ODOT contract 250580 bid tabulation
BEL-TR 428-00.30 (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on December 18, 2025, BEL. 4 bids received; low bid $884,486 by Stanley Miller Construction Company, -17% against the engineer's estimate of $1,065,000.
- Owner
- Ohio DOT
- Letting
- 18 DEC 2025
- Pay items
- 69
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Stanley Miller Construction Company | $884,486 | Low | -17% |
| 2 | Alan Stone Co Inc | $949,094 | +7.0% | -11% |
| 3 | Shelly & Sands Inc | $958,394 | +8.0% | -10% |
| 4 | R C Construction Company and Son Inc | $1,207,611 | +37% | +13% |
Engineer's estimate: $1,065,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Stanley Miller Construction Company | 2. Alan Stone Co Inc | 3. Shelly & Sands Inc | 4. R C Construction Company and Son Inc |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $2,000.00 | $5,200.00 | $12,000 | $15,000 |
| 2 | Guardrail removed (202E38000) | FT | 30 | $11.00 | $35.00 | $9.00 | $10.00 |
| 3 | Excavation (203E10000) | CY | 216 | $39.50 | $45.00 | $30.00 | $25.00 |
| 4 | Embankment (203E20000) | CY | 211 | $72.00 | $15.00 | $25.00 | $25.00 |
| 5 | Subgrade compaction (204E10000) | SY | 838 | $1.00 | $6.50 | $6.00 | $2.00 |
| 6 | Excavation of subgrade (204E13000) | CY | 45 | $29.00 | $90.00 | $32.00 | $50.00 |
| 7 | Proof rolling (204E45000) | HR | 1 | $125.00 | $290.00 | $275.00 | $200.00 |
| 8 | Guardrail, type MGS (606E15050) | FT | 62.50 | $43.34 | $30.00 | $25.00 | $60.00 |
| 9 | Guardrail, type MGS with long posts (606E15100) | FT | 12.50 | $72.24 | $35.00 | $27.50 | $65.00 |
| 10 | Anchor assembly, MGS type A (606E25550) | EACH | 2 | $2,195.00 | $2,100.00 | $1,750.00 | $2,000.00 |
| 11 | Anchor assembly, type T (606E26500) | EACH | 1 | $1,670.00 | $1,500.00 | $1,250.00 | $1,500.00 |
| 12 | MGS bridge terminal assembly, type 1, as per plan (606E35003) | EACH | 4 | $3,278.00 | $3,300.00 | $2,750.00 | $3,000.00 |
| 13 | Right-of-way monument, type B (623E40520) | EACH | 1 | $555.00 | $1,300.00 | $1,250.00 | $1,500.00 |
| 14 | Special - work involving asbestos containing mater (690E98400) | LS | 1 | $500.00 | $240.00 | $240.00 | $50,000 |
| 15 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 4 | $81.00 | $740.00 | $185.00 | $400.00 |
| 16 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 79 | $156.00 | $210.00 | $68.00 | $175.00 |
| 17 | Soil analysis test (659E00100) | EACH | 2 | $150.00 | $180.00 | $150.00 | $10.00 |
| 18 | Topsoil (659E00300) | CY | 107 | $69.00 | $20.00 | $49.00 | $10.00 |
| 19 | Seeding and mulching (659E10000) | SY | 965 | $6.30 | $2.00 | $3.15 | $10.00 |
| 20 | Repair seeding and mulching (659E14000) | SY | 48 | $1.00 | $15.00 | $3.15 | $0.20 |
| 21 | Inter-seeding (659E15000) | SY | 48 | $1.00 | $35.00 | $3.15 | $0.20 |
| 22 | Commercial fertilizer (659E20000) | TON | 0.14 | $939.00 | $670.00 | $1,250.00 | $2,500.00 |
| 23 | Lime (659E31000) | ACRE | 0.20 | $178.00 | $960.00 | $150.00 | $2,000.00 |
| 24 | Water (659E35000) | MGAL | 5 | $5.00 | $120.00 | $1.00 | $1.00 |
| 25 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 26 | Seeding and erosion control with turf reinforcing mat, type 1 (836E10000) | SY | 21 | $9.50 | $35.00 | $15.00 | $25.00 |
| 27 | 4" unclassified pipe underdrains (605E05200) | FT | 25 | $17.00 | $350.00 | $30.00 | $100.00 |
| 28 | Aggregate drains (605E31100) | FT | 50 | $34.00 | $35.00 | $20.00 | $50.00 |
| 29 | 4" conduit, type F (611E00406) | FT | 20 | $23.00 | $110.00 | $8.00 | $20.00 |
| 30 | 10" conduit, type D (611E03400) | FT | 28 | $67.00 | $110.00 | $52.00 | $35.00 |
| 31 | Precast reinforced concrete outlet (611E99710) | EACH | 2 | $328.00 | $730.00 | $500.00 | $350.00 |
| 32 | Granular material, type E, as per plan (204E30041) | CY | 173 | $105.00 | $200.00 | $85.00 | $175.00 |
| 33 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 52 | $528.00 | $440.00 | $454.00 | $575.00 |
| 34 | Aggregate base (304E20000) | CY | 133 | $143.00 | $130.00 | $100.00 | $175.00 |
| 35 | Prime coat (408E10000) | GAL | 32 | $78.00 | $4.00 | $4.25 | $75.00 |
| 36 | Barrier reflector, type 2, bidirectional (626E00110) | EACH | 10 | $14.50 | $15.00 | $12.00 | $25.00 |
| 37 | Ground mounted support, no. 3 post (630E03100) | FT | 128 | $24.50 | $20.00 | $17.50 | $25.00 |
| 38 | Sign, flat sheet (630E80100) | SF | 45 | $35.50 | $30.00 | $25.00 | $75.00 |
| 39 | Removal of ground mounted sign and disposal (630E84900) | EACH | 5 | $167.00 | $30.00 | $25.00 | $50.00 |
| 40 | Removal of ground mounted post support and disposal (630E86002) | EACH | 5 | $167.00 | $30.00 | $25.00 | $50.00 |
| 41 | Traffic compacted surface, type A or B (410E12000) | CY | 75 | $45.00 | $160.00 | $70.00 | $65.00 |
| 42 | Detour signing (614E12420) | LS | 1 | $3,611.00 | $6,000.00 | $3,250.00 | $20,000 |
| 43 | Asphalt concrete for maintaining traffic (614E13000) | CY | 15 | $100.00 | $330.00 | $315.00 | $65.00 |
| 44 | Water (616E10000) | MGAL | 10 | $1.00 | $0.10 | $106.00 | $1.00 |
| 45 | Structure removed, over 20 foot span, as per plan (202E11003) | LS | 1 | $28,944 | $37,000 | $36,000 | $50,000 |
| 46 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $31,900 | $72,000 | $100,000 | $25,000 |
| 47 | Unclassified excavation (503E21100) | CY | 125 | $118.00 | $50.00 | $220.00 | $100.00 |
| 48 | Steel piles HP12X53, furnished, as per plan (507E00201) | FT | 240 | $41.60 | $55.00 | $38.00 | $95.00 |
| 49 | Steel piles HP14X89, furnished, as per plan (507E00361) | FT | 290 | $70.00 | $80.00 | $63.00 | $120.00 |
| 50 | Special - pile encasement (507E71200) | FT | 116 | $94.00 | $150.00 | $175.00 | $275.00 |
| 51 | Prebored holes, as per plan (507E92201) | FT | 418 | $290.00 | $25.00 | $141.00 | $275.00 |
| 52 | Epoxy coated steel reinforcement (509E10000) | LB | 36,996 | $1.53 | $2.00 | $1.75 | $3.00 |
| 53 | Class QC2 concrete, superstructure (511E32210) | CY | 115 | $1,227.00 | $1,900.00 | $1,400.00 | $1,400.00 |
| 54 | Class QC1 concrete, pier cap (511E42510) | CY | 9 | $1,762.00 | $2,600.00 | $4,695.00 | $1,200.00 |
| 55 | Class QC1 concrete, abutment including footing (511E43510) | CY | 62 | $653.00 | $860.00 | $1,575.00 | $1,200.00 |
| 56 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 102 | $62.00 | $30.00 | $48.00 | $65.00 |
| 57 | 1/2" preformed expansion joint filler (516E13200) | SF | 35 | $2.00 | $2.00 | $4.00 | $45.00 |
| 58 | 1" preformed expansion joint filler (516E13600) | SF | 31 | $3.00 | $2.50 | $4.50 | $55.00 |
| 59 | Integral abutment expansion joint seal (516E14014) | FT | 58 | $37.00 | $10.00 | $52.00 | $65.00 |
| 60 | Railing (twin steel tube) (517E70000) | FT | 182 | $300.00 | $300.00 | $250.00 | $275.00 |
| 61 | Porous backfill with geotextile fabric (518E21200) | CY | 53 | $160.00 | $130.00 | $157.00 | $175.00 |
| 62 | Special - steel drip strip (518E22300) | FT | 178 | $16.00 | $40.00 | $15.50 | $75.00 |
| 63 | 6" perforated corrugated plastic pipe (518E40000) | FT | 83 | $16.00 | $20.00 | $5.00 | $25.00 |
| 64 | 6" non-perforated corrugated plastic pipe, including specials, as per plan (518E40011) | FT | 48 | $35.00 | $25.00 | $5.00 | $25.00 |
| 65 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $10,225 | $8,000.00 | $5,185.00 | $45,000 |
| 66 | Maintaining traffic (614E11000) | LS | 1 | $10,670 | $15,000 | $2,500.00 | $50,000 |
| 67 | Field office, type B (619E16010) | MNTH | 8 | $1,000.00 | $2,000.00 | $4,900.00 | $200.00 |
| 68 | Construction layout stakes and surveying (623E10000) | LS | 1 | $60,111 | $18,000 | $17,000 | $35,000 |
| 69 | Mobilization (624E10000) | LS | 1 | $54,500 | $64,000 | $48,735 | $75,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of December 18, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.