ODOT contract 254033 bid tabulation

KNO-SR 3-25.94 (SIDEWALK). Let by Ohio DOT on December 18, 2025, KNO. 3 bids received; low bid $154,585 by Crawford Construction Company Inc, +0.4% against the engineer's estimate of $154,000.

Owner
Ohio DOT
Letting
18 DEC 2025
Pay items
33
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Crawford Construction Company Inc$154,585Low0.0%
2Rietschlin Construction Inc$158,025+2.0%+3.0%
3Madex Construction Co$224,091+45%+46%
ODOT contract 254033: bids by rank

Engineer's estimate: $154,000.

Bid tabulation

LinePay itemUnitQuantity1. Crawford Construction Company Inc2. Rietschlin Construction Inc3. Madex Construction Co
1Pavement removed, as per plan (202E23001)SY125$42.00$40.00$53.62
2Walk removed (202E30000)SF1,896$3.62$2.50$7.26
3Pipe removed, 24" and under (202E35100)FT20$20.00$50.00$35.85
4Mailbox removed (202E53100)EACH7$100.00$50.00$140.32
5Excavation (203E10000)CY109$70.00$64.00$81.80
6Subgrade compaction (204E10000)SY220$3.30$12.00$10.42
7Full depth pavement sawing (252E01500)FT552$10.00$3.00$5.79
86" concrete walk (608E13000)SF1,896$20.00$12.00$19.51
9Detectable warning (608E53020)SF16$57.00$61.00$57.89
10Curb, type 4-A, as per plan (609E24001)FT552$33.00$60.00$81.05
11Preconstruction survey monument verification and report (623E50000)LS1$835.00$860.00$8,105.26
12Post construction survey monument verification and report (623E51000)LS1$835.00$860.00$5,789.47
13Special - mailbox support system, single (690E50100)EACH3$230.00$655.00$694.74
14Special - mailbox support system, double (690E50200)EACH2$383.00$798.00$926.32
15Topsoil furnished and placed, as per plan (653E10001)CY60$70.00$103.00$86.84
16Soil analysis test (659E00100)EACH2$100.00$110.00$89.47
17Seeding and mulching, class 1 (659E00500)SY535$5.90$7.00$8.11
18Repair seeding and mulching (659E14000)SY27$1.00$7.00$1.16
19Inter-seeding (659E15000)SY27$1.00$7.00$1.16
20Commercial fertilizer (659E20000)TON0.07$660.00$1,300.00$2,857.14
21Lime (659E31000)ACRE0.11$2,500.00$150.00$568.45
22Water (659E35000)MGAL3$18.00$22.00$7.53
23Erosion control (832E30000)EACH5,000$1.00$1.00$1.00
244" conduit, type D (611E00300)FT20$45.00$61.00$47.89
25Aggregate base (304E20000)CY25$138.00$220.00$183.68
26Stabilized crushed aggregate (411E10000)CY26$178.00$210.00$183.68
276" non-reinforced concrete pavement, class QC MS (452E10050)SY67$110.00$136.00$156.32
28Ground mounted support, no. 3 post, as per plan (630E03101)FT10.50$26.00$80.00$86.84
29Removal of ground mounted sign and reerection (630E85100)EACH1$115.00$105.00$115.79
30Premium for contract performance bond and for payment bond (103E05000)LS1$2,800.00$2,000.00$8,094.74
31Maintaining traffic (614E11000)LS1$9,100.00$20,000$12,113
32Construction layout stakes and surveying (623E10000)LS1$5,400.00$2,600.00$9,947.37
33Mobilization (624E10000)LS1$20,300$11,000$19,974
ODOT contract 254033: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of December 18, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy