ODOT contract 268003 bid tabulation
AUG-US 33/Willipie St Infield TP (PARKING AREAS). Let by Ohio DOT on March 12, 2026, AUG. 5 bids received.
- Owner
- Ohio DOT
- Letting
- 12 MAR 2026
- Pay items
- 87
- Data through
- 12 NOV 2026
1 of the 5 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 2 | Eagle Bridge Co | $2,445,787 | +1.0% | -5.0% |
Engineer's estimate: $2,578,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Eagle Bridge Co |
|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $5,000.00 |
| 2 | Pavement removed (202E23000) | SY | 267 | $30.00 |
| 3 | Concrete median removed (202E30600) | SY | 8 | $90.00 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 143 | $30.00 |
| 5 | Excavation (203E10000) | CY | 2,884 | $18.00 |
| 6 | Embankment (203E20000) | CY | 2,512 | $18.00 |
| 7 | Subgrade compaction (204E10000) | SY | 110 | $12.00 |
| 8 | Proof rolling (204E45000) | HR | 7 | $300.00 |
| 9 | Cement (206E10500) | TON | 478 | $220.00 |
| 10 | Curing coat (206E11000) | SY | 18,452 | $1.30 |
| 11 | Cement stabilized subgrade, 12 inches deep (206E15010) | SY | 18,452 | $5.50 |
| 12 | Mixture design for chemically stabilized soils (206E30000) | LS | 1 | $9,500.00 |
| 13 | Fence, misc.: wooden slat fence (607E98000) | FT | 56 | $156.00 |
| 14 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $3,500.00 |
| 15 | Post construction survey monument verification and report (623E51000) | LS | 1 | $3,500.00 |
| 16 | Special - bollard (690E50600) | EACH | 5 | $975.00 |
| 17 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 229 | $100.00 |
| 18 | Topsoil (659E00300) | CY | 987 | $10.00 |
| 19 | Seeding and mulching (659E10000) | SY | 8,500 | $2.00 |
| 20 | Repair seeding and mulching (659E14000) | SY | 425 | $3.00 |
| 21 | Inter-seeding (659E15000) | SY | 425 | $3.00 |
| 22 | Commercial fertilizer (659E20000) | TON | 1.20 | $1,500.00 |
| 23 | Lime (659E31000) | ACRE | 1.80 | $5.00 |
| 24 | Water (659E35000) | MGAL | 47 | $15.00 |
| 25 | Ditch erosion protection (670E00700) | SY | 526 | $3.50 |
| 26 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,500.00 |
| 27 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $10,000 |
| 28 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $11,000 |
| 29 | Erosion control (832E30000) | EACH | 30,000 | $1.00 |
| 30 | Concrete masonry (602E20000) | CY | 1 | $2,500.00 |
| 31 | 6" shallow pipe underdrains (605E11100) | FT | 4,767 | $13.00 |
| 32 | 6" unclassified pipe underdrains (605E13300) | FT | 1,991 | $13.00 |
| 33 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 475 | $20.00 |
| 34 | 12" conduit, type A (611E04200) | FT | 142 | $100.00 |
| 35 | 12" conduit, type B (611E04400) | FT | 130 | $90.00 |
| 36 | 12" conduit, type D, as per plan (611E04901) | FT | 106 | $200.00 |
| 37 | 24" conduit, type B (611E10400) | FT | 54 | $200.00 |
| 38 | 24" conduit, type C (611E10600) | FT | 221 | $125.00 |
| 39 | Catch basin, no. 3, as per plan (611E98151) | EACH | 6 | $5,000.00 |
| 40 | Catch basin, no. 2-3 (611E98510) | EACH | 1 | $2,750.00 |
| 41 | Catch basin reconstructed to grade (611E98634) | EACH | 1 | $1,000.00 |
| 42 | Drainage structure, misc.: curb cut (611E99900) | EACH | 14 | $500.00 |
| 43 | Full depth pavement sawing (255E20000) | FT | 291 | $3.00 |
| 44 | Aggregate base (304E20000) | CY | 3,093 | $48.45 |
| 45 | 8" non-reinforced concrete pavement, class QC 1P (452E12010) | SY | 89 | $77.00 |
| 46 | Curb, type 7 (609E28000) | FT | 2,209 | $20.00 |
| 47 | 6" concrete traffic island (609E54000) | SY | 8 | $80.00 |
| 48 | 4" concrete median (609E70000) | SY | 575 | $60.00 |
| 49 | Connection, unfused bolted (625E00470) | EACH | 15 | $145.00 |
| 50 | Light tower, misc.: installation only, BB45 (625E13500) | EACH | 7 | $2,200.00 |
| 51 | Light tower foundation, misc.: 36" X 10' deep (625E15700) | EACH | 7 | $8,000.00 |
| 52 | No. 4 AWG 2400 volt distribution cable (625E23200) | FT | 1,143 | $3.25 |
| 53 | 1-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320) | FT | 1,657 | $16.00 |
| 54 | Conduit, 2", 725.051 (625E25408) | FT | 217 | $12.00 |
| 55 | Conduit, jacked or drilled, 725.051, 2" (625E25906) | FT | 124 | $35.00 |
| 56 | Luminaire, high mast, solid state (LED), type V (625E26262) | EACH | 14 | $1,000.00 |
| 57 | Trench (625E29000) | FT | 1,780 | $5.50 |
| 58 | Pull box, 725.08, 18" (625E30700) | EACH | 8 | $1,350.00 |
| 59 | Ground rod (625E32000) | EACH | 8 | $335.00 |
| 60 | Power service, as per plan (625E34001) | EACH | 1 | $6,500.00 |
| 61 | Control center cabinet, complete (625E34450) | EACH | 1 | $3,750.00 |
| 62 | Underground warning marking tape (625E36010) | FT | 1,780 | $1.75 |
| 63 | Arc flash calculations and label, lighting power S (625E76000) | EACH | 1 | $3,500.00 |
| 64 | Power cable, 1 conductor, no. 4 AWG (632E69100) | FT | 729 | $5.00 |
| 65 | Ground mounted support, no. 3 post (630E03100) | FT | 448 | $16.00 |
| 66 | Ground mounted structural beam support, W8X18 (630E07000) | FT | 324 | $60.00 |
| 67 | Ground mounted structural beam support, W10X22 (630E07500) | FT | 207 | $70.00 |
| 68 | Sign post reflector (630E08600) | EACH | 7 | $45.00 |
| 69 | Breakaway structural beam connection (630E09000) | EACH | 22 | $780.00 |
| 70 | Sign, flat sheet (630E80100) | SF | 188 | $20.50 |
| 71 | Sign, ground mounted extrusheet (630E80200) | SF | 1,098 | $28.50 |
| 72 | Ground mounted structural beam support foundation (630E84500) | EACH | 22 | $885.00 |
| 73 | Detour signing (614E12420) | LS | 1 | $5,000.00 |
| 74 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 3,046 | $169.54 |
| 75 | Non-tracking tack coat (407E20000) | GAL | 2,255 | $2.42 |
| 76 | Asphalt concrete surface course, 12.5 MM, type A (446) (442E10000) | CY | 752 | $251.70 |
| 77 | Asphalt concrete intermediate course, 19 MM, type A (446) (442E10100) | CY | 1,253 | $222.66 |
| 78 | Edge line, 6" (644E00104) | MI | 0.06 | $16,708 |
| 79 | Center line (644E00300) | MI | 0.02 | $5,375.00 |
| 80 | Channelizing line, 12" (644E00404) | FT | 1,473 | $1.70 |
| 81 | Stop line (644E00500) | FT | 75 | $5.50 |
| 82 | Parking lot stall marking (644E01200) | FT | 6,200 | $1.15 |
| 83 | Lane arrow (644E01300) | EACH | 14 | $125.00 |
| 91 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $50,000 |
| 92 | Maintaining traffic (614E11000) | LS | 1 | $7,500.00 |
| 93 | Construction layout stakes and surveying (623E10000) | LS | 1 | $30,000 |
| 94 | Mobilization (624E10000) | LS | 1 | $115,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of March 12, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.