ODOT contract 250610 bid tabulation
CUY-IR 77-15.46/VAR Decks (BRIDGE REPAIR). Let by Ohio DOT on December 18, 2025, CUY. 5 bids received; low bid $25,286,681 by Great Lakes Construction Co, +12% against the engineer's estimate of $22,500,000.
- Owner
- Ohio DOT
- Letting
- 18 DEC 2025
- Pay items
- 320
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Great Lakes Construction Co | $25,286,681 | Low | +12% |
| 2 | Ruhlin Company | $26,571,061 | +5.0% | +18% |
| 3 | Beaver Excavating Company | $27,173,281 | +7.0% | +21% |
| 4 | Perk Company Inc Catts Construction Inc Joint Venture | $29,109,076 | +15% | +29% |
| 5 | Kenmore Construction Co Inc | $29,383,106 | +16% | +31% |
Engineer's estimate: $22,500,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Great Lakes Construction Co | 2. Ruhlin Company | 3. Beaver Excavating Company | 4. Perk Company Inc Catts Construction Inc Joint Venture | 5. Kenmore Construction Co Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $31,000 | $95,000 | $80,000 | $21,735 | $15,000 |
| 2 | Pavement removed (202E23000) | SY | 6,702 | $22.00 | $26.00 | $27.50 | $21.00 | $25.00 |
| 3 | Walk removed (202E30000) | SF | 1,924 | $2.25 | $3.25 | $6.50 | $2.25 | $3.00 |
| 4 | Concrete barrier removed (202E30700) | FT | 658 | $42.00 | $41.00 | $40.00 | $328.00 | $25.00 |
| 5 | Curb removed (202E32000) | FT | 1,276 | $8.00 | $3.25 | $5.75 | $13.75 | $3.00 |
| 6 | Gutter removed (202E32600) | FT | 25 | $27.00 | $8.50 | $10.50 | $42.00 | $30.00 |
| 7 | Concrete slope protection removed (202E32800) | SY | 108 | $52.00 | $30.00 | $65.00 | $18.00 | $18.00 |
| 8 | Pipe removed, 24" and under (202E35100) | FT | 87 | $70.00 | $150.00 | $70.00 | $21.00 | $120.00 |
| 9 | Guardrail removed (202E38000) | FT | 2,555 | $3.00 | $3.00 | $2.00 | $2.50 | $2.00 |
| 10 | Inlet removed (202E58200) | EACH | 2 | $690.00 | $1,600.00 | $1,000.00 | $968.00 | $750.00 |
| 11 | Special - fill and plug existing conduit (202E70000) | FT | 73 | $14.00 | $100.00 | $25.00 | $90.00 | $30.00 |
| 12 | Special - pipe cleanout, 24" and under (202E70110) | FT | 600 | $18.50 | $85.00 | $24.00 | $63.00 | $140.00 |
| 13 | Excavation (203E10000) | CY | 2,843 | $50.00 | $35.00 | $52.50 | $42.00 | $43.00 |
| 14 | Embankment (203E20000) | CY | 787 | $24.00 | $40.00 | $67.50 | $36.00 | $25.00 |
| 15 | Subgrade compaction (204E10000) | SY | 7,996 | $2.00 | $4.00 | $5.75 | $1.00 | $3.00 |
| 16 | Excavation of subgrade (204E13000) | CY | 100 | $52.15 | $39.00 | $48.00 | $44.45 | $60.00 |
| 17 | Granular material, type B (204E30010) | CY | 100 | $70.00 | $77.00 | $75.00 | $109.75 | $80.00 |
| 18 | Proof rolling (204E45000) | HR | 4 | $400.00 | $930.00 | $1,000.00 | $400.00 | $250.00 |
| 19 | Geotextile fabric (204E50000) | SY | 1,000 | $2.25 | $1.07 | $3.00 | $3.00 | $5.00 |
| 20 | Ditch cleanout, as per plan (209E10001) | FT | 300 | $24.00 | $44.00 | $20.00 | $13.00 | $75.00 |
| 21 | Reshaping under guardrail, as per plan (209E15001) | STA | 24 | $125.00 | $650.00 | $95.00 | $153.00 | $500.00 |
| 22 | Linear grading, as per plan (209E60201) | STA | 29 | $290.00 | $300.00 | $420.00 | $1,655.00 | $300.00 |
| 23 | Guardrail, type MGS (606E15050) | FT | 2,207 | $21.50 | $21.50 | $21.60 | $25.00 | $21.50 |
| 24 | Anchor assembly, MGS type T (606E26550) | EACH | 1 | $1,350.00 | $1,350.00 | $1,450.00 | $1,673.00 | $1,450.00 |
| 25 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 8 | $2,550.00 | $2,550.00 | $2,865.00 | $3,306.00 | $2,865.00 |
| 26 | MGS bridge terminal assembly, type 2 (606E35102) | EACH | 8 | $875.00 | $875.00 | $580.00 | $670.00 | $580.00 |
| 27 | Fence, misc.: remove and reerect (607E98000) | FT | 100 | $88.75 | $88.75 | $59.60 | $73.00 | $70.50 |
| 28 | 4" concrete walk (608E10000) | SF | 1,895 | $16.00 | $9.00 | $14.00 | $10.00 | $9.00 |
| 29 | Concrete barrier, single slope, type C1 (622E10140) | FT | 303 | $360.00 | $250.00 | $650.00 | $350.00 | $630.00 |
| 30 | Concrete barrier, single slope, type D, as per plan (622E10161) | FT | 40 | $360.00 | $400.00 | $230.00 | $367.00 | $350.00 |
| 31 | Barrier transition (622E10200) | EACH | 4 | $9,030.00 | $7,600.00 | $12,500 | $7,706.00 | $8,000.00 |
| 32 | Barrier transition, as per plan (622E10201) | EACH | 1 | $10,000 | $7,800.00 | $12,500 | $9,776.00 | $13,000 |
| 33 | Concrete barrier end section, type D (622E25000) | EACH | 4 | $5,900.00 | $5,100.00 | $5,500.00 | $10,125 | $5,200.00 |
| 34 | Concrete barrier, end anchorage, reinforced, type C1 (622E25014) | EACH | 6 | $6,950.00 | $6,500.00 | $10,000 | $10,150 | $8,300.00 |
| 35 | Concrete barrier, end anchorage, reinforced, type C1, as per plan (622E25015) | EACH | 2 | $7,500.00 | $11,500 | $10,000 | $12,500 | $12,000 |
| 36 | Barrier, misc.: temporary median barrier transitio (622E90200) | EACH | 3 | $6,600.00 | $5,900.00 | $5,650.00 | $10,775 | $7,000.00 |
| 37 | Monument assembly adjusted to grade (623E39500) | EACH | 5 | $275.00 | $450.00 | $400.00 | $775.00 | $700.00 |
| 38 | Right-of-way monument, type B (623E40520) | EACH | 5 | $200.00 | $275.00 | $800.00 | $688.00 | $700.00 |
| 39 | Concrete slope protection, as per plan (601E21001) | SY | 3,362 | $85.00 | $135.00 | $120.00 | $89.00 | $87.00 |
| 40 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 21 | $135.00 | $215.00 | $245.00 | $95.00 | $130.00 |
| 41 | Tied concrete block mat with type 2 underlayment (601E21060) | SY | 68 | $83.00 | $105.00 | $100.00 | $95.00 | $115.00 |
| 42 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 18 | $215.00 | $250.00 | $245.00 | $476.00 | $325.00 |
| 43 | Soil analysis test (659E00100) | EACH | 2 | $400.00 | $400.00 | $400.00 | $200.00 | $50.00 |
| 44 | Topsoil (659E00300) | CY | 688 | $59.00 | $59.00 | $45.00 | $72.00 | $48.00 |
| 45 | Seeding and mulching (659E10000) | SY | 6,196 | $0.95 | $0.95 | $0.95 | $1.25 | $3.00 |
| 46 | Repair seeding and mulching (659E14000) | SY | 310 | $2.00 | $2.00 | $2.00 | $1.00 | $3.00 |
| 47 | Inter-seeding (659E15000) | SY | 310 | $0.10 | $0.01 | $0.01 | $1.00 | $0.50 |
| 48 | Commercial fertilizer (659E20000) | TON | 0.84 | $1,500.00 | $1,500.00 | $1,500.00 | $500.00 | $250.00 |
| 49 | Lime (659E31000) | ACRE | 1.28 | $1.00 | $135.00 | $0.01 | $100.00 | $25.00 |
| 50 | Water (659E35000) | MGAL | 35 | $60.00 | $60.00 | $60.00 | $46.00 | $10.00 |
| 51 | Slope erosion protection, as per plan (670E00501) | SY | 2,826 | $4.00 | $4.00 | $4.00 | $1.75 | $2.00 |
| 52 | Erosion control (832E30000) | EACH | 100,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 53 | Seeding and erosion control with turf reinforcing mat, type 1 (836E10000) | SY | 32 | $15.00 | $15.00 | $15.00 | $6.00 | $5.00 |
| 54 | Concrete masonry (602E20000) | CY | 1.10 | $2,500.00 | $2,600.00 | $2,900.00 | $2,645.00 | $4,000.00 |
| 55 | 6" shallow pipe underdrains with geotextile fabric (605E11110) | FT | 971 | $32.75 | $37.00 | $29.00 | $21.00 | $22.00 |
| 56 | 6" unclassified pipe underdrains with geotextile fabric (605E13410) | FT | 1,390 | $33.75 | $30.00 | $32.00 | $21.00 | $25.00 |
| 57 | 6" base pipe underdrains with geotextile fabric (605E14020) | FT | 627 | $23.00 | $23.00 | $37.00 | $24.00 | $20.00 |
| 58 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 281 | $39.00 | $48.00 | $46.00 | $24.50 | $50.00 |
| 59 | 6" conduit, type B (611E00900) | FT | 382 | $46.00 | $34.00 | $50.00 | $31.00 | $45.00 |
| 60 | 6" conduit, type F (611E01500) | FT | 50 | $40.00 | $66.00 | $50.00 | $24.50 | $50.00 |
| 61 | 12" conduit, type B (611E04400) | FT | 4 | $310.00 | $550.00 | $870.00 | $695.00 | $550.00 |
| 62 | 12" conduit, type B, as per plan (611E04401) | FT | 34 | $495.00 | $505.00 | $260.00 | $323.50 | $485.00 |
| 63 | 12" conduit, type C (611E04600) | FT | 8 | $435.00 | $430.00 | $635.00 | $610.75 | $475.00 |
| 64 | 15" conduit, type B (611E05900) | FT | 49 | $240.00 | $265.00 | $150.00 | $304.50 | $300.00 |
| 65 | 15" conduit, type C (611E06100) | FT | 52 | $165.00 | $158.00 | $160.00 | $271.50 | $200.00 |
| 66 | 15" conduit, type F (611E06700) | FT | 259 | $125.00 | $83.00 | $95.00 | $245.00 | $120.00 |
| 67 | Conduit, bored or jacked (6", type B) (611E96600) | FT | 184 | $450.00 | $981.00 | $1,100.00 | $945.00 | $140.00 |
| 68 | Catch basin, no. 3A (611E98180) | EACH | 5 | $6,000.00 | $4,000.00 | $4,400.00 | $7,015.00 | $3,000.00 |
| 69 | Catch basin adjusted to grade (611E98630) | EACH | 3 | $715.00 | $2,150.00 | $1,130.00 | $1,137.00 | $500.00 |
| 70 | Inlet, no. 3 for single slope barrier, type C1 (611E99110) | EACH | 1 | $22,000 | $14,000 | $21,500 | $22,722 | $14,000 |
| 71 | Inlet adjusted to grade (611E99150) | EACH | 1 | $845.00 | $2,300.00 | $2,000.00 | $1,210.00 | $500.00 |
| 72 | Inlet adjusted to grade, as per plan (611E99151) | EACH | 1 | $1,040.00 | $11,000 | $6,000.00 | $9,223.00 | $500.00 |
| 73 | Manhole, no. 3, as per plan (611E99575) | EACH | 1 | $13,050 | $8,000.00 | $14,000 | $15,845 | $4,000.00 |
| 74 | Manhole adjusted to grade (611E99654) | EACH | 1 | $900.00 | $2,150.00 | $1,100.00 | $1,000.00 | $600.00 |
| 75 | Precast reinforced concrete outlet (611E99710) | EACH | 11 | $420.00 | $525.00 | $460.00 | $212.00 | $380.00 |
| 76 | Special - miscellaneous metal (611E99820) | LB | 5,000 | $2.00 | $2.25 | $4.00 | $2.30 | $3.00 |
| 77 | Partial depth pavement repair (441) (251E01010) | CY | 685 | $490.00 | $490.00 | $1,050.00 | $350.00 | $600.00 |
| 78 | Pavement repair (253E02000) | CY | 100 | $1,100.00 | $1,100.00 | $750.00 | $1,000.00 | $800.00 |
| 79 | Pavement planing, asphalt concrete (thickness = 1 (254E01000) | SY | 4,179 | $13.50 | $13.50 | $12.50 | $15.50 | $14.00 |
| 80 | Pavement planing, asphalt concrete (variable thick (254E01000) | SY | 14,928 | $4.00 | $4.00 | $8.75 | $7.00 | $6.00 |
| 81 | Full depth pavement removal and rigid replacement, type 1, class QC RS, as per plan (255E19001) | SY | 1,232 | $195.00 | $263.62 | $450.00 | $195.00 | $215.00 |
| 82 | Full depth pavement removal and rigid replacement, type 1, class QC RS, as per plan (255E19001) | SY | 1,232 | $192.00 | $199.79 | $325.00 | $180.00 | $225.00 |
| 83 | Full depth pavement sawing (255E20000) | FT | 8,448 | $4.00 | $3.00 | $2.75 | $4.00 | $3.00 |
| 84 | Asphalt concrete base, PG64-22, (449) (302E56000) | CY | 1,957 | $295.00 | $295.00 | $285.00 | $340.00 | $330.00 |
| 85 | Aggregate base (304E20000) | CY | 1,573 | $97.00 | $100.00 | $97.00 | $87.00 | $92.00 |
| 86 | Non-tracking tack coat (407E20000) | GAL | 3,682 | $3.02 | $3.02 | $2.50 | $3.50 | $6.00 |
| 87 | Asphalt concrete intermediate course, type 1, (449), (under guardrail), as per plan (441E70801) | CY | 77 | $925.00 | $925.00 | $350.00 | $1,067.00 | $1,000.00 |
| 88 | Asphalt concrete surface course, 12.5 MM, type A (446), as per plan (442E10001) | CY | 868 | $460.00 | $460.00 | $450.00 | $530.00 | $355.00 |
| 89 | Asphalt concrete intermediate course, 12.5 MM, type A (446) (442E10080) | CY | 287 | $525.00 | $525.00 | $480.00 | $605.00 | $445.00 |
| 90 | Asphalt concrete surface course, 12.5 MM, type A (449), as per plan (442E22101) | CY | 78 | $725.00 | $725.00 | $560.00 | $835.00 | $565.00 |
| 91 | Curb, type 4-C (609E24510) | FT | 182 | $125.00 | $50.00 | $44.00 | $52.00 | $35.00 |
| 92 | Curb, type 6 (609E26000) | FT | 1,101 | $97.00 | $38.00 | $41.00 | $33.00 | $38.00 |
| 93 | Compacted aggregate, as per plan (617E10101) | CY | 133 | $190.00 | $190.00 | $245.00 | $219.00 | $200.00 |
| 94 | Rumble strips, transverse (asphalt concrete) (618E39000) | EACH | 9 | $834.00 | $2,500.00 | $1,250.00 | $577.00 | $725.00 |
| 95 | Rumble strips, shoulder (asphalt concrete) (618E40600) | MI | 1.82 | $7,150.00 | $7,150.00 | $7,150.00 | $8,251.00 | $7,150.00 |
| 96 | Connection, unfused permanent (625E00480) | EACH | 15 | $125.00 | $185.00 | $125.00 | $127.00 | $125.00 |
| 97 | No. 4 AWG 2400 volt distribution cable (625E23200) | FT | 1,281 | $4.25 | $3.75 | $4.25 | $4.00 | $4.00 |
| 98 | Conduit, 2", 725.04 (625E25400) | FT | 362 | $26.00 | $25.50 | $26.00 | $26.00 | $26.00 |
| 99 | Luminaire, underpass, solid state (LED), as per plan (625E27503) | EACH | 28 | $875.00 | $1,000.00 | $875.00 | $1,331.00 | $875.00 |
| 100 | Trench, 24" deep (625E29002) | FT | 20 | $20.00 | $17.00 | $20.00 | $15.00 | $20.00 |
| 101 | Junction box (625E29900) | EACH | 7 | $1,250.00 | $1,400.00 | $1,250.00 | $2,668.00 | $1,250.00 |
| 102 | Pull box, 725.08, 24" (625E30706) | EACH | 1 | $1,351.00 | $1,750.00 | $1,351.00 | $1,384.00 | $1,351.00 |
| 103 | Pull box removed (625E31510) | EACH | 3 | $250.00 | $332.00 | $250.00 | $403.00 | $250.00 |
| 104 | Structure grounding system (625E33000) | EACH | 6 | $7,250.00 | $13,500 | $7,250.00 | $11,141 | $7,250.00 |
| 105 | Power service, as per plan (625E34001) | EACH | 3 | $10,535 | $11,000 | $15,000 | $10,152 | $10,535 |
| 106 | Service to underpass lighting, as per plan (625E37101) | EACH | 3 | $10,750 | $21,000 | $10,750 | $64,476 | $10,750 |
| 107 | Special - maintain existing lighting (625E40004) | EACH | 3 | $17,500 | $15,000 | $17,500 | $28,329 | $17,500 |
| 108 | Power service removed, as per plan (625E75511) | EACH | 3 | $600.00 | $1,300.00 | $600.00 | $836.00 | $600.00 |
| 109 | Disconnect circuit (625E75800) | EACH | 3 | $75.00 | $190.00 | $75.00 | $346.00 | $75.00 |
| 110 | Arc flash calculations and label (CC-1, CC-2 & CC- (625E76000) | EACH | 3 | $3,450.00 | $825.00 | $3,450.00 | $1,731.00 | $3,450.00 |
| 111 | Lighting, misc.: disconnect switch (625E98000) | EACH | 1 | $1,600.00 | $1,850.00 | $1,600.00 | $2,729.00 | $1,600.00 |
| 112 | Lighting, misc.: HL-40.20 solar radiation shield (625E98000) | EACH | 3 | $850.00 | $1,250.00 | $850.00 | $1,980.00 | $850.00 |
| 113 | Lighting, misc.: removal of underpass lighting ins (625E98000) | EACH | 3 | $3,750.00 | $3,250.00 | $3,750.00 | $2,193.00 | $3,750.00 |
| 114 | Service cable, 3 conductor, with ground, no. 4 AWG (632E69910) | FT | 730 | $15.00 | $11.00 | $15.00 | $20.50 | $15.00 |
| 115 | Delineator, post ground mounted (620E00500) | EACH | 10 | $120.00 | $95.00 | $95.00 | $109.00 | $95.00 |
| 116 | Delineator, bracket mounted (620E11000) | EACH | 6 | $53.00 | $210.00 | $210.00 | $242.00 | $210.00 |
| 117 | RPM (621E00100) | EACH | 436 | $37.40 | $37.40 | $37.00 | $68.00 | $56.25 |
| 118 | Raised pavement marker removed, as per plan (621E54001) | EACH | 358 | $15.00 | $28.50 | $5.00 | $63.00 | $6.00 |
| 119 | Barrier reflector, type 1, BI-directional (626E00102) | EACH | 36 | $13.00 | $13.00 | $11.80 | $13.00 | $12.00 |
| 120 | Barrier reflector, type 1, one-way (626E00102) | EACH | 12 | $13.00 | $13.00 | $12.00 | $14.00 | $12.00 |
| 121 | Barrier reflector, type 2, one-way (626E00110) | EACH | 35 | $13.00 | $13.00 | $14.00 | $16.00 | $14.00 |
| 122 | Ground mounted support, no. 2 post (630E02100) | FT | 123.80 | $12.85 | $16.00 | $16.00 | $18.00 | $16.00 |
| 123 | Ground mounted support, no. 3 post (630E03100) | FT | 59.80 | $13.00 | $19.00 | $19.00 | $22.00 | $19.00 |
| 124 | Sign post reflector (630E08600) | EACH | 4 | $23.00 | $45.00 | $45.00 | $52.00 | $45.00 |
| 125 | Overhead sign support, type TC-15.116, design 2 (630E72420) | EACH | 1 | $79,500 | $79,850 | $79,850 | $92,144 | $80,000 |
| 126 | Sign, flat sheet (630E80100) | SF | 89.90 | $20.25 | $20.00 | $20.00 | $23.00 | $20.00 |
| 127 | Concrete median barrier sign bracket, as per plan (630E81021) | EACH | 6 | $785.00 | $6,300.00 | $1,120.00 | $1,293.00 | $1,120.00 |
| 128 | Concrete barrier median overhead sign support foundation, type TC-21.50 (630E84010) | EACH | 1 | $20,116 | $18,200 | $18,975 | $20,166 | $15,475 |
| 129 | Rigid overhead sign support foundation (630E84510) | EACH | 1 | $12,450 | $12,980 | $12,980 | $14,978 | $12,980 |
| 130 | Removal of ground mounted sign and disposal (630E84900) | EACH | 17 | $23.00 | $10.00 | $10.00 | $11.00 | $10.00 |
| 131 | Removal of ground mounted sign and reerection, as per plan (630E85101) | EACH | 1 | $500.00 | $5,450.00 | $5,450.00 | $6,289.00 | $5,450.00 |
| 132 | Removal of ground mounted sign and reerection, as per plan (630E85101) | EACH | 1 | $500.00 | $6,525.00 | $6,525.00 | $7,529.00 | $6,525.00 |
| 133 | Removal of ground mounted post support and disposal (630E86002) | EACH | 15 | $27.00 | $20.00 | $20.00 | $23.00 | $20.00 |
| 134 | Removal of overhead mounted sign and reerection (630E87100) | EACH | 4 | $1,050.00 | $525.00 | $525.00 | $606.00 | $525.00 |
| 135 | Removal of overhead sign support and disposal, type TC-7.65 (630E89802) | EACH | 1 | $2,700.00 | $2,650.00 | $2,650.00 | $3,058.00 | $2,650.00 |
| 136 | Removal of pavement marking (642E30000) | FT | 49,104 | $0.29 | $0.29 | $0.30 | $2.30 | $0.30 |
| 137 | Stop line (646E10400) | FT | 25 | $13.65 | $13.65 | $13.65 | $20.00 | $13.00 |
| 138 | Crosswalk line, 12" (646E10510) | FT | 144 | $9.90 | $9.90 | $9.90 | $9.00 | $10.00 |
| 139 | Transverse/diagonal line (646E10600) | FT | 961 | $13.15 | $13.15 | $13.15 | $11.50 | $13.00 |
| 140 | Chevron marking (646E10620) | FT | 435 | $13.15 | $13.15 | $13.15 | $11.50 | $13.00 |
| 141 | Lane arrow (646E20300) | EACH | 4 | $175.00 | $175.00 | $175.00 | $231.00 | $175.00 |
| 142 | Word on pavement, 72" (646E20400) | EACH | 1 | $205.00 | $205.00 | $205.00 | $318.00 | $205.00 |
| 143 | Yield line (646E20800) | FT | 17 | $20.65 | $20.65 | $20.65 | $17.50 | $20.00 |
| 144 | Wet reflective epoxy pavement marking, edge line, 6" (807E12010) | MI | 5.16 | $6,000.00 | $6,000.00 | $6,000.00 | $5,769.00 | $6,000.00 |
| 145 | Wet reflective epoxy pavement marking, lane line, 6" (807E12110) | MI | 2.60 | $2,500.00 | $2,500.00 | $2,500.00 | $2,884.00 | $2,500.00 |
| 146 | Wet reflective epoxy pavement marking, channelizing line, 12" (807E12310) | FT | 4,611 | $2.75 | $2.75 | $2.75 | $3.50 | $2.75 |
| 147 | Wet reflective epoxy pavement marking, dotted line, 6" (807E12410) | FT | 2,770 | $1.75 | $1.75 | $1.75 | $2.00 | $1.75 |
| 148 | Wet reflective epoxy pavement marking, dotted line, 12" (807E12430) | FT | 4,292 | $2.50 | $2.50 | $2.50 | $2.50 | $2.50 |
| 149 | Grooving for 6" recessed pavement marking, (asphalt) (850E10010) | MI | 7.04 | $2,125.00 | $2,125.00 | $2,125.00 | $1,442.00 | $2,125.00 |
| 150 | Grooving for 6" recessed pavement marking, (asphalt) (850E10110) | FT | 2,246 | $1.50 | $1.50 | $1.50 | $1.10 | $1.50 |
| 151 | Grooving for 12" recessed pavement marking, (asphalt) (850E10130) | FT | 7,360 | $1.75 | $1.75 | $1.75 | $1.50 | $1.75 |
| 152 | Grooving for 6" recessed pavement marking, (concrete) (850E20010) | MI | 0.73 | $5,250.00 | $5,250.00 | $5,250.00 | $3,173.00 | $5,250.00 |
| 153 | Grooving for 6" recessed pavement marking, (concrete) (850E20110) | FT | 524 | $2.50 | $2.50 | $2.50 | $2.00 | $2.50 |
| 154 | Grooving for 12" recessed pavement marking, (concrete) (850E20130) | FT | 1,542 | $3.25 | $3.25 | $3.25 | $3.00 | $3.25 |
| 155 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 500 | $110.00 | $98.00 | $85.00 | $75.00 | $120.00 |
| 156 | Special - work zone traffic signal (614E11300) | EACH | 2 | $22,500 | $50,000 | $22,500 | $51,208 | $22,500 |
| 157 | Increased barrier delineation (614E11630) | FT | 6,767 | $0.58 | $2.32 | $2.30 | $2.50 | $2.50 |
| 158 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 8 | $2,000.00 | $1,790.00 | $1,800.00 | $7,431.00 | $2,380.00 |
| 159 | Detour signing (614E12420) | LS | 1 | $36,500 | $30,000 | $125,000 | $100,000 | $29,610 |
| 160 | Work zone increased penalties sign (614E12484) | EACH | 7 | $185.00 | $255.29 | $260.00 | $248.00 | $255.00 |
| 161 | Work zone raised pavement marker, as per plan (614E12801) | EACH | 1,074 | $24.24 | $6.38 | $14.00 | $45.50 | $39.50 |
| 162 | Asphalt concrete for maintaining traffic (614E13000) | CY | 249 | $350.00 | $125.48 | $450.00 | $420.00 | $445.00 |
| 163 | Barrier reflector, type 1, (BI-directional) (614E13310) | EACH | 298 | $9.00 | $11.52 | $11.52 | $20.00 | $11.00 |
| 164 | Barrier reflector, type 1, (one way) (614E13310) | EACH | 141 | $8.85 | $11.52 | $11.52 | $17.00 | $11.00 |
| 165 | Barrier reflector, type 2, (one way) (614E13312) | EACH | 118 | $8.95 | $11.52 | $11.52 | $29.00 | $11.00 |
| 166 | Object marker, one way (614E13350) | EACH | 259 | $14.50 | $19.02 | $19.02 | $28.00 | $19.00 |
| 167 | Object marker, two way (614E13360) | EACH | 298 | $15.50 | $21.43 | $21.43 | $29.00 | $21.00 |
| 168 | Maintaining traffic, misc.: barrier median inlet R (614E18000) | EACH | 2 | $4,800.00 | $7,500.00 | $10,000 | $6,178.00 | $2,500.00 |
| 169 | Maintaining traffic, misc.: site access (614E18002) | LS | 1 | $170,000 | $55,000 | $100,000 | $130,000 | $450,000 |
| 170 | Portable changeable message sign, as per plan (614E18601) | SNMT | 192 | $500.00 | $816.82 | $865.00 | $800.00 | $815.00 |
| 171 | Work zone lane line, class I, 6", 807 paint (614E20056) | MI | 7.04 | $1,300.00 | $1,300.00 | $1,300.00 | $1,471.00 | $1,300.00 |
| 172 | Work zone edge line, class I, 6", 807 paint (614E22056) | MI | 21.46 | $2,675.00 | $2,675.00 | $2,675.00 | $3,174.00 | $2,675.00 |
| 173 | Work zone channelizing line, class I, 12", 807 paint (614E23110) | FT | 16,636 | $2.25 | $2.25 | $2.25 | $2.30 | $2.25 |
| 174 | Work zone dotted line, class I, 6", 807 paint (614E24102) | FT | 9,007 | $1.50 | $1.50 | $1.50 | $1.50 | $1.50 |
| 175 | Work zone dotted line, class I, 12", 642 paint (614E24208) | FT | 8,465 | $0.85 | $0.85 | $0.85 | $1.10 | $0.85 |
| 176 | Work zone transverse/diagonal line, class I (614E25000) | FT | 2,882 | $3.25 | $3.25 | $3.25 | $5.00 | $3.25 |
| 177 | Work zone stop line, class I (614E26000) | FT | 393 | $3.50 | $3.50 | $3.50 | $5.00 | $3.50 |
| 178 | Work zone crosswalk line, class I, 12" (614E27010) | FT | 504 | $3.00 | $3.00 | $3.00 | $3.74 | $3.00 |
| 179 | Work zone gore marking, class II (614E28000) | FT | 1,752 | $3.25 | $3.25 | $3.25 | $3.00 | $3.25 |
| 180 | Work zone arrow, class I (614E30000) | EACH | 28 | $75.00 | $75.00 | $75.00 | $86.00 | $75.00 |
| 181 | Work zone word on pavement, 96", class I (614E31640) | EACH | 4 | $100.00 | $100.00 | $100.00 | $202.00 | $100.00 |
| 182 | Work zone pavement marking, misc.: yield line (614E98100) | FT | 60 | $6.50 | $6.50 | $6.50 | $7.48 | $6.50 |
| 183 | Roads for maintaining traffic (615E10000) | LS | 1 | $35,000 | $115,000 | $220,000 | $182,000 | $35,000 |
| 184 | Pavement for maintaining traffic, class A (615E20000) | SY | 1,037 | $80.00 | $100.00 | $80.00 | $182.00 | $85.00 |
| 185 | Water (616E10000) | MGAL | 15 | $60.00 | $100.00 | $180.00 | $50.50 | $10.00 |
| 186 | Portable barrier, unanchored (622E41100) | FT | 8,462 | $21.00 | $15.00 | $20.00 | $14.00 | $35.00 |
| 187 | Portable barrier, anchored (622E41110) | FT | 2,567 | $35.00 | $33.00 | $30.00 | $68.00 | $50.00 |
| 188 | Portable non-intrusive traffic sensor, class I (896E00010) | SNMT | 60 | $700.00 | $827.61 | $850.00 | $865.00 | $825.00 |
| 189 | Portable changeable message sign, as per plan (896E00021) | SNMT | 20 | $610.00 | $862.92 | $950.00 | $1,154.00 | $850.00 |
| 190 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $1,100,000 | $945,000 | $775,000 | $744,105 | $600,000 |
| 191 | Approach slab removed (202E22900) | SY | 400 | $55.00 | $50.00 | $55.00 | $107.00 | $90.00 |
| 192 | Wearing course removed (202E23500) | SY | 400 | $9.00 | $16.50 | $30.00 | $40.25 | $50.00 |
| 193 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $60,000 | $100,000 | $150,000 | $131,205 | $100,000 |
| 194 | Unclassified excavation (503E21100) | CY | 485 | $225.00 | $312.00 | $200.00 | $45.00 | $130.00 |
| 195 | Epoxy coated steel reinforcement (509E10000) | LB | 264,359 | $1.95 | $1.94 | $1.60 | $1.85 | $2.00 |
| 196 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 100 | $4.00 | $7.00 | $2.00 | $4.00 | $2.00 |
| 197 | No. 4 deformed GFRP reinforcement (509E30020) | FT | 13,512 | $1.45 | $1.25 | $2.00 | $1.80 | $2.00 |
| 198 | Dowel holes with nonshrink, nonmetallic grout, as per plan (510E10001) | EACH | 1,721 | $35.00 | $30.00 | $35.00 | $25.00 | $35.00 |
| 199 | Class QC2 concrete with QC/QA, bridge deck (511E34446) | CY | 683 | $1,260.00 | $1,050.00 | $1,180.00 | $1,375.00 | $1,900.00 |
| 200 | Class QC2 concrete with QC/QA, bridge deck (parapet) (511E34450) | CY | 199 | $610.00 | $975.00 | $880.00 | $965.00 | $1,200.00 |
| 201 | Class QC1 concrete with QC/QA, abutment (511E45712) | CY | 181 | $1,650.00 | $2,000.00 | $860.00 | $2,633.00 | $2,400.00 |
| 202 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 1,348 | $30.00 | $31.50 | $31.50 | $31.50 | $30.00 |
| 203 | Treating of concrete bridge deck with SRS (512E10400) | SY | 2,554 | $8.00 | $12.00 | $12.00 | $16.50 | $8.00 |
| 204 | Type 2 waterproofing (512E33000) | SY | 145 | $30.00 | $41.00 | $45.00 | $48.20 | $60.00 |
| 205 | Treating concrete bridge decks with gravity fed resin (512E73500) | SY | 2,554 | $12.00 | $16.50 | $16.50 | $16.50 | $12.00 |
| 206 | Structural steel members, level 1, as per plan (513E10221) | LB | 13,250 | $14.25 | $26.86 | $13.00 | $21.00 | $20.00 |
| 207 | Welded stud shear connectors (513E20000) | EACH | 10,592 | $4.53 | $4.95 | $5.00 | $4.55 | $4.50 |
| 208 | Replacement of deteriorated end crossframes (513E21500) | LB | 10,019 | $9.50 | $9.51 | $10.00 | $10.60 | $9.50 |
| 209 | Structural steel, misc.: cross frames (seismic ret (513E90000) | LB | 1,686 | $15.93 | $13.83 | $16.50 | $18.10 | $16.00 |
| 210 | Surface preparation of existing structural steel, as per plan (514E00051) | SF | 2,496 | $59.85 | $59.85 | $60.00 | $59.85 | $60.00 |
| 211 | Field painting of existing structural steel, prime coat, as per plan (514E00057) | SF | 2,496 | $14.00 | $14.00 | $14.00 | $14.00 | $14.00 |
| 212 | Field painting structural steel, intermediate coat, as per plan (514E00061) | SF | 3,463 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 |
| 213 | Field painting structural steel, finish coat, as per plan (514E00067) | SF | 3,463 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 |
| 214 | Structural expansion joint including elastomeric strip seal (516E11210) | FT | 406 | $775.00 | $950.00 | $800.00 | $975.00 | $1,200.00 |
| 215 | 1/2" preformed expansion joint filler (516E13200) | SF | 18 | $17.50 | $6.50 | $10.00 | $13.50 | $25.00 |
| 216 | 1" preformed expansion joint filler (516E13600) | SF | 81 | $20.00 | $9.00 | $12.00 | $10.65 | $23.00 |
| 217 | 2" preformed expansion joint filler (516E13900) | SF | 22 | $22.00 | $8.00 | $20.00 | $13.75 | $22.00 |
| 218 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44001) | EACH | 16 | $900.00 | $1,000.00 | $750.00 | $1,650.00 | $700.00 |
| 219 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44101) | EACH | 16 | $2,000.00 | $2,400.00 | $2,000.00 | $3,840.00 | $1,962.00 |
| 220 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $60,000 | $75,000 | $60,000 | $48,500 | $48,500 |
| 221 | Porous backfill with geotextile fabric (518E21200) | CY | 222 | $130.00 | $125.00 | $135.00 | $195.65 | $160.00 |
| 222 | 6" perforated corrugated plastic pipe (518E40000) | FT | 395 | $13.50 | $18.00 | $16.00 | $29.75 | $50.00 |
| 223 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 40 | $65.00 | $18.00 | $24.00 | $29.75 | $55.00 |
| 224 | Special - composite fiber wrap system (519E00100) | SF | 1,536 | $45.00 | $54.00 | $60.00 | $112.00 | $45.00 |
| 225 | Reinforced concrete approach slabs with QC/QA (T=1 (526E25011) | SY | 638 | $500.00 | $440.00 | $525.00 | $440.00 | $600.00 |
| 226 | Type A installation (526E90010) | FT | 230 | $300.00 | $280.00 | $225.00 | $345.00 | $250.00 |
| 228 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $1,000,000 | $810,000 | $775,000 | $775,030 | $430,000 |
| 229 | Approach slab removed (202E22900) | SY | 400 | $55.00 | $55.00 | $55.00 | $107.00 | $90.00 |
| 230 | Wearing course removed (202E23500) | SY | 400 | $10.00 | $16.50 | $30.00 | $40.25 | $50.00 |
| 231 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $60,000 | $100,000 | $150,000 | $131,385 | $140,000 |
| 232 | Unclassified excavation (503E21100) | CY | 139 | $410.00 | $625.00 | $300.00 | $135.55 | $130.00 |
| 233 | Epoxy coated steel reinforcement (509E10000) | LB | 223,658 | $1.95 | $1.99 | $1.60 | $1.90 | $2.00 |
| 234 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 165 | $4.00 | $7.00 | $2.00 | $4.00 | $2.00 |
| 235 | No. 4 deformed GFRP reinforcement (509E30020) | FT | 13,261 | $1.45 | $1.25 | $2.00 | $1.80 | $2.00 |
| 236 | Dowel holes with nonshrink, nonmetallic grout, as per plan (510E10001) | EACH | 700 | $35.00 | $30.00 | $35.00 | $25.00 | $35.00 |
| 237 | Class QC2 concrete with QC/QA, bridge deck (511E34446) | CY | 699 | $1,250.00 | $1,050.00 | $1,115.00 | $1,314.00 | $1,800.00 |
| 238 | Class QC2 concrete with QC/QA, bridge deck (parapet) (511E34450) | CY | 197 | $650.00 | $960.00 | $850.00 | $965.00 | $1,200.00 |
| 239 | Class QC1 concrete with QC/QA, abutment (511E45712) | CY | 97 | $1,900.00 | $1,750.00 | $1,295.00 | $2,080.00 | $1,600.00 |
| 240 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 1,108 | $30.00 | $31.50 | $31.50 | $31.50 | $30.00 |
| 241 | Treating of concrete bridge deck with SRS (512E10400) | SY | 3,071 | $8.00 | $12.00 | $12.00 | $16.75 | $8.00 |
| 242 | Concrete repair by epoxy injection (512E10600) | FT | 4 | $400.00 | $185.00 | $185.00 | $185.00 | $400.00 |
| 243 | Type 2 waterproofing (512E33000) | SY | 97 | $31.00 | $41.00 | $45.00 | $54.00 | $60.00 |
| 244 | Treating concrete bridge decks with gravity fed resin (512E73500) | SY | 3,071 | $12.00 | $16.50 | $16.50 | $16.75 | $12.00 |
| 245 | Structural steel members, level 1, as per plan (513E10221) | LB | 14,111 | $13.25 | $25.75 | $12.00 | $18.55 | $18.50 |
| 246 | Welded stud shear connectors (513E20000) | EACH | 15,776 | $4.53 | $4.95 | $5.00 | $4.55 | $4.50 |
| 247 | Replacement of deteriorated end crossframes (513E21500) | LB | 4,230 | $16.75 | $10.29 | $18.00 | $16.15 | $16.50 |
| 248 | Structural steel, misc.: seismic retrofit (513E90000) | LB | 845 | $15.25 | $28.66 | $9.75 | $18.35 | $15.00 |
| 249 | Structural steel, misc.: replacement of cross fram (513E95030) | EACH | 28 | $1,275.00 | $2,150.00 | $1,150.00 | $1,340.00 | $1,300.00 |
| 250 | Surface preparation of existing structural steel, as per plan (514E00051) | SF | 3,782 | $49.29 | $49.29 | $50.00 | $49.29 | $50.00 |
| 251 | Field painting of existing structural steel, prime coat, as per plan (514E00057) | SF | 3,782 | $14.00 | $14.00 | $14.00 | $14.00 | $14.00 |
| 252 | Field painting structural steel, intermediate coat, as per plan (514E00061) | SF | 4,824 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 |
| 253 | Field painting structural steel, finish coat, as per plan (514E00067) | SF | 4,824 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 |
| 254 | Structural expansion joint including elastomeric strip seal (516E11210) | FT | 229 | $908.00 | $830.00 | $825.00 | $975.00 | $1,200.00 |
| 255 | 1" preformed expansion joint filler (516E13600) | SF | 135 | $16.00 | $9.00 | $12.00 | $10.65 | $25.00 |
| 256 | 2" preformed expansion joint filler (516E13900) | SF | 13 | $22.00 | $8.00 | $20.00 | $13.75 | $25.00 |
| 257 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44001) | EACH | 16 | $950.00 | $900.00 | $750.00 | $1,760.00 | $580.00 |
| 258 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44101) | EACH | 16 | $2,650.00 | $3,000.00 | $2,500.00 | $3,965.00 | $2,970.00 |
| 259 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $60,000 | $65,000 | $60,000 | $48,500 | $48,500 |
| 260 | Scuppers, including supports (518E12200) | EACH | 5 | $2,800.00 | $3,200.00 | $3,500.00 | $3,265.00 | $3,000.00 |
| 261 | Porous backfill with geotextile fabric (518E21200) | CY | 139 | $155.00 | $130.00 | $140.00 | $178.00 | $160.00 |
| 262 | 6" perforated corrugated plastic pipe (518E40000) | FT | 285 | $14.00 | $18.00 | $16.00 | $29.75 | $50.00 |
| 263 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 100 | $40.00 | $18.00 | $20.00 | $29.75 | $55.00 |
| 264 | 8" pipe downspout, including specials (518E51100) | FT | 17 | $1,200.00 | $350.00 | $630.00 | $1,535.00 | $800.00 |
| 265 | Special - composite fiber wrap system (519E00100) | SF | 971 | $45.00 | $54.00 | $45.00 | $76.70 | $45.00 |
| 266 | Patching concrete structure, as per plan (519E11101) | SF | 11 | $250.00 | $165.00 | $165.00 | $400.00 | $250.00 |
| 267 | Reinforced concrete approach slabs with QC/QA (T=1 (526E25011) | SY | 640 | $455.00 | $405.00 | $385.00 | $450.00 | $600.00 |
| 268 | Type A installation (526E90010) | FT | 224 | $240.00 | $160.00 | $180.00 | $345.00 | $250.00 |
| 270 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $750,000 | $650,000 | $750,000 | $676,715 | $500,000 |
| 271 | Approach slab removed (202E22900) | SY | 296 | $60.00 | $68.00 | $55.00 | $116.00 | $90.00 |
| 272 | Wearing course removed (202E23500) | SY | 296 | $13.00 | $15.00 | $30.00 | $32.70 | $50.00 |
| 273 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $60,000 | $100,000 | $150,000 | $131,385 | $145,000 |
| 274 | Unclassified excavation (503E21100) | CY | 112 | $465.00 | $1,000.00 | $375.00 | $168.00 | $130.00 |
| 275 | Epoxy coated steel reinforcement (509E10000) | LB | 182,077 | $1.95 | $1.75 | $1.60 | $1.80 | $2.00 |
| 276 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 100 | $4.00 | $12.00 | $2.00 | $4.00 | $2.00 |
| 277 | No. 4 deformed GFRP reinforcement (509E30020) | FT | 11,683 | $1.45 | $1.50 | $2.00 | $1.90 | $2.00 |
| 278 | Dowel holes with nonshrink, nonmetallic grout, as per plan (510E10001) | EACH | 840 | $35.00 | $38.00 | $35.00 | $25.00 | $35.00 |
| 279 | Class QC2 concrete with QC/QA, bridge deck (511E34446) | CY | 453 | $1,450.00 | $1,080.00 | $1,405.00 | $1,714.00 | $1,950.00 |
| 280 | Class QC2 concrete with QC/QA, bridge deck (parapet) (511E34450) | CY | 173 | $675.00 | $1,000.00 | $1,105.00 | $1,045.00 | $1,400.00 |
| 281 | Class QC1 concrete with QC/QA, abutment (511E45712) | CY | 98 | $1,700.00 | $1,600.00 | $1,225.00 | $2,090.00 | $1,600.00 |
| 282 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 1,011 | $30.00 | $31.50 | $31.50 | $31.50 | $30.00 |
| 283 | Treating of concrete bridge deck with SRS (512E10400) | SY | 2,048 | $8.00 | $12.00 | $12.00 | $17.00 | $8.00 |
| 284 | Type 2 waterproofing (512E33000) | SY | 82 | $30.00 | $72.00 | $50.00 | $55.75 | $60.00 |
| 285 | Treating concrete bridge decks with gravity fed resin (512E73500) | SY | 2,048 | $12.00 | $16.50 | $16.50 | $17.00 | $12.00 |
| 286 | Welded stud shear connectors (513E20000) | EACH | 9,052 | $4.53 | $4.95 | $5.00 | $4.55 | $4.50 |
| 287 | Replacement of deteriorated end crossframes (513E21500) | LB | 3,474 | $14.50 | $23.90 | $15.75 | $15.95 | $14.50 |
| 288 | Surface preparation of existing structural steel, as per plan (514E00051) | SF | 2,941 | $46.13 | $46.13 | $47.00 | $46.13 | $46.00 |
| 289 | Field painting of existing structural steel, prime coat, as per plan (514E00057) | SF | 2,941 | $14.00 | $14.00 | $14.00 | $14.00 | $14.00 |
| 290 | Field painting structural steel, intermediate coat, as per plan (514E00061) | SF | 3,436 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 |
| 291 | Field painting structural steel, finish coat, as per plan (514E00067) | SF | 3,436 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 |
| 292 | Structural expansion joint including elastomeric strip seal (516E11210) | FT | 191 | $945.00 | $845.00 | $855.00 | $975.00 | $1,400.00 |
| 293 | 1/2" preformed expansion joint filler (516E13200) | SF | 14 | $17.50 | $13.00 | $12.00 | $13.50 | $25.00 |
| 294 | 1" preformed expansion joint filler (516E13600) | SF | 75 | $20.00 | $9.00 | $15.00 | $10.65 | $25.00 |
| 295 | 2" preformed expansion joint filler (516E13900) | SF | 13 | $22.00 | $8.00 | $20.00 | $13.75 | $25.00 |
| 296 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44101) | EACH | 26 | $1,000.00 | $1,300.00 | $750.00 | $1,695.00 | $850.00 |
| 297 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $60,000 | $60,000 | $55,000 | $43,000 | $43,000 |
| 298 | Scuppers, including supports (518E12200) | EACH | 3 | $2,750.00 | $3,800.00 | $3,500.00 | $3,065.00 | $5,000.00 |
| 299 | Porous backfill with geotextile fabric (518E21200) | CY | 58 | $140.00 | $185.00 | $145.00 | $177.00 | $160.00 |
| 300 | 6" perforated corrugated plastic pipe (518E40000) | FT | 200 | $15.00 | $18.00 | $16.00 | $40.00 | $50.00 |
| 301 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 30 | $55.00 | $110.00 | $25.00 | $30.00 | $55.00 |
| 302 | Special - composite fiber wrap system (519E00100) | SF | 608 | $45.00 | $54.00 | $45.00 | $92.00 | $45.00 |
| 303 | Reinforced concrete approach slabs with QC/QA (T=1 (526E25011) | SY | 528 | $485.00 | $450.00 | $425.00 | $455.00 | $600.00 |
| 304 | Type A installation (526E90010) | FT | 195 | $275.00 | $255.00 | $210.00 | $348.00 | $250.00 |
| 306 | Department'S share of the dispute resolution advisor (100E51200) | EACH | 40,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 307 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $200,000 | $148,000 | $245,000 | $236,000 | $300,000 |
| 308 | CPM progress schedule (108E10000) | LS | 1 | $1,250.00 | $5,000.00 | $20,000 | $11,530 | $40,000 |
| 309 | Maintaining traffic (614E11000) | LS | 1 | $900,000 | $820,500 | $1,100,000 | $1,114,000 | $1,700,000 |
| 311 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $150,000 | $176,000 | $84,500 | $99,500 | $80,000 |
| 312 | Mobilization (624E10000) | LS | 1 | $1,048,000 | $1,000,000 | $1,050,000 | $1,593,125 | $1,600,000 |
| 313 | Special - calendar days of contract time for opening to traffic (unit price field should reflect number of days bid) (614E15000) | DLR | 12,000 | $180.00 | $220.00 | $220.00 | $220.00 | $220.00 |
| 314 | Special - calendar days of contract time for opening to traffic (unit price field should reflect number of days bid) (614E15000) | DLR | 12,000 | $180.00 | $220.00 | $220.00 | $220.00 | $220.00 |
| 400 | Manhole, no. 3, as per plan (611E99575) | EACH | 1 | $7,900.00 | $13,000 | $7,700.00 | $5,990.00 | $10,000 |
| 401 | Maintaining traffic, misc.: dotted line, class 1, (614E18030) | FT | 17,795 | $1.75 | $1.75 | $1.75 | $1.55 | $1.75 |
| 402 | Work zone lane line, class I, 6", 642 paint (614E20110) | MI | 2.15 | $475.00 | $475.00 | $475.00 | $866.00 | $475.00 |
| 403 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 6.54 | $770.00 | $770.00 | $770.00 | $1,442.00 | $775.00 |
| 404 | Work zone channelizing line, class I, 12", 642 paint (614E23210) | FT | 5,447 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 405 | Work zone dotted line, class I, 6", 642 paint (614E24202) | FT | 4,119 | $0.75 | $0.75 | $0.75 | $1.00 | $0.75 |
| 406 | Concrete median removed, as per plan (202E30601) | SY | 115 | $46.00 | $45.00 | $33.00 | $85.00 | $35.00 |
| 407 | Concrete slope protection removed, as per plan (202E32801) | SY | 305 | $38.27 | $25.00 | $33.00 | $21.70 | $15.00 |
| 408 | Concrete slope protection, as per plan (601E21001) | SY | 305 | $100.00 | $150.00 | $140.00 | $93.00 | $85.00 |
| 409 | Concrete median, as per plan (609E72001) | SY | 115 | $155.00 | $95.00 | $90.00 | $121.00 | $95.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of December 18, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.