ODOT contract 260141 bid tabulation

ROS-US 35/US 50 Interchange TP (PARKING AREAS). Let by Ohio DOT on March 12, 2026, ROS. 4 bids received; low bid $3,084,299 by Shelly & Sands Inc, -11% against the engineer's estimate of $3,458,000.

Owner
Ohio DOT
Letting
12 MAR 2026
Pay items
96
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Shelly & Sands Inc$3,084,299Low-11%
2Allard Excavation LLC$3,195,377+4.0%-8.0%
3Complete General Construction Company$3,548,830+15%+3.0%
4Boss Excavating & Grading Inc$3,819,811+24%+10%
ODOT contract 260141: bids by rank

Engineer's estimate: $3,458,000.

Bid tabulation

LinePay itemUnitQuantity1. Shelly & Sands Inc2. Allard Excavation LLC3. Complete General Construction Company4. Boss Excavating & Grading Inc
1Clearing and grubbing, as per plan (201E11001)LS1$48,000$3,507.00$7,500.00$4,985.61
2Pavement removed (202E23000)SY3,355$10.00$4.00$9.00$9.19
3Pipe removed, 24" and under (202E35100)FT109$27.00$2.00$24.00$25.50
4Guardrail removed (202E38000)FT25$17.00$4.00$18.00$14.53
5Fence removed (202E75000)FT1,210$3.50$2.00$4.00$5.37
6Excavation (203E10000)CY3,279$10.00$14.00$12.00$20.00
7Embankment (203E20000)CY47,721$12.75$19.00$22.00$28.03
8Subgrade compaction (204E10000)SY21,379$2.00$1.00$1.75$1.09
9Excavation of subgrade (204E13000)CY100$38.00$20.00$44.00$8.89
10Granular material, type C (204E30020)CY100$85.00$68.00$79.00$70.85
11Proof rolling (204E45000)HR8$1,350.00$244.00$360.00$276.96
12Geotextile fabric (204E50000)SY500$1.25$1.00$2.00$1.77
13Fence, misc.:wooden slat fence (607E98000)FT47$193.00$193.00$193.00$112.13
14Monument assembly adjusted to grade (623E39500)EACH6$1,700.00$754.00$350.00$560.63
15Monument assembly removed and reset (623E40000)EACH2$2,275.00$1,641.00$1,300.00$560.63
16Reference monument, type A (623E40500)EACH6$550.00$1,202.00$1,250.00$1,121.25
17Preconstruction survey monument verification and report (623E50000)LS1$3,000.00$7,000.00$2,700.00$11,213
18Post construction survey monument verification and report (623E51000)LS1$3,000.00$7,000.00$2,700.00$4,372.89
19Special - bollard (690E50600)EACH4$965.00$1,200.00$965.00$1,479.88
20Inspection and compaction testing of unbound materials (878E25000)LS1$49,000$66,864$80,000$20,183
21Tied concrete block mat with type 1 underlayment (601E21050)SY6$110.00$135.00$170.00$146.29
22Rock channel protection, type C with geotextile fabric (601E32204)CY71$130.00$79.00$135.00$109.80
23Soil analysis test (659E00100)EACH2$150.00$300.00$150.00$224.25
24Topsoil (659E00300)CY553$20.00$28.00$32.00$8.58
25Seeding and mulching (659E10000)SY4,922$0.80$0.80$0.80$1.85
26Repair seeding and mulching (659E14000)SY247$0.80$0.80$0.80$1.12
27Inter-seeding (659E15000)SY247$0.80$0.80$0.80$0.01
28Commercial fertilizer (659E20000)TON1.11$1,250.00$1,250.00$1,250.00$1,681.88
29Lime (659E31000)ACRE1.02$150.00$150.00$150.00$224.25
30Water (659E35000)MGAL28$1.00$1.00$1.00$1.12
31Slope erosion protection (670E00500)SY51$2.50$2.50$2.50$2.63
32Storm water pollution prevention plan (832E15000)LS1$1,600.00$1,500.00$1,500.00$4,485.02
33Storm water pollution prevention inspections (832E15002)LS1$6,500.00$6,000.00$6,000.00$5,382.02
34Storm water pollution prevention inspection software (832E15010)LS1$10,000$5,100.00$9,400.00$10,511
35Erosion control (832E30000)EACH60,000$1.00$1.00$1.00$1.00
36Concrete masonry (602E20000)CY0.30$4,400.00$7,906.00$4,750.00$3,441.60
376" base pipe underdrains (605E14000)FT9,554$12.00$10.00$11.00$12.31
386" conduit, type F for underdrain outlets (611E00510)FT86$32.00$33.00$28.00$22.10
3912" conduit, type B (611E04400)FT4$500.00$76.00$230.00$164.92
4012" conduit, type C (611E04600)FT161$79.00$63.00$93.00$49.42
4115" conduit, type B (611E05900)FT150$96.00$89.00$120.00$67.75
4215" conduit, type B (611E05900)FT4$506.00$94.00$235.00$194.36
4318" conduit, type B (611E07400)FT257$96.00$116.00$140.00$72.74
44Catch basin, no. 2-2B (611E98470)EACH1$3,530.00$4,443.00$3,570.00$1,912.22
45Catch basin, no. 2-2C (611E98504)EACH1$3,850.00$4,392.00$3,760.00$1,912.22
46Manhole, no. 3 (611E99574)EACH2$4,300.00$5,216.00$5,230.00$3,218.39
47Precast reinforced concrete outlet (611E99710)EACH3$615.00$365.00$400.00$443.14
48Asphalt concrete base, PG64-22, (449) (301E56000)CY414$155.50$188.00$188.00$216.40
49Aggregate base (304E20000)CY3,499$68.00$68.00$72.00$51.19
50Non-tracking tack coat (407E20000)GAL280$3.50$4.10$4.10$4.60
51Asphalt concrete surface course, type 1, (449), (driveways) (441E70500)CY6$550.00$615.00$615.00$689.57
52Asphalt concrete surface course, 12.5 MM, type A (446) (442E10000)CY102$290.00$285.00$285.00$330.77
53Asphalt concrete intermediate course, 19 MM, type A (446) (442E10100)CY170$195.00$303.00$303.00$353.19
548" non-reinforced concrete pavement, class QC 1P (452E12010)SY30$220.00$175.00$130.00$117.73
55Curb, type 7 (609E28000)FT1,825$33.00$18.00$35.00$28.03
56Connection, fused pull apart (625E00450)EACH8$166.00$166.00$145.00$186.13
57Light pole (installation only), as per plan (625E10503)EACH4$690.00$690.00$500.00$773.67
58Light pole (installation only), as per plan (625E10503)EACH11$1,205.00$1,205.00$1,000.00$1,351.11
59Light pole foundation, 24" X 8' deep (625E14100)EACH4$2,272.00$2,272.00$3,700.00$2,547.49
60Light tower foundation, misc.: 36" X 10' deep (625E15700)EACH11$6,090.00$6,090.00$7,900.00$6,828.44
61No. 4 AWG 2400 volt distribution cable (625E23200)FT7,167$4.01$4.01$3.40$4.50
62No. 10 AWG pole and bracket cable (625E23400)FT576$5.31$5.31$2.50$5.95
63Conduit, 2", 725.04 (625E25400)FT2,209$20.81$20.81$24.00$23.33
64Luminaire, conventional, solid state (LED), as per plan (625E26253)EACH4$604.00$604.00$475.00$677.24
65Luminaire, high mast, solid state (LED), as per plan (625E26263)EACH11$1,540.00$1,540.00$1,050.00$1,726.73
66Trench, 24" deep (625E29002)FT2,209$8.76$8.76$9.00$9.86
67Pull box, 725.08, 18" (625E30700)EACH2$1,342.00$1,342.00$1,375.00$1,504.73
68Ground rod (625E32000)EACH15$436.00$436.00$325.00$488.87
69Power service, as per plan (625E34001)EACH1$11,376$11,376$9,500.00$12,755
70Underground warning marking tape (625E36010)FT2,209$0.25$0.10$1.50$0.11
71Arc flash calculations and label, ros-US35/US50 in (625E76000)EACH1$3,655.00$3,655.00$3,625.00$4,098.18
72Ground mounted support, no. 3 post (630E03100)FT143.50$17.00$17.00$17.00$29.15
73Ground mounted structural beam support, W10X22 (630E07500)FT100.90$73.00$73.00$73.00$117.73
74Ground mounted structural beam support, W10X12 (630E07600)FT99.10$58.00$58.00$58.00$78.49
75Sign post reflector (630E08600)EACH1$50.00$50.00$50.00$151.37
76Breakaway structural beam connection (630E09000)EACH4$880.00$880.00$880.00$1,681.88
77Sign, flat sheet (630E80100)SF69.90$20.00$20.00$20.00$40.37
78Sign, ground mounted extrusheet (630E80200)SF372$27.00$27.00$27.00$51.58
79Ground mounted structural beam support foundation (630E84500)EACH8$1,050.00$1,050.00$1,050.00$3,139.51
80Removal of ground mounted sign and disposal (630E84900)EACH2$15.00$12.00$15.00$95.31
81Removal of ground mounted post support and disposal (630E86002)EACH2$25.00$12.00$25.00$95.31
82Traffic compacted surface, type A (410E10000)CY25$135.00$68.00$150.00$45.68
83Water (616E10000)MGAL101$100.00$1.00$90.00$1.08
84Asphalt concrete base, PG64-22, (449) (301E56000)CY2,979$146.50$154.00$154.00$181.08
85Non-tracking tack coat (407E20000)GAL1,980$3.50$4.10$4.10$4.60
86Asphalt concrete surface course, 12.5 MM, type A (446) (442E10000)CY745$251.50$213.00$213.00$247.80
87Asphalt concrete intermediate course, 19 MM, type A (446) (442E10100)CY1,241$176.00$200.00$200.00$233.22
88Center line (644E00300)MI0.14$12,000$5,300.00$5,300.00$13,455
89Stop line (644E00500)FT32$9.00$5.50$5.50$16.82
90Transverse/diagonal line (644E00700)FT5,050$5.50$1.00$1.00$5.77
91Parking lot stall marking (644E01200)FT4,682$2.00$1.00$1.00$2.24
97Premium for contract performance bond and for payment bond (103E05000)LS1$18,891$22,000$23,000$42,608
98Maintaining traffic (614E11000)LS1$15,009$46,610$25,000$5,332.60
99Field office, type A (619E16000)MNTH6$3,200.00$1,760.00$1,800.00$4,040.91
100Construction layout stakes and surveying (623E10000)LS1$85,000$56,438$32,500$30,554
101Mobilization (624E10000)LS1$154,000$70,000$177,000$70,000
ODOT contract 260141: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of March 12, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy