ODOT contract 250604 bid tabulation
D07-GR FY 2026 (GUARDRAIL REBUILDING). Let by Ohio DOT on December 18, 2025, District 7. 2 bids received; low bid $511,844 by M P Dory Co, -9.2% against the engineer's estimate of $564,000.
- Owner
- Ohio DOT
- Letting
- 18 DEC 2025
- Pay items
- 20
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | M P Dory Co | $511,844 | Low | -9.0% |
| 2 | Lake Erie Construction Company | $514,820 | +1.0% | -9.0% |
Engineer's estimate: $564,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. M P Dory Co | 2. Lake Erie Construction Company |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $1,000.00 | $1,150.00 |
| 2 | Guardrail removed (202E38000) | FT | 10,426 | $2.50 | $2.00 |
| 3 | Anchor assembly removed, type A, as per plan (202E42001) | EACH | 25 | $350.00 | $320.00 |
| 4 | Anchor assembly removed, type E (202E42010) | EACH | 45 | $185.00 | $175.00 |
| 5 | Anchor assembly removed, type T (202E42040) | EACH | 3 | $125.00 | $100.00 |
| 6 | Anchor assembly removed, type B (202E42050) | EACH | 5 | $125.00 | $175.00 |
| 7 | Embankment (203E20000) | CY | 282 | $48.00 | $65.00 |
| 8 | Guardrail, type MGS (606E15050) | FT | 10,095 | $20.00 | $18.80 |
| 9 | Rounded end section (606E20050) | EACH | 1 | $90.00 | $65.00 |
| 10 | Anchor assembly, MGS type B (606E26050) | EACH | 5 | $2,400.00 | $2,575.00 |
| 11 | Anchor assembly, MGS type E, MASH 2016 (606E26150) | EACH | 70 | $2,300.00 | $2,550.00 |
| 12 | Anchor assembly, MGS type T (606E26550) | EACH | 3 | $1,200.00 | $1,330.00 |
| 13 | Special - mailbox removed and reset (690E50350) | EACH | 3 | $150.00 | $150.00 |
| 14 | Seeding and mulching, class 3B, as per plan (659E00531) | SY | 5,616 | $1.75 | $1.50 |
| 15 | Erosion control, as per plan (832E30001) | EACH | 10,000 | $1.00 | $1.00 |
| 16 | Stabilized crushed aggregate (411E10000) | CY | 288 | $80.00 | $97.00 |
| 17 | Barrier reflector, type 1, BI-directional (626E00102) | EACH | 276 | $10.00 | $12.00 |
| 18 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $5,000.00 | $2,800.00 |
| 19 | Maintaining traffic (614E11000) | LS | 1 | $3,500.00 | $6,500.00 |
| 20 | Mobilization (624E10000) | LS | 1 | $20,000 | $12,800 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of December 18, 2025. Compiled by Mirage Metrics.