ODOT contract 254034 bid tabulation

MOE-SR 78-08.35 (SLIDE REPAIR). Let by Ohio DOT on December 18, 2025, MOE. 4 bids received; low bid $426,626 by S.T.A.R.T., LLC, +0.1% against the engineer's estimate of $426,000.

Owner
Ohio DOT
Letting
18 DEC 2025
Pay items
47
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1S.T.A.R.T., LLC$426,626Low0.0%
2Alan Stone Co Inc$463,758+9.0%+9.0%
3LMS Construction Inc$514,447+21%+21%
4R C Construction Company and Son Inc$685,527+61%+61%
ODOT contract 254034: bids by rank

Engineer's estimate: $426,000.

Bid tabulation

LinePay itemUnitQuantity1. S.T.A.R.T., LLC2. Alan Stone Co Inc3. LMS Construction Inc4. R C Construction Company and Son Inc
1Clearing and grubbing (201E11000)LS1$16,500$15,000$33,000$25,000
2Pavement removed (202E23000)SY197$25.48$10.00$14.00$30.00
3Guardrail removed (202E38000)FT250$2.53$7.50$1.00$5.00
4Anchor assembly removed (202E42206)EACH1$180.00$470.00$100.00$1,000.00
5Excavation (203E10000)CY1,971$24.71$25.00$20.00$25.00
6Embankment (203E20000)CY1,000$26.69$15.00$22.00$30.00
7Subgrade compaction (204E10000)SY261$9.92$5.00$5.00$2.00
8Guardrail, type MGS (606E15050)FT187.50$24.87$30.00$22.00$30.00
9Guardrail, type MGS with long posts (606E15100)FT200$27.20$30.00$25.00$32.00
10Anchor assembly, MGS type E (606E26150)EACH1$3,610.00$3,700.00$2,300.00$3,000.00
11Seeding and mulching (659E10000)SY1,739$2.10$2.00$2.50$10.00
12Commercial fertilizer (659E20000)TON0.24$1,749.00$650.00$800.00$2,500.00
13Lime (659E31000)ACRE0.36$1,218.75$930.00$200.00$2,000.00
14Water (659E35000)MGAL10$1.00$120.00$2.00$1.00
15Erosion control (832E30000)EACH3,000$1.00$1.00$1.00$1.00
16Granular embankment, as per plan (203E35001)CY212$91.29$110.00$150.00$200.00
17Granular material, type C, as per plan (203E35121)CY161$118.54$100.00$140.00$200.00
18Geotextile fabric, as per plan (204E50001)SY936$2.56$1.00$3.00$10.00
19Tied concrete block mat with type 1 underlayment (601E21050)SY4$511.63$220.00$200.00$200.00
20Dumped rock fill, type C, as per plan (601E27001)CY1,213$62.81$90.00$125.00$150.00
216" conduit, type F for underdrain outlets (611E00510)FT32$30.06$50.00$30.00$40.00
226" conduit, type E (611E01400)FT450$10.32$10.00$25.00$40.00
23Precast reinforced concrete outlet (611E99710)EACH2$626.88$900.00$250.00$375.00
24Pavement planing, asphalt concrete (1 1/2") (254E01000)SY1,231$9.45$12.00$7.00$25.00
25Asphalt concrete base, PG64-22, (449) (301E56000)CY42$515.00$420.00$450.00$575.00
26Aggregate base (304E20000)CY44$185.26$150.00$175.00$150.00
27Tack coat (407E10000)GAL132$4.20$4.00$3.00$10.00
28Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000)CY72$506.00$400.00$475.00$600.00
29Aggregate drains (605E31100)FT26$100.06$70.00$20.00$50.00
30Ground mounted support, no. 3 post (630E03100)FT12$20.00$25.00$20.00$40.00
31Sign post reflector (630E08600)EACH2$45.00$50.00$28.00$250.00
32Sign, flat sheet (630E80100)SF9$25.00$30.00$20.00$250.00
33Removal of ground mounted sign and disposal (630E84900)EACH1$10.00$10.00$10.00$50.00
34Removal of ground mounted post support and disposal (630E86002)EACH1$15.00$15.00$10.00$50.00
35Edge line, 6", type 1 (642E00104)MI0.18$13,011$3,900.00$2,500.00$28,000
36Center line, type 1 (642E00300)MI0.09$15,570$7,400.00$5,500.00$28,000
37Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384)EACH2$2,380.78$3,600.00$2,400.00$3,000.00
38Work zone lighting system (614E12740)EACH1$5,169.00$1,700.00$3,000.00$20,000
39Barrier reflector, type 1, (two way) (614E13310)EACH10$11.64$35.00$25.00$50.00
40Object marker, two way (614E13360)EACH10$19.88$40.00$30.00$50.00
41Work zone edge line, class I, 6", 740.06, type I (614E22210)MI0.18$11,400$12,000$8,000.00$25,000
42Work zone stop line, class I, 740.06, type I (614E26400)FT22$7.03$15.00$5.00$100.00
43Portable barrier, unanchored (622E41100)FT390$39.00$30.77$40.00$35.00
44Premium for contract performance bond and for payment bond (103E05000)LS1$7,050.00$7,000.00$20,000$18,500
45Maintaining traffic (614E11000)LS1$30,360$65,000$25,000$25,000
46Construction layout stakes and surveying (623E10000)LS1$8,500.00$8,700.00$2,000.00$15,000
47Mobilization (624E10000)LS1$20,250$20,000$30,000$25,000
ODOT contract 254034: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of December 18, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy