E11110)HR80$125.00$100.00$125.00$125.00$120.00$80.00
37Asphalt concrete for maintaining traffic (614E13000)CY10$120.00$100.00$300.00$100.00$115.00$320.00
38Portable changeable message sign, as per plan (614E18601)SNMT8$900.00$900.00$1,225.95$1,000.00$900.00$900.00
39Work zone lane line, class I, 6", 642 paint (614E20110)MI3.52$675.00$575.00$315.00$675.00$675.00$575.00
40Work zone lane line, class III, 6", 642 paint (614E20560)MI3.52$674.00$575.00$160.00$674.00$675.00$575.00
41Work zone center line, class I, 642 paint (614E21100)MI2.61$1,110.00$1,250.00$890.00$1,110.00$1,110.00$1,250.00
42Work zone center line, class III, 642 paint (614E21550)MI2.61$1,100.00$1,250.00$515.00$1,100.00$1,100.00$1,250.00
43Work zone edge line, class I, 6", 642 paint (614E22110)MI0.22$800.00$1,000.00$765.00$800.00$800.00$1,000.00
44Work zone edge line, class III, 6", 642 paint (614E22360)MI0.22$700.00$1,000.00$435.00$700.00$700.00$1,000.00
45Work zone channelizing line, class I, 8", 642 paint (614E23200)FT595$0.70$0.60$0.55$0.70$0.70$0.60
46Work zone channelizing line, class III, 8", 642 paint (614E23680)FT595$0.60$0.60$0.50$0.60$0.60$0.60
47Work zone transverse/diagonal line, class I, 642 paint (614E25200)FT962$0.50$3.50$3.25$0.50$0.50$3.50
48Work zone transverse/diagonal line, class III, 642 paint (614E25620)FT962$0.49$3.50$3.20$0.49$0.50$3.50
49Work zone stop line, class I, 642 paint (614E26200)FT387$3.00$3.50$3.50$3.00$3.00$3.50
50Work zone stop line, class III, 642 paint (614E26610)FT387$3.00$3.50$3.45$3.00$3.00$3.50
51Work zone crosswalk line, class I, 12", 642 paint (614E27050)FT910$1.45$2.50$3.00$1.45$1.45$2.50
52Work zone crosswalk line, class III, 12", 642 paint (614E27250)FT910$1.45$2.50$2.95$1.45$1.45$2.50
53Work zone arrow, class I, 642 paint (614E30200)EACH16$45.00$50.00$55.00$45.00$45.00$50.00
54Work zone arrow, class III, 642 paint (614E30650)EACH16$44.00$50.00$50.00$44.00$45.00$50.00
55Work zone island marking, class I (614E32700)SF105$1.00$3.00$3.00$1.00$1.00$3.00
56Work zone island marking, class III, 642 paint (614E32800)SF105$1.00$3.00$2.95$1.00$1.00$3.00
57Signing, misc.: additional signs, ground mounted, (630E97800)SF300$25.00$25.00$27.95$25.00$25.00$25.00
58Premium for contract performance bond and for payment bond (103E05000)LS1$6,399.64$9,000.00$20,000$15,000$5,000.00$12,000
59Maintaining traffic (614E11000)LS1$40,000$35,000$95,000$100,000$130,500$75,000
60Field office, type B, as per plan (619E16011)MNTH6$1,500.00$1,000.00$2,500.00$3,500.00$2,500.00$1,800.00
61Construction layout stakes and surveying, as per plan (623E10001)LS1$5,050.00$2,500.00$6,400.00$3,500.00$5,000.00$2,500.00
62Mobilization (624E10000)LS1$25,800$5,000.00$57,000$125,000$50,000$90,000
ODOT contract 250588: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of December 18, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy