ODOT contract 250598 bid tabulation
TRU-US 422-08.01 (SIGNALIZATION). Let by Ohio DOT on December 18, 2025, TRU. 6 bids received; low bid $204,472 by Cornerstone Electric Inc, -14% against the engineer's estimate of $237,000.
- Owner
- Ohio DOT
- Letting
- 18 DEC 2025
- Pay items
- 38
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Cornerstone Electric Inc | $204,472 | Low | -14% |
| 2 | Perram Electric Inc | $208,078 | +2.0% | -12% |
| 3 | TC Randel Constructon LLC | $217,713 | +6.0% | -8.0% |
| 4 | S E T Inc | $223,000 | +9.0% | -6.0% |
| 5 | Kokosing Construction Company Inc | $265,202 | +30% | +12% |
| 6 | Miller Cable Company | $275,000 | +34% | +16% |
Engineer's estimate: $237,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Cornerstone Electric Inc | 2. Perram Electric Inc | 3. TC Randel Constructon LLC | 4. S E T Inc | 5. Kokosing Construction Company Inc | 6. Miller Cable Company |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Special - as-built construction plans (690E91000) | LS | 1 | $1,000.00 | $394.50 | $500.00 | $500.00 | $1,000.00 | $5,500.00 |
| 2 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 3 | 4" conduit, type E (611E00400) | FT | 20 | $10.00 | $10.85 | $10.00 | $20.00 | $15.00 | $8.00 |
| 4 | Sign attachment assembly (630E75000) | EACH | 2 | $800.00 | $497.00 | $1,660.00 | $1,700.00 | $1,630.00 | $1,725.00 |
| 5 | Sign, overhead extrusheet (630E80224) | SF | 77 | $45.00 | $32.35 | $46.00 | $48.00 | $45.00 | $50.00 |
| 6 | Removal of ground mounted sign and disposal (630E84900) | EACH | 2 | $50.00 | $49.30 | $22.00 | $20.00 | $20.00 | $21.00 |
| 7 | Removal of overhead mounted sign and disposal (630E87400) | EACH | 1 | $750.00 | $394.50 | $500.00 | $500.00 | $475.00 | $500.00 |
| 8 | Signing, misc.: removal of sign post reflector (630E97700) | EACH | 4 | $25.00 | $24.65 | $16.00 | $16.00 | $15.00 | $15.75 |
| 9 | Stop line (646E10400) | FT | 71 | $100.00 | $46.15 | $56.00 | $26.00 | $49.55 | $77.50 |
| 10 | Conduit, 3", 725.04 (625E25500) | FT | 42 | $30.00 | $37.85 | $27.00 | $44.00 | $57.00 | $35.00 |
| 11 | Conduit, jacked or drilled, 725.04, 4" (625E25902) | FT | 147 | $75.00 | $87.35 | $111.00 | $72.00 | $125.00 | $80.00 |
| 12 | Trench (625E29000) | FT | 42 | $20.00 | $14.10 | $19.00 | $20.00 | $20.00 | $16.00 |
| 13 | Pull box, 725.08, 24" (625E30706) | EACH | 3 | $1,500.00 | $2,005.00 | $925.00 | $1,200.00 | $2,900.00 | $1,685.00 |
| 14 | Ground rod (625E32000) | EACH | 3 | $200.00 | $322.00 | $185.00 | $230.00 | $350.00 | $285.00 |
| 15 | Underground warning/marking tape, as per plan (625E36011) | FT | 42 | $1.00 | $1.00 | $3.50 | $2.00 | $35.00 | $3.00 |
| 16 | Arc flash calculations and label (tru 422 controll (625E76000) | EACH | 1 | $500.00 | $2,000.00 | $3,500.00 | $840.00 | $1,400.00 | $4,250.00 |
| 17 | Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate (632E05006) | EACH | 7 | $900.00 | $970.00 | $900.00 | $1,100.00 | $1,100.00 | $1,525.00 |
| 18 | Covering of vehicular signal head (632E25000) | EACH | 7 | $25.00 | $10.00 | $20.00 | $50.00 | $70.00 | $50.00 |
| 19 | Signal cable, 5 conductor, no. 14 AWG (632E40500) | FT | 523 | $3.50 | $2.40 | $6.50 | $3.00 | $3.00 | $3.50 |
| 20 | Signal cable, 7 conductor, no. 14 AWG (632E40700) | FT | 126 | $4.00 | $2.80 | $22.75 | $3.00 | $4.50 | $3.75 |
| 21 | Signal support foundation (632E64010) | EACH | 2 | $8,000.00 | $8,345.00 | $7,250.00 | $9,000.00 | $16,000 | $9,950.00 |
| 22 | Power cable, 3 conductor, no. 4 AWG (632E69300) | FT | 30 | $6.00 | $9.95 | $4.50 | $10.00 | $25.00 | $15.00 |
| 23 | Power service, as per plan (632E70001) | EACH | 1 | $3,000.00 | $2,685.00 | $1,250.00 | $3,500.00 | $6,000.00 | $2,750.00 |
| 24 | Signal support, type TC-81.22, design 14 (632E72150) | EACH | 1 | $20,000 | $19,940 | $20,000 | $24,000 | $24,000 | $26,235 |
| 25 | Combination signal support, type TC-12.31 design 1 (632E78349) | EACH | 1 | $34,000 | $33,435 | $31,000 | $42,000 | $40,000 | $47,730 |
| 26 | Cabinet, type TS-2, as per plan (633E65511) | EACH | 1 | $17,000 | $17,045 | $17,500 | $22,000 | $23,000 | $21,580 |
| 27 | Cabinet foundation, as per plan (633E67101) | EACH | 1 | $2,500.00 | $3,375.00 | $2,350.00 | $2,500.00 | $2,200.00 | $3,300.00 |
| 28 | Controller work pad, as per plan (633E67201) | EACH | 1 | $800.00 | $790.00 | $400.00 | $500.00 | $5,300.00 | $950.00 |
| 29 | Uninterruptible power supply (UPS), 1000 watt, as per plan (633E75001) | EACH | 1 | $6,500.00 | $6,440.00 | $5,700.00 | $7,000.00 | $6,800.00 | $6,850.00 |
| 30 | Advance radar detection, as per plan (809E69001) | EACH | 2 | $8,600.00 | $9,340.00 | $8,700.00 | $10,000 | $10,000 | $10,600 |
| 31 | Stop line radar detection, as per plan (809E69101) | EACH | 1 | $8,400.00 | $8,735.00 | $8,400.00 | $10,000 | $9,500.00 | $10,100 |
| 32 | Atc controller, as per plan (809E69123) | EACH | 1 | $500.00 | $547.00 | $550.00 | $1,000.00 | $1,100.00 | $1,861.50 |
| 33 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 40 | $50.00 | $75.00 | $85.00 | $95.00 | $80.00 | $80.00 |
| 34 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $2,000.00 | $2,019.35 | $6,000.00 | $2,671.00 | $1,500.00 | $3,500.00 |
| 35 | Maintaining traffic (614E11000) | LS | 1 | $6,000.00 | $8,235.00 | $10,000 | $15,000 | $13,979 | $25,500 |
| 36 | Field office, type B (619E16010) | MNTH | 9 | $1,500.00 | $1,500.00 | $1,650.00 | $200.00 | $300.00 | $750.00 |
| 37 | Construction layout stakes and surveying (623E10000) | LS | 1 | $2,000.00 | $1,185.00 | $3,600.00 | $3,000.00 | $2,500.00 | $5,560.00 |
| 38 | Mobilization (624E10000) | LS | 1 | $10,000 | $10,000 | $9,600.00 | $6,000.00 | $13,000 | $10,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of December 18, 2025. Compiled by Mirage Metrics.