ODOT contract 250584 bid tabulation
D05-Guardrail FY2026 (GUARDRAIL REBUILDING). Let by Ohio DOT on December 18, 2025, District 5. 2 bids received; low bid $2,887,120 by Lake Erie Construction Company, +2.6% against the engineer's estimate of $2,814,000.
- Owner
- Ohio DOT
- Letting
- 18 DEC 2025
- Pay items
- 41
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Lake Erie Construction Company | $2,887,120 | Low | +3.0% |
| 2 | M P Dory Co | $2,994,927 | +4.0% | +6.0% |
Engineer's estimate: $2,814,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Lake Erie Construction Company | 2. M P Dory Co |
|---|---|---|---|---|---|
| 1 | Guardrail removed (202E38000) | FT | 30,932 | $1.60 | $1.80 |
| 2 | Guardrail removed, as per plan (202E38001) | FT | 12,601 | $2.80 | $2.00 |
| 3 | Bridge railing removed (202E38500) | FT | 282 | $3.50 | $5.00 |
| 4 | Anchor assembly removed, type A (202E42000) | EACH | 148 | $345.00 | $280.00 |
| 5 | Anchor assembly removed, type E (202E42010) | EACH | 61 | $175.00 | $150.00 |
| 6 | Anchor assembly removed, type T (202E42040) | EACH | 57 | $100.00 | $100.00 |
| 7 | Anchor assembly removed, type B (202E42050) | EACH | 2 | $160.00 | $100.00 |
| 8 | Bridge terminal assembly removed (202E47000) | EACH | 46 | $80.00 | $85.00 |
| 9 | Guardrail, type MGS with long posts (606E15100) | FT | 53,764 | $24.00 | $24.00 |
| 10 | Guardrail rebuilt, as per plan (606E16001) | FT | 1,425 | $16.00 | $10.00 |
| 11 | Guardrail, type MGS, long-span (606E17360) | FT | 632 | $24.50 | $21.00 |
| 12 | Guardrail post, steel, as per plan (606E19001) | EACH | 5,500 | $10.00 | $12.00 |
| 13 | Guardrail post, steel, as per plan (606E19001) | EACH | 60 | $95.00 | $85.00 |
| 14 | Anchor assembly, MGS type A (606E25550) | EACH | 9 | $1,620.00 | $1,450.00 |
| 15 | Anchor assembly, MGS type E (606E26150) | EACH | 142 | $2,550.00 | $2,300.00 |
| 16 | Anchor assembly, MGS type T (606E26550) | EACH | 100 | $1,325.00 | $1,000.00 |
| 17 | MGS bridge terminal assembly, type TST-2 (606E34600) | EACH | 12 | $2,475.00 | $2,250.00 |
| 18 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 4 | $2,550.00 | $2,250.00 |
| 19 | Bridge terminal assembly, type 4 (606E35140) | EACH | 30 | $1,000.00 | $800.00 |
| 20 | Special - reshaping berm (606E50000) | FT | 54,435 | $0.20 | $0.50 |
| 21 | Guardrail, misc.: existing W-beam for shoulder SU (606E98000) | FT | 125 | $19.60 | $10.00 |
| 22 | Guardrail, misc.: shoulder support benching (606E98000) | FT | 12,601 | $7.00 | $6.75 |
| 23 | Ground rod (625E32000) | EACH | 3 | $320.00 | $500.00 |
| 24 | Special - mailbox removed and reset (690E50350) | EACH | 40 | $75.00 | $45.00 |
| 25 | Granular material, type B, as per plan (203E35111) | CY | 5,528 | $50.00 | $90.00 |
| 26 | Granular material, type B, as per plan (203E35111) | CY | 1,865 | $50.00 | $80.00 |
| 27 | Geotextile fabric, as per plan (204E50001) | SY | 2,798 | $2.50 | $2.00 |
| 28 | Seeding and mulching, class 2 (659E00510) | SY | 11,215 | $1.00 | $0.50 |
| 29 | Commercial fertilizer (659E20000) | TON | 1.52 | $275.00 | $1,250.00 |
| 30 | Lime (659E31000) | ACRE | 2.32 | $50.00 | $150.00 |
| 31 | Water (659E35000) | MGAL | 61 | $1.00 | $1.00 |
| 32 | Slope erosion protection (670E00500) | SY | 14,245 | $2.00 | $1.50 |
| 33 | Erosion control (832E30000) | EACH | 3,000 | $1.00 | $1.00 |
| 34 | Barrier reflector, type 2 , BI-directional (626E00110) | EACH | 1,025 | $10.00 | $10.00 |
| 35 | Ground mounted support, no. 3 post (630E03100) | FT | 3,075 | $10.00 | $8.00 |
| 36 | Removal of ground mounted sign and reerection (630E85100) | EACH | 208 | $50.00 | $35.00 |
| 37 | Removal of ground mounted post support and disposal (630E86002) | EACH | 205 | $15.00 | $15.00 |
| 38 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $14,600 | $25,000 |
| 39 | Maintaining traffic (614E11000) | LS | 1 | $44,500 | $5,000.00 |
| 40 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $27,500 | $22,000 |
| 41 | Mobilization (624E10000) | LS | 1 | $95,000 | $65,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of December 18, 2025. Compiled by Mirage Metrics.