ODOT contract 250590 bid tabulation
MAD-IR 70-00.00 (FOUR LANE RESURFACING). Let by Ohio DOT on December 18, 2025, MAD. 4 bids received; low bid $9,132,215 by Kokosing Construction Company Inc, -9.0% against the engineer's estimate of $10,033,000.
- Owner
- Ohio DOT
- Letting
- 18 DEC 2025
- Pay items
- 74
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Kokosing Construction Company Inc | $9,132,215 | Low | -9.0% |
| 2 | Shelly & Sands Inc | $9,616,896 | +5.0% | -4.0% |
| 3 | John R Jurgensen Company | $10,334,048 | +13% | +3.0% |
| 4 | Shelly Company | $12,095,261 | +32% | +21% |
Engineer's estimate: $10,033,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Kokosing Construction Company Inc | 2. Shelly & Sands Inc | 3. John R Jurgensen Company | 4. Shelly Company |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $500.00 | $5,000.00 | $2,619.52 | $10,000 |
| 2 | Guardrail removed, as per plan (202E38001) | FT | 7,473.75 | $1.80 | $1.80 | $3.00 | $1.80 |
| 3 | Anchor assembly removed, as per plan (202E42207) | EACH | 25 | $200.00 | $200.00 | $350.00 | $200.00 |
| 4 | Impact attenuator removed, as per plan (202E47801) | EACH | 18 | $150.00 | $150.00 | $1,432.89 | $150.00 |
| 5 | Embankment, as per plan (203E20001) | CY | 90 | $30.00 | $30.00 | $72.50 | $30.00 |
| 6 | Reshaping under guardrail (209E15000) | STA | 84.90 | $45.00 | $45.00 | $65.00 | $45.00 |
| 7 | Guardrail, type MGS (606E15050) | FT | 3,687.50 | $20.00 | $20.00 | $21.00 | $20.00 |
| 8 | Guardrail, barrier design, type MGS (606E15550) | FT | 2,187.50 | $34.00 | $34.00 | $28.00 | $34.00 |
| 9 | Anchor assembly, MGS type B (606E26050) | EACH | 24 | $2,450.00 | $2,450.00 | $2,775.00 | $2,450.00 |
| 10 | Anchor assembly, MGS type E (606E26150) | EACH | 1 | $2,500.00 | $2,500.00 | $2,850.00 | $2,500.00 |
| 11 | Anchor assembly, MGS type T (606E26550) | EACH | 21 | $1,100.00 | $1,100.00 | $1,400.00 | $1,100.00 |
| 12 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 24 | $2,450.00 | $2,450.00 | $2,550.00 | $2,450.00 |
| 13 | MGS bridge terminal assembly, type 2 (606E35102) | EACH | 2 | $500.00 | $500.00 | $750.00 | $500.00 |
| 14 | Impact attenuator, type 1 (bidirectional) (606E60012) | EACH | 18 | $7,850.00 | $7,850.00 | $12,766 | $7,850.00 |
| 15 | Seeding and mulching, as per plan (659E10001) | SY | 630 | $7.65 | $7.65 | $7.65 | $5.00 |
| 16 | Commercial fertilizer (659E20000) | TON | 0.09 | $700.00 | $700.00 | $700.00 | $1,500.00 |
| 17 | Lime (659E31000) | ACRE | 0.13 | $10.00 | $10.00 | $10.00 | $200.00 |
| 18 | Water (659E35000) | MGAL | 4 | $1.00 | $10.00 | $1.00 | $1.00 |
| 19 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 20 | Partial depth pavement repair (asphalt concrete base), as per plan (251E01041) | SY | 2,464 | $70.00 | $70.00 | $78.37 | $90.00 |
| 21 | Partial depth pavement repair (asphalt concrete base), as per plan (251E01041) | SY | 1,479 | $94.00 | $80.00 | $99.42 | $140.00 |
| 22 | Pavement planing, asphalt concrete, 1 1/2" (254E01000) | SY | 338 | $12.00 | $2.00 | $21.09 | $7.00 |
| 23 | Pavement planing, asphalt concrete, as per plan, 1 (254E01001) | SY | 602,113 | $1.60 | $2.10 | $1.42 | $2.00 |
| 24 | Patching planed surface (254E01600) | SY | 12,042 | $1.25 | $1.50 | $4.04 | $6.50 |
| 25 | Full depth pavement removal and rigid replacement, type 2, class QC MS (255E16000) | SY | 375 | $345.00 | $275.00 | $473.23 | $285.00 |
| 26 | Full depth pavement sawing (255E20000) | FT | 240 | $4.00 | $5.99 | $9.17 | $15.00 |
| 27 | Non-tracking tack coat (407E20000) | GAL | 51,211 | $2.65 | $3.50 | $4.62 | $3.00 |
| 29 | Anti-segregation equipment (442E00100) | CY | 15,238 | $1.00 | $8.00 | $8.00 | $15.00 |
| 30 | Asphalt concrete surface course, 12.5 MM, type A (446) (442E10000) | CY | 25,088 | $211.00 | $230.00 | $233.16 | $275.00 |
| 31 | Asphalt concrete surface course, 12.5 MM, type A (449) (442E22100) | CY | 14 | $600.00 | $230.00 | $858.70 | $275.00 |
| 32 | Compacted aggregate (617E10100) | CY | 1,100 | $80.00 | $75.00 | $149.65 | $108.00 |
| 33 | Shoulder preparation (617E20000) | SY | 19,793 | $0.35 | $1.00 | $1.57 | $0.55 |
| 34 | Rumble strips, shoulder (asphalt concrete) (618E40600) | MI | 33.58 | $815.00 | $815.00 | $815.00 | $815.00 |
| 35 | Void reducing asphalt membrane (vram) (872E10000) | FT | 88,652 | $2.10 | $1.90 | $4.20 | $2.93 |
| 36 | RPM (621E00100) | EACH | 1,629 | $36.00 | $36.50 | $36.00 | $36.00 |
| 37 | Raised pavement marker removed (621E54000) | EACH | 1,629 | $1.00 | $6.00 | $11.12 | $8.00 |
| 38 | Barrier reflector, type 2(bidirectional) (626E00110) | EACH | 68 | $12.00 | $12.00 | $13.00 | $12.00 |
| 39 | Barrier reflector, type 2(one-way) (626E00110) | EACH | 81 | $12.00 | $12.00 | $13.00 | $12.00 |
| 42 | Stop line (646E10400) | FT | 192 | $9.50 | $12.00 | $9.50 | $12.00 |
| 43 | Lane arrow (646E20300) | EACH | 14 | $125.00 | $175.00 | $125.00 | $175.00 |
| 44 | Speed measurement marking (644E40000) | EACH | 40 | $500.00 | $200.00 | $855.64 | $375.00 |
| 45 | Wet reflective epoxy pavement marking, edge line, 6" (807E12010) | MI | 3.64 | $3,300.00 | $5,325.00 | $3,300.00 | $5,325.00 |
| 46 | Wet reflective epoxy pavement marking, lane line, 6" (807E12110) | MI | 0.38 | $2,100.00 | $3,155.00 | $2,100.00 | $3,155.00 |
| 47 | Wet reflective epoxy pavement marking, channelizing line, 12" (807E12310) | FT | 3,597 | $1.85 | $2.55 | $1.85 | $2.55 |
| 48 | Wet reflective epoxy pavement marking, dotted line, 6" (807E12410) | FT | 915 | $1.60 | $1.25 | $1.60 | $1.25 |
| 49 | Wet reflective thermoplastic pavement marking, edge line, 6" (807E14010) | MI | 33.61 | $4,080.00 | $4,125.00 | $4,080.00 | $4,125.00 |
| 50 | Wet reflective thermoplastic pavement marking, lane line, 6" (807E14110) | MI | 33.72 | $1,715.00 | $1,410.00 | $1,715.00 | $1,410.00 |
| 51 | Wet reflective thermoplastic pavement marking, channelizing line, 12" (807E14310) | FT | 4,277 | $2.20 | $2.60 | $2.20 | $2.60 |
| 52 | Wet reflective thermoplastic pavement marking, dotted line, 6" (807E14410) | FT | 4,928 | $0.85 | $0.85 | $0.85 | $0.85 |
| 53 | Grooving for 6" recessed pavement marking, (asphalt) (850E10010) | MI | 67.33 | $1,410.00 | $1,390.00 | $1,410.00 | $1,390.00 |
| 54 | Grooving for 6" recessed pavement marking, (asphalt) (850E10110) | FT | 4,840 | $0.80 | $0.90 | $0.80 | $0.90 |
| 55 | Grooving for 12" recessed pavement marking, (asphalt) (850E10130) | FT | 4,277 | $1.65 | $1.30 | $1.65 | $1.30 |
| 56 | Grooving for 6" recessed pavement marking, (concrete) (850E20010) | MI | 4 | $4,000.00 | $1,750.00 | $4,000.00 | $1,750.00 |
| 57 | Grooving for 6" recessed pavement marking, (concrete) (850E20110) | FT | 915 | $1.00 | $0.90 | $1.00 | $0.90 |
| 58 | Grooving for 12" recessed pavement marking, (concrete) (850E20130) | FT | 3,597 | $1.40 | $1.30 | $1.40 | $1.30 |
| 59 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 1,000 | $100.00 | $85.00 | $124.88 | $100.00 |
| 60 | Detour signing, as per plan (614E12421) | LS | 1 | $16,340 | $21,000 | $27,367 | $20,853 |
| 61 | Work zone marking sign (614E12460) | EACH | 20 | $105.72 | $175.00 | $105.72 | $175.00 |
| 62 | Work zone increased penalties sign (614E12484) | EACH | 20 | $249.73 | $325.00 | $249.73 | $325.00 |
| 63 | Replacement sign (614E12500) | EACH | 5 | $239.36 | $250.00 | $239.36 | $250.00 |
| 64 | Replacement drum (614E12600) | EACH | 50 | $50.00 | $50.00 | $55.23 | $50.00 |
| 65 | Portable changeable message sign, as per plan (614E18601) | SNMT | 20 | $800.00 | $625.00 | $750.00 | $750.00 |
| 66 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 33.86 | $660.00 | $550.00 | $660.00 | $550.00 |
| 67 | Work zone channelizing line, class III, 12", 642 paint (614E23690) | FT | 4,277 | $0.75 | $0.95 | $0.75 | $0.95 |
| 68 | Work zone dotted line, class III, 6", 642 paint (614E24612) | FT | 4,928 | $0.50 | $0.80 | $0.50 | $0.80 |
| 69 | Digital speed limit (DSL) sign assembly (808E18700) | SNMT | 50 | $600.00 | $595.00 | $575.00 | $714.00 |
| 70 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $37,000 | $35,749 | $64,050 | $50,000 |
| 71 | Maintaining traffic (614E11000) | LS | 1 | $300,449 | $201,000 | $153,320 | $945,000 |
| 72 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $10,000 | $10,000 | $9,724.23 | $15,000 |
| 73 | Mobilization (624E10000) | LS | 1 | $456,000 | $200,000 | $512,500 | $400,000 |
| 100 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 20 | $20.00 | $50.00 | $56.89 | $250.00 |
| 101 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 33.86 | $890.00 | $690.00 | $890.00 | $690.00 |
| 102 | Removal of pavement marking (642E30000) | FT | 192 | $2.00 | $5.00 | $2.00 | $5.00 |
| 103 | Removal of pavement marking (642E30020) | EACH | 7 | $50.00 | $80.00 | $50.00 | $80.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of December 18, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.