ODOT contract 260476 bid tabulation
WOO-SR 281-11.91 Structure Repl (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on October 29, 2026, WOO. 7 bids received; low bid $952,236 by Great Lakes Demolition Company, -32% against the engineer's estimate of $1,405,000.
- Owner
- Ohio DOT
- Letting
- 29 OCT 2026
- Pay items
- 73
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Great Lakes Demolition Company | $952,236 | Low | -32% |
| 2 | R & I Construction Inc | $1,003,615 | +5.0% | -29% |
| 3 | Eagle Bridge Co | $1,044,336 | +10% | -26% |
| 4 | Crawford Construction Company Inc | $1,149,606 | +21% | -18% |
| 5 | Vernon Nagel Inc | $1,167,366 | +23% | -17% |
| 6 | R G Zachrich Construction Inc | $1,183,723 | +24% | -16% |
| 7 | Mosser Construction Inc | $1,190,641 | +25% | -15% |
Engineer's estimate: $1,405,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Great Lakes Demolition Company | 2. R & I Construction Inc | 3. Eagle Bridge Co | 4. Crawford Construction Company Inc | 5. Vernon Nagel Inc | 6. R G Zachrich Construction Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $1,000.00 | $1,000.00 | $50.00 | $2,200.00 | $6,000.00 | $1,000.00 |
| 2 | Pavement removed (202E23000) | SY | 1,484 | $15.00 | $7.00 | $7.00 | $19.00 | $15.00 | $10.00 |
| 3 | Guardrail removed (202E38000) | FT | 419 | $2.00 | $2.00 | $4.00 | $10.00 | $4.00 | $10.00 |
| 4 | Excavation (203E10000) | CY | 616 | $20.00 | $6.00 | $15.00 | $26.00 | $25.00 | $20.00 |
| 5 | Excavation, as per plan (203E10001) | CY | 115 | $20.00 | $6.00 | $20.00 | $64.00 | $30.00 | $20.00 |
| 6 | Embankment (203E20000) | CY | 478 | $25.00 | $20.00 | $25.00 | $42.00 | $15.00 | $25.00 |
| 7 | Embankment, as per plan (203E20001) | CY | 115 | $25.00 | $50.00 | $25.00 | $42.00 | $25.00 | $70.00 |
| 8 | Granular material, type C (203E35120) | CY | 554 | $70.00 | $64.00 | $50.00 | $80.00 | $70.00 | $30.00 |
| 9 | Subgrade compaction (204E10000) | SY | 1,806 | $1.00 | $2.00 | $4.00 | $2.00 | $1.00 | $2.50 |
| 10 | Excavation of subgrade (204E13000) | CY | 554 | $25.00 | $6.00 | $23.00 | $48.00 | $35.00 | $70.00 |
| 11 | Proof rolling (204E45000) | HR | 2 | $200.00 | $25.00 | $150.00 | $345.00 | $200.00 | $350.00 |
| 12 | Geotextile fabric (204E50000) | SY | 1,661 | $3.00 | $2.00 | $2.50 | $2.00 | $2.50 | $2.30 |
| 13 | Guardrail, type MGS with long posts (606E15100) | FT | 332 | $22.00 | $21.00 | $21.00 | $29.50 | $21.00 | $21.00 |
| 14 | Anchor assembly, MGS type E, as per plan (606E26151) | EACH | 3 | $2,600.00 | $2,400.00 | $2,400.00 | $2,870.00 | $2,400.00 | $2,400.00 |
| 15 | Anchor assembly, MGS type T, as per plan (606E26551) | EACH | 1 | $1,600.00 | $1,400.00 | $1,400.00 | $1,500.00 | $1,400.00 | $1,400.00 |
| 16 | MGS bridge terminal assembly, type TST-2, as per plan (606E34601) | EACH | 4 | $2,500.00 | $2,275.00 | $2,275.00 | $3,200.00 | $2,275.00 | $2,275.00 |
| 17 | Tied concrete block mat with type 2 underlayment (601E21060) | SY | 2 | $200.00 | $300.00 | $150.00 | $350.00 | $250.00 | $250.00 |
| 18 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 14 | $125.00 | $80.00 | $90.00 | $225.00 | $200.00 | $115.00 |
| 19 | Topsoil (659E00300) | CY | 119 | $35.00 | $50.00 | $15.00 | $64.00 | $35.00 | $28.00 |
| 20 | Seeding and mulching (659E10000) | SY | 1,071 | $3.00 | $3.50 | $5.00 | $3.78 | $3.00 | $2.98 |
| 21 | Repair seeding and mulching (659E14000) | SY | 54 | $1.00 | $0.10 | $2.00 | $1.00 | $3.00 | $2.98 |
| 22 | Inter-seeding (659E15000) | SY | 54 | $1.00 | $0.10 | $2.00 | $1.00 | $2.00 | $2.00 |
| 23 | Commercial fertilizer (659E20000) | TON | 0.14 | $800.00 | $1,000.00 | $2,000.00 | $1,100.00 | $850.00 | $850.00 |
| 24 | Lime (659E31000) | ACRE | 0.22 | $1,000.00 | $10.00 | $1.00 | $660.00 | $35.00 | $35.00 |
| 25 | Water (659E35000) | MGAL | 7.04 | $1.00 | $1.00 | $10.00 | $3.00 | $1.00 | $1.00 |
| 26 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 27 | Concrete masonry (602E20000) | CY | 2 | $1,000.00 | $2,000.00 | $1,500.00 | $1,900.00 | $2,200.00 | $2,200.00 |
| 28 | 6" unclassified pipe underdrains (605E13300) | FT | 448 | $10.00 | $10.00 | $14.00 | $27.00 | $22.00 | $20.00 |
| 29 | 6" base pipe underdrains (605E14000) | FT | 378 | $10.00 | $10.00 | $14.00 | $27.00 | $16.00 | $20.00 |
| 30 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 74 | $15.00 | $10.00 | $25.00 | $27.00 | $16.00 | $32.00 |
| 31 | 6" conduit, type B (611E00900) | FT | 42 | $15.00 | $10.00 | $25.00 | $27.00 | $16.00 | $37.00 |
| 32 | 30" conduit, type C (611E13600) | FT | 257 | $90.00 | $90.00 | $150.00 | $108.00 | $170.00 | $135.00 |
| 33 | Precast reinforced concrete outlet (611E99710) | EACH | 2 | $250.00 | $200.00 | $400.00 | $382.00 | $375.00 | $550.00 |
| 34 | Pavement planing, asphalt concrete,1.75" (254E01000) | SY | 194 | $50.00 | $10.25 | $12.50 | $26.00 | $10.25 | $4.00 |
| 35 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 406 | $222.00 | $215.00 | $215.00 | $225.00 | $215.00 | $192.00 |
| 36 | Aggregate base (304E20000) | CY | 322 | $70.00 | $75.00 | $90.00 | $105.00 | $75.00 | $80.00 |
| 37 | Tack coat (407E10000) | GAL | 311 | $4.00 | $1.00 | $1.00 | $3.75 | $1.00 | $53.50 |
| 38 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 148 | $290.00 | $285.00 | $285.00 | $332.00 | $285.00 | $305.00 |
| 39 | RPM (621E00100) | EACH | 6 | $770.00 | $819.30 | $819.30 | $728.00 | $1,450.00 | $900.00 |
| 40 | Removal of ground mounted sign and disposal (630E84900) | EACH | 3 | $25.00 | $20.00 | $10.00 | $92.00 | $25.00 | $25.00 |
| 41 | Removal of ground mounted sign and reerection (630E85100) | EACH | 7 | $100.00 | $100.00 | $50.00 | $107.00 | $100.00 | $100.00 |
| 42 | Removal of ground mounted post support and disposal (630E86002) | EACH | 1 | $25.00 | $20.00 | $22.51 | $92.00 | $25.00 | $25.00 |
| 43 | Removal of ground mounted post support and reerection (630E86010) | EACH | 6 | $150.00 | $150.00 | $100.00 | $166.00 | $150.00 | $150.00 |
| 44 | Edge line, 6" (644E00104) | MI | 0.22 | $8,000.00 | $11,515 | $11,515 | $8,560.00 | $8,000.00 | $11,515 |
| 45 | Center line (644E00300) | MI | 0.11 | $12,000 | $14,985 | $14,985 | $12,840 | $12,000 | $14,985 |
| 46 | Structure removed, over 20 foot span (202E11002) | LS | 1 | $30,000 | $55,800 | $47,500 | $20,500 | $40,000 | $90,000 |
| 47 | Approach slab removed (202E22900) | SY | 84 | $80.00 | $30.00 | $45.00 | $66.00 | $60.00 | $60.00 |
| 48 | Unclassified excavation (503E21100) | CY | 207 | $40.00 | $25.00 | $100.00 | $120.00 | $75.00 | $70.00 |
| 49 | Unclassified excavation, including rock (503E21104) | CY | 22 | $200.00 | $100.00 | $225.00 | $770.00 | $225.00 | $250.00 |
| 50 | Epoxy coated steel reinforcement (509E10000) | LB | 16,452 | $1.40 | $2.00 | $1.75 | $1.80 | $1.75 | $1.50 |
| 51 | Class QC2 concrete, superstructure, as per plan (511E31611) | CY | 50 | $950.00 | $1,000.00 | $1,450.00 | $878.00 | $1,300.00 | $1,500.00 |
| 52 | Class QC1 concrete, abutment including footing (511E43510) | CY | 122 | $650.00 | $850.00 | $650.00 | $575.00 | $700.00 | $800.00 |
| 53 | Sealing of concrete surfaces (non-epoxy) (512E10050) | SY | 61 | $40.00 | $35.00 | $30.00 | $47.00 | $32.00 | $50.00 |
| 54 | Type 2 waterproofing (512E33000) | SY | 9 | $60.00 | $40.00 | $100.00 | $177.00 | $75.00 | $35.00 |
| 55 | Prestressed concrete composite box beam bridge members, level 1, CB17-48 (515E12030) | EACH | 8 | $18,657 | $21,000 | $19,000 | $20,550 | $26,000 | $21,500 |
| 56 | 2" preformed expansion joint filler (516E13900) | SF | 28 | $20.00 | $5.00 | $15.00 | $20.00 | $10.00 | $15.00 |
| 57 | Semi-integral abutment expansion joint seal (516E14020) | FT | 80 | $40.00 | $30.00 | $45.00 | $40.00 | $45.00 | $45.00 |
| 58 | 1/8" preformed bearing pad, type CDP (516E41100) | EACH | 32 | $60.00 | $5.00 | $50.00 | $61.00 | $60.00 | $10.00 |
| 59 | Elastomeric bearing with internal laminates and load plate (516E44000) | EACH | 32 | $600.00 | $1,000.00 | $700.00 | $1,007.00 | $735.00 | $550.00 |
| 60 | Railing (three steel tube bridge railing) (517E70100) | FT | 127 | $420.00 | $414.25 | $414.25 | $443.00 | $415.00 | $414.25 |
| 61 | Porous backfill with geotextile fabric (518E21200) | CY | 48 | $90.00 | $100.00 | $125.00 | $127.00 | $125.00 | $145.00 |
| 62 | Special - steel drip strip (518E22300) | FT | 134 | $15.00 | $15.00 | $18.00 | $26.00 | $18.00 | $22.00 |
| 63 | 6" perforated corrugated plastic pipe (518E40000) | FT | 94 | $15.00 | $10.00 | $12.00 | $15.00 | $12.00 | $16.00 |
| 64 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 80 | $15.00 | $10.00 | $15.00 | $15.00 | $12.00 | $16.00 |
| 65 | Reinforced concrete approach slabs (T=13") (526E15000) | SY | 143 | $180.00 | $270.00 | $340.00 | $366.00 | $375.00 | $400.00 |
| 66 | Type A installation (526E90010) | FT | 64 | $240.00 | $200.00 | $175.00 | $202.00 | $180.00 | $150.00 |
| 67 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 172 | $125.00 | $80.00 | $75.00 | $144.00 | $125.00 | $115.00 |
| 68 | Polymer modified asphalt expansion joint system, as per plan (846E00111) | CF | 27 | $550.00 | $748.85 | $800.00 | $650.00 | $750.00 | $750.00 |
| 69 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $7,700.00 | $4,388.65 | $15,000 | $13,600 | $15,000 | $18,000 |
| 70 | Maintaining traffic (614E11000) | LS | 1 | $8,500.00 | $3,500.00 | $4,500.00 | $8,000.00 | $5,500.00 | $8,000.00 |
| 71 | Construction layout stakes and surveying (623E10000) | LS | 1 | $7,500.00 | $50,000 | $10,000 | $7,800.00 | $15,000 | $15,000 |
| 72 | Mobilization (624E10000) | LS | 1 | $32,350 | $100.00 | $45,000 | $55,300 | $50,000 | $55,000 |
| 100 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $8,500.00 | $14,000 | $9,258.74 | $2,500.00 | $22,000 | $5,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 29, 2026. Compiled by Mirage Metrics.