ODOT contract 254032 bid tabulation
FAI-US 22-03.68 (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on December 18, 2025, FAI. 4 bids received; low bid $1,795,146 by Alan Stone Co Inc, -2.4% against the engineer's estimate of $1,840,000.
- Owner
- Ohio DOT
- Letting
- 18 DEC 2025
- Pay items
- 72
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Alan Stone Co Inc | $1,795,146 | Low | -2.0% |
| 2 | Rietschlin Construction Inc | $1,823,052 | +2.0% | -1.0% |
| 3 | Axis Civil Construction LLC | $2,091,667 | +17% | +14% |
| 4 | Orders Construction Company Inc | $2,999,569 | +67% | +63% |
Engineer's estimate: $1,840,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Alan Stone Co Inc | 2. Rietschlin Construction Inc | 3. Axis Civil Construction LLC | 4. Orders Construction Company Inc |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $20,000 | $7,700.00 | $15,000 | $363,000 |
| 2 | Pavement removed (202E23000) | SY | 1,671 | $10.00 | $18.00 | $24.00 | $5.90 |
| 3 | Wearing course removed (202E23500) | SY | 325 | $4.00 | $9.00 | $10.00 | $12.00 |
| 4 | Guardrail removed (202E38000) | FT | 419 | $10.00 | $6.00 | $7.00 | $14.00 |
| 5 | Excavation (203E10000) | CY | 749 | $50.00 | $25.00 | $28.00 | $54.00 |
| 6 | Embankment (203E20000) | CY | 733 | $9.00 | $17.00 | $28.00 | $41.00 |
| 7 | Subgrade compaction (204E10000) | SY | 1,299 | $5.00 | $3.00 | $3.00 | $4.60 |
| 8 | Subgrade compaction (204E10000) | SY | 1,099 | $9.50 | $3.00 | $3.00 | $5.40 |
| 9 | Excavation of subgrade (204E13000) | CY | 349 | $30.00 | $27.00 | $30.00 | $46.00 |
| 10 | Granular material, type B (204E30010) | CY | 349 | $95.00 | $82.00 | $82.00 | $95.00 |
| 11 | Geogrid (204E51000) | SY | 1,099 | $8.00 | $5.00 | $1.00 | $7.50 |
| 12 | Reshaping under guardrail (209E15000) | STA | 7 | $460.00 | $290.00 | $700.00 | $630.00 |
| 13 | Guardrail, type MGS (606E15050) | FT | 375 | $25.00 | $23.50 | $21.00 | $22.00 |
| 14 | Anchor assembly, MGS type E (MASH 2016) (606E26150) | EACH | 4 | $3,000.00 | $2,775.00 | $2,500.00 | $2,700.00 |
| 15 | MGS bridge terminal assembly, type TST-2 (606E34600) | EACH | 4 | $3,000.00 | $2,775.00 | $2,500.00 | $2,600.00 |
| 16 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $5,400.00 | $1,400.00 | $1,600.00 | $5,300.00 |
| 17 | Post construction survey monument verification and report (623E51000) | LS | 1 | $5,400.00 | $1,400.00 | $1,600.00 | $5,300.00 |
| 18 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 434 | $110.00 | $108.00 | $118.00 | $140.00 |
| 19 | Seeding and mulching, class 2 (659E00510) | SY | 2,307 | $2.00 | $2.75 | $1.40 | $4.20 |
| 20 | Commercial fertilizer (659E20000) | TON | 0.31 | $670.00 | $1,000.00 | $1,250.00 | $700.00 |
| 21 | Lime (659E31000) | ACRE | 0.47 | $960.00 | $180.00 | $150.00 | $93.00 |
| 22 | Water (659E35000) | MGAL | 6.20 | $120.00 | $1.25 | $1.00 | $1.20 |
| 23 | Erosion control (832E30000) | EACH | 4,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 24 | Full depth pavement sawing (252E01500) | FT | 52 | $5.00 | $28.00 | $4.00 | $27.00 |
| 25 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 328 | $270.00 | $212.00 | $190.00 | $220.00 |
| 26 | Aggregate base (304E20000) | CY | 794 | $75.00 | $92.00 | $110.00 | $90.00 |
| 27 | Non-tracking tack coat (407E20000) | GAL | 231 | $6.50 | $5.00 | $4.00 | $4.60 |
| 28 | Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100) | CY | 80 | $330.00 | $318.00 | $285.00 | $320.00 |
| 29 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 93 | $300.00 | $284.00 | $250.00 | $290.00 |
| 30 | Raised pavement marker removed (621E54000) | EACH | 11 | $100.00 | $38.00 | $100.00 | $130.00 |
| 31 | Barrier reflector, type 2, bidirectional (626E00110) | EACH | 12 | $15.00 | $14.00 | $12.00 | $21.00 |
| 32 | Ground mounted support, no. 3 post, as per plan (630E03101) | FT | 48 | $20.00 | $20.00 | $17.50 | $21.00 |
| 33 | Sign, flat sheet (630E80100) | SF | 2 | $50.00 | $45.00 | $40.00 | $26.00 |
| 34 | Removal of ground mounted sign and disposal (630E84900) | EACH | 1 | $25.00 | $23.00 | $20.00 | $460.00 |
| 35 | Removal of ground mounted sign and reerection, as per plan (630E85101) | EACH | 4 | $40.00 | $39.00 | $35.10 | $90.00 |
| 36 | Removal of ground mounted post support and disposal, as per plan (630E86003) | EACH | 4 | $25.00 | $23.00 | $20.00 | $250.00 |
| 37 | Edge line, 6" (646E10010) | MI | 0.26 | $9,800.00 | $9,400.00 | $8,250.00 | $7,900.00 |
| 38 | Center line (646E10200) | MI | 0.13 | $15,000 | $12,500 | $13,000 | $16,000 |
| 39 | Traffic compacted surface, type C (410E13000) | CY | 10 | $310.00 | $86.00 | $60.00 | $560.00 |
| 40 | Detour signing (614E12420) | LS | 1 | $13,000 | $8,000.00 | $4,800.00 | $5,100.00 |
| 41 | Asphalt concrete for maintaining traffic (614E13000) | CY | 20 | $540.00 | $300.00 | $150.00 | $670.00 |
| 42 | Portable changeable message sign, as per plan (614E18601) | SNMT | 6 | $770.00 | $1,100.00 | $1,500.00 | $1,600.00 |
| 43 | Structure removed, over 20 foot span, as per plan (202E11003) | LS | 1 | $39,000 | $70,000 | $75,000 | $110,000 |
| 44 | Approach slab removed (202E22900) | SY | 80 | $90.00 | $70.00 | $65.00 | $150.00 |
| 45 | Bridge railing removed (202E38500) | FT | 171 | $5.50 | $12.00 | $30.00 | $27.00 |
| 46 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $18,000 | $70,000 | $50,000 | $79,000 |
| 47 | Unclassified excavation (503E21300) | LS | 1 | $9,300.00 | $81,000 | $25,000 | $70,000 |
| 48 | Pile driving equipment mobilization (505E11100) | LS | 1 | $20,000 | $80,000 | $105,000 | $38,000 |
| 49 | Piling, misc.: 18 inch open-ended steel pipe piles (507E98000) | FT | 1,730 | $80.00 | $20.00 | $40.00 | $150.00 |
| 50 | Piling, misc.: 18 inch open-ended steel pipe piles (507E98000) | FT | 1,850 | $142.00 | $150.00 | $155.00 | $120.00 |
| 51 | Epoxy coated reinforcing steel, as per plan (509E10001) | LB | 47,015 | $2.00 | $2.00 | $1.70 | $2.20 |
| 52 | Class QC2 concrete with QC/QA, superstructure (511E33312) | CY | 166 | $1,700.00 | $1,260.00 | $2,100.00 | $2,700.00 |
| 53 | Class QC1 concrete, abutment not including footing (511E44110) | CY | 49 | $870.00 | $765.00 | $1,280.00 | $3,200.00 |
| 54 | Class QC1 concrete, footing (511E46510) | CY | 40 | $800.00 | $765.00 | $1,050.00 | $930.00 |
| 55 | Sealing of concrete surfaces (non-epoxy) (512E10050) | SY | 111 | $50.00 | $26.50 | $23.50 | $130.00 |
| 56 | Type A waterproofing (512E33300) | SY | 17 | $120.00 | $86.00 | $35.00 | $220.00 |
| 57 | 1" preformed expansion joint filler, as per plan (516E13601) | SF | 131 | $20.00 | $43.00 | $22.00 | $35.00 |
| 58 | Integral abutment expansion joint seal (516E14014) | FT | 82 | $55.00 | $39.50 | $50.00 | $80.00 |
| 59 | Structural joint or joint sealer, misc.: emseal WI (516E14600) | FT | 64 | $520.00 | $582.00 | $500.00 | $660.00 |
| 60 | 2" deep joint sealer, as per plan (516E31011) | FT | 64 | $35.00 | $29.00 | $30.00 | $43.00 |
| 61 | Elastomeric bearing pad, misc.: 8" X 1.5" (516E42600) | FT | 70 | $130.00 | $104.00 | $130.00 | $200.00 |
| 62 | Railing (three steel tube bridge railing) (517E70100) | FT | 176 | $475.00 | $475.00 | $428.00 | $500.00 |
| 63 | Porous backfill with geotextile fabric (518E21200) | CY | 46 | $120.00 | $115.00 | $180.00 | $160.00 |
| 64 | Special - steel drip strip (518E22300) | FT | 192 | $35.00 | $16.00 | $25.00 | $42.00 |
| 65 | 6" perforated corrugated plastic pipe (518E40000) | FT | 104 | $15.00 | $18.00 | $12.00 | $51.00 |
| 66 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 112 | $15.00 | $23.00 | $12.00 | $69.00 |
| 67 | Dynamic load testing, as per plan (523E20001) | EACH | 24 | $1,200.00 | $1,225.00 | $3,700.00 | $1,500.00 |
| 68 | Reinforced concrete approach slabs (T=15"), as per plan (526E25001) | SY | 178 | $470.00 | $351.00 | $495.00 | $530.00 |
| 69 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $15,000 | $20,000 | $15,000 | $15,000 |
| 70 | Maintaining traffic (614E11000) | LS | 1 | $9,300.00 | $5,000.00 | $12,000 | $17,000 |
| 71 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $15,000 | $15,000 | $23,500 | $64,000 |
| 72 | Mobilization (624E10000) | LS | 1 | $35,000 | $100,000 | $100,000 | $145,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of December 18, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way