ODOT contract 260471 bid tabulation
MOT-SR 835-02.57 (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on October 29, 2026, MOT. 5 bids received; low bid $5,570,980 by Eagle Bridge Co, -26% against the engineer's estimate of $7,500,000.
- Owner
- Ohio DOT
- Letting
- 29 OCT 2026
- Pay items
- 126
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Eagle Bridge Co | $5,570,980 | Low | -26% |
| 2 | Jutte Excavating Inc | $5,914,491 | +6.0% | -21% |
| 3 | Brumbaugh Construction Inc | $5,990,000 | +8.0% | -20% |
| 4 | Complete General Construction Company | $6,353,979 | +14% | -15% |
| 5 | Sunesis Construction Co | $6,647,696 | +19% | -11% |
Engineer's estimate: $7,500,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Eagle Bridge Co | 2. Jutte Excavating Inc | 3. Brumbaugh Construction Inc | 4. Complete General Construction Company | 5. Sunesis Construction Co |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $1,500.00 | $1,250.00 | $10,000 | $4,000.00 | $3,147.02 |
| 2 | Pavement removed (202E23000) | SY | 1,127 | $12.00 | $5.15 | $12.00 | $18.00 | $13.79 |
| 3 | Curb removed (202E32000) | FT | 274 | $3.00 | $10.00 | $15.00 | $14.00 | $5.03 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 24 | $20.00 | $15.00 | $20.00 | $65.00 | $35.87 |
| 5 | Guardrail removed (202E38000) | FT | 88 | $5.00 | $3.00 | $20.00 | $3.00 | $12.14 |
| 6 | Anchor assembly removed, type E (202E42010) | EACH | 2 | $300.00 | $150.00 | $500.00 | $165.00 | $556.68 |
| 7 | Bridge terminal assembly removed (202E47000) | EACH | 2 | $150.00 | $100.00 | $500.00 | $520.00 | $481.23 |
| 8 | Removal misc.: precast reinforced concrete outlet (202E98100) | EACH | 1 | $65.00 | $150.00 | $200.00 | $300.00 | $481.23 |
| 9 | Removal misc.: concrete pad removed (202E98400) | SF | 67 | $5.00 | $12.00 | $7.00 | $7.00 | $17.93 |
| 10 | Excavation (203E10000) | CY | 255 | $30.00 | $20.00 | $20.00 | $35.00 | $7.18 |
| 11 | Embankment (203E20000) | CY | 237 | $30.00 | $17.00 | $20.00 | $40.00 | $17.14 |
| 12 | Subgrade compaction (204E10000) | SY | 1,055 | $7.00 | $3.00 | $1.50 | $4.50 | $4.36 |
| 13 | Excavation of subgrade (204E13000) | CY | 35 | $20.00 | $20.00 | $30.00 | $50.00 | $61.37 |
| 14 | Granular material, type C (204E30020) | CY | 35 | $75.00 | $55.00 | $80.00 | $80.00 | $155.25 |
| 15 | Proof rolling (204E45000) | HR | 1 | $125.00 | $150.00 | $150.00 | $140.00 | $377.23 |
| 16 | Geotextile fabric (204E50000) | SY | 130 | $2.50 | $2.00 | $4.00 | $4.00 | $8.47 |
| 17 | Guardrail, type MGS (606E15050) | FT | 87.50 | $32.00 | $32.00 | $40.00 | $32.00 | $31.00 |
| 18 | Anchor assembly, MGS type E (MASH 2016) (606E26150) | EACH | 2 | $2,840.00 | $2,840.00 | $3,000.00 | $2,840.00 | $2,975.00 |
| 19 | Bridge terminal assembly, type 1 (606E35000) | EACH | 2 | $1,295.00 | $1,295.00 | $2,800.00 | $1,295.00 | $1,550.00 |
| 20 | Fence, misc.: wood fence (607E98000) | FT | 154 | $62.50 | $62.50 | $75.00 | $62.50 | $88.00 |
| 21 | 6" concrete walk, as per plan (608E13001) | SF | 1,849 | $15.00 | $8.00 | $16.00 | $15.00 | $16.75 |
| 22 | Curb, type 4-C (609E24510) | FT | 34 | $60.00 | $50.00 | $43.00 | $75.00 | $80.34 |
| 23 | Curb, type 6 (609E26000) | FT | 274 | $45.00 | $60.00 | $45.00 | $65.00 | $66.59 |
| 24 | Concrete barrier, type D (622E24000) | FT | 52 | $195.00 | $40.00 | $250.00 | $248.00 | $195.00 |
| 25 | Concrete barrier end section, type D (622E25000) | EACH | 1 | $6,000.00 | $2,500.00 | $4,500.00 | $5,500.00 | $4,000.00 |
| 26 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 311 | $100.00 | $80.00 | $90.00 | $130.00 | $59.78 |
| 27 | Topsoil (659E00300) | CY | 234 | $15.00 | $60.00 | $40.00 | $40.00 | $58.86 |
| 28 | Seeding and mulching, as per plan (659E10001) | SY | 2,106 | $3.00 | $5.00 | $5.00 | $2.00 | $3.55 |
| 29 | Repair seeding and mulching (659E14000) | SY | 105 | $2.00 | $1.00 | $2.00 | $2.00 | $2.65 |
| 30 | Inter-seeding (659E15000) | SY | 105 | $2.00 | $0.01 | $2.00 | $1.00 | $2.65 |
| 31 | Commercial fertilizer (659E20000) | TON | 0.29 | $1,500.00 | $1,500.00 | $1,000.00 | $1,000.00 | $820.00 |
| 32 | Lime (659E31000) | ACRE | 0.44 | $1.00 | $200.00 | $1.00 | $100.00 | $50.00 |
| 33 | Water (659E35000) | MGAL | 12 | $10.00 | $100.00 | $10.00 | $1.00 | $50.00 |
| 34 | Ditch erosion protection mat, type B (670E00720) | SY | 430 | $2.50 | $5.00 | $4.00 | $4.00 | $4.00 |
| 35 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,250.00 | $2,700.00 | $3,000.00 | $2,700.00 | $2,700.00 |
| 36 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $10,500 | $8,000.00 | $10,000 | $9,000.00 | $7,840.00 |
| 37 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $8,000.00 | $7,000.00 | $7,000.00 | $7,000.00 | $6,911.99 |
| 38 | Erosion control (832E30000) | EACH | 10,600 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 39 | Concrete masonry (602E20000) | CY | 0.20 | $4,500.00 | $4,500.00 | $5,000.00 | $4,300.00 | $7,285.85 |
| 40 | 6" unclassified pipe underdrains (605E13300) | FT | 17 | $20.00 | $10.00 | $20.00 | $42.00 | $42.19 |
| 41 | 6" base pipe underdrains (605E14000) | FT | 116 | $20.00 | $5.00 | $25.00 | $38.00 | $28.12 |
| 42 | Aggregate drains (605E31100) | FT | 28 | $12.00 | $15.00 | $35.00 | $75.00 | $16.62 |
| 43 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 27 | $25.00 | $10.00 | $30.00 | $80.00 | $47.96 |
| 44 | 12" conduit, type C (611E04600) | FT | 40 | $75.00 | $40.00 | $55.00 | $190.00 | $152.56 |
| 45 | Catch basin, no. 3A (611E98180) | EACH | 1 | $3,500.00 | $4,000.00 | $4,000.00 | $4,400.00 | $3,861.54 |
| 46 | Precast reinforced concrete outlet (611E99710) | EACH | 3 | $350.00 | $215.00 | $400.00 | $400.00 | $622.35 |
| 47 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 235 | $244.00 | $384.00 | $330.00 | $250.00 | $250.00 |
| 48 | Aggregate base (304E20000) | CY | 217 | $140.00 | $44.00 | $90.00 | $140.00 | $95.00 |
| 49 | Non-tracking tack coat (407E20000) | GAL | 113 | $5.00 | $9.00 | $3.00 | $4.50 | $4.50 |
| 50 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 86 | $433.00 | $404.00 | $400.00 | $450.00 | $450.00 |
| 51 | Conduit, misc.: review of sanitary sewer facilitie (611E97400) | FT | 100 | $50.00 | $10.00 | $50.00 | $75.00 | $74.60 |
| 52 | Connection, fused pull apart (625E00450) | EACH | 5 | $202.00 | $129.51 | $205.00 | $200.00 | $204.33 |
| 53 | Connection, unfused pull apart (625E00460) | EACH | 5 | $180.00 | $111.81 | $190.00 | $200.00 | $182.08 |
| 54 | Connection, unfused permanent (625E00480) | EACH | 2 | $196.50 | $76.41 | $205.00 | $160.00 | $198.77 |
| 55 | Light pole, conventional, as per plan, davit style (625E10491) | EACH | 2 | $5,480.00 | $5,857.52 | $5,700.00 | $6,000.00 | $5,543.19 |
| 56 | Light pole anchor bolts on structure (625E10614) | EACH | 8 | $277.50 | $1,180.00 | $290.00 | $200.00 | $280.70 |
| 57 | No. 4 AWG 2400 volt distribution cable (625E23200) | FT | 1,554 | $4.85 | $5.44 | $5.00 | $4.75 | $4.91 |
| 58 | No. 10 AWG pole and bracket cable (625E23400) | FT | 288 | $6.40 | $1.20 | $7.00 | $2.00 | $6.47 |
| 59 | Conduit, 2", 725.04 (625E25400) | FT | 173 | $37.50 | $32.98 | $40.00 | $90.00 | $37.93 |
| 60 | Conduit, 2", 725.05 (625E25402) | FT | 468 | $5.80 | $18.09 | $6.00 | $10.00 | $5.87 |
| 61 | Conduit, concrete encased, 725.04, 2" (625E25802) | FT | 36 | $68.55 | $45.62 | $72.00 | $115.00 | $69.34 |
| 62 | Conduit, misc.: conduit removed (625E25920) | FT | 291 | $3.50 | $7.72 | $4.00 | $16.00 | $9.92 |
| 63 | Trench (625E29000) | FT | 209 | $14.15 | $19.69 | $15.00 | $17.00 | $14.31 |
| 64 | Transition junction box (625E29910) | EACH | 2 | $2,782.00 | $4,370.72 | $2,900.00 | $2,400.00 | $2,814.08 |
| 65 | Structure junction box (625E29920) | EACH | 2 | $2,782.00 | $4,606.72 | $2,900.00 | $3,500.00 | $2,814.08 |
| 66 | Barrier junction box (625E29940) | EACH | 2 | $5,092.00 | $4,370.72 | $5,300.00 | $2,500.00 | $5,150.72 |
| 67 | Pull box, 725.08, 18" (625E30700) | EACH | 2 | $960.00 | $1,742.86 | $1,000.00 | $1,500.00 | $971.07 |
| 68 | Pull box removed (625E31510) | EACH | 2 | $555.00 | $304.44 | $580.00 | $1,000.00 | $561.40 |
| 69 | Structure grounding system, as per plan (625E33001) | EACH | 1 | $14,400 | $11,460 | $15,000 | $25,000 | $14,566 |
| 70 | Reerect existing luminaire (625E35100) | EACH | 2 | $158.00 | $70.21 | $165.00 | $150.00 | $159.82 |
| 71 | Underground warning marking tape (625E36010) | FT | 209 | $4.05 | $1.91 | $4.25 | $2.00 | $4.10 |
| 72 | Light pole removed (625E75400) | EACH | 2 | $250.00 | $561.68 | $260.00 | $1,500.00 | $252.89 |
| 73 | Luminaire removed for reuse (625E75508) | EACH | 2 | $125.00 | $82.01 | $130.00 | $500.00 | $126.44 |
| 74 | Distribution cable removed (625E75550) | FT | 1,362 | $1.00 | $0.84 | $1.00 | $3.00 | $1.01 |
| 75 | Disconnect circuit (625E75800) | EACH | 4 | $1,305.00 | $164.02 | $1,400.00 | $1,000.00 | $1,320.05 |
| 76 | RPM (621E00100) | EACH | 4 | $750.00 | $750.00 | $800.00 | $800.00 | $800.00 |
| 77 | Barrier reflector, type 1 (1-way) (626E00102) | EACH | 13 | $12.00 | $10.80 | $13.00 | $20.00 | $13.00 |
| 78 | Barrier reflector, type 3 (1-way) (626E00112) | EACH | 5 | $15.00 | $10.80 | $13.00 | $20.00 | $13.00 |
| 79 | Sign support assembly, pole mounted (630E79500) | EACH | 3 | $130.96 | $130.96 | $140.00 | $385.00 | $130.96 |
| 80 | Sign, flat sheet (630E80100) | SF | 9 | $22.71 | $22.71 | $25.00 | $30.00 | $22.71 |
| 81 | Removal of ground mounted post support and disposal (630E86002) | EACH | 1 | $33.64 | $34.00 | $100.00 | $20.00 | $33.64 |
| 82 | Removal of pole mounted sign and disposal (630E87500) | EACH | 1 | $25.23 | $25.00 | $100.00 | $45.00 | $25.23 |
| 83 | Removal of pole mounted sign and disposal, as per plan (630E87501) | EACH | 2 | $142.06 | $140.00 | $200.00 | $195.00 | $142.06 |
| 84 | Edge line, 6" (646E10010) | MI | 0.18 | $10,000 | $10,000 | $11,500 | $49,066 | $49,066 |
| 85 | Lane line, 6" (646E10110) | MI | 0.16 | $10,000 | $10,000 | $11,500 | $27,598 | $27,598 |
| 86 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 40 | $60.00 | $25.00 | $155.00 | $95.00 | $110.00 |
| 87 | Detour signing (614E12420) | LS | 1 | $6,000.00 | $4,800.00 | $10,000 | $6,000.00 | $6,910.00 |
| 88 | Water (616E10000) | MGAL | 2 | $10.00 | $20.00 | $10.00 | $170.53 | $81.10 |
| 89 | Structure removed, over 20 foot span (202E11002) | LS | 1 | $250,000 | $318,578 | $350,000 | $250,000 | $272,680 |
| 90 | Approach slab removed (202E22900) | SY | 380 | $35.00 | $56.90 | $75.00 | $39.44 | $42.55 |
| 91 | Wearing course removed (202E23500) | SY | 2,215 | $3.00 | $2.45 | $10.00 | $11.60 | $6.75 |
| 92 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $215,000 | $178,500 | $150,000 | $200,000 | $273,198 |
| 93 | Unclassified excavation (503E21300) | LS | 1 | $65,000 | $25,000 | $25,000 | $95,000 | $117,785 |
| 94 | Pile driving equipment mobilization (505E11100) | LS | 1 | $30,000 | $153,500 | $30,000 | $30,000 | $13,635 |
| 95 | 14" cast-in-place reinforced concrete piles, driven (507E00600) | FT | 6,520 | $5.00 | $18.00 | $6.00 | $15.00 | $38.11 |
| 96 | 14" cast-in-place reinforced concrete piles, furnished (507E00650) | FT | 7,000 | $130.00 | $124.35 | $112.00 | $126.00 | $120.63 |
| 97 | Epoxy coated steel reinforcement (509E10000) | LB | 117,470 | $1.60 | $1.02 | $1.25 | $1.54 | $1.54 |
| 98 | Galvanized steel reinforcement (509E26000) | LB | 110,385 | $2.25 | $1.38 | $1.75 | $2.06 | $2.08 |
| 99 | No. 4 deformed GFRP reinforcement (509E30020) | FT | 6,439 | $1.35 | $2.05 | $3.00 | $1.41 | $1.78 |
| 100 | Class QC2 concrete with QC/QA, bridge deck (511E34446) | CY | 674 | $500.00 | $740.00 | $900.00 | $700.00 | $640.94 |
| 101 | Class QC2 concrete with QC/QA, bridge deck (parapet) (511E34450) | CY | 68 | $1,000.00 | $1,200.00 | $1,200.00 | $1,100.00 | $1,376.21 |
| 102 | Class QC1 concrete with QC/QA, pier above footings (511E41012) | CY | 123 | $1,100.00 | $925.00 | $1,000.00 | $1,800.00 | $1,439.67 |
| 103 | Class QC1 concrete with QC/QA, abutment including footing (511E43512) | CY | 182 | $675.00 | $975.00 | $750.00 | $900.00 | $924.02 |
| 104 | Class QC1 concrete with QC/QA, footing (511E46512) | CY | 157 | $500.00 | $900.00 | $500.00 | $600.00 | $611.18 |
| 105 | Sealing of concrete surfaces (non-epoxy) (512E10050) | SY | 698 | $13.50 | $5.50 | $15.00 | $13.50 | $13.50 |
| 106 | Prestressed concrete composite box beam bridge members, level 1, CB33-48 (515E12090) | EACH | 72 | $24,500 | $26,923 | $29,000 | $27,000 | $33,435 |
| 107 | 1" preformed expansion joint filler (516E13600) | SF | 8 | $12.00 | $5.00 | $4.00 | $14.00 | $13.67 |
| 108 | 2" preformed expansion joint filler (516E13900) | SF | 39 | $16.00 | $6.00 | $6.00 | $16.00 | $10.11 |
| 109 | Integral abutment expansion joint seal (516E14014) | FT | 225 | $37.00 | $32.00 | $40.00 | $45.00 | $46.75 |
| 110 | 1/8" preformed bearing pad, type CDP (516E41100) | EACH | 144 | $25.00 | $51.00 | $15.00 | $75.00 | $94.25 |
| 111 | Elastomeric bearing with internal laminates only (neoprene) (516E43200) | EACH | 288 | $115.00 | $90.00 | $180.00 | $200.00 | $219.54 |
| 112 | Railing, misc.: modified twin steel tube bridge RA (517E76300) | FT | 207 | $355.00 | $315.00 | $530.00 | $355.00 | $429.00 |
| 113 | Porous backfill with geotextile fabric (518E21200) | CY | 148 | $140.00 | $55.00 | $80.00 | $135.00 | $111.59 |
| 114 | Special - steel drip strip (518E22300) | FT | 247 | $14.00 | $20.00 | $15.00 | $19.00 | $16.10 |
| 115 | 6" perforated corrugated plastic pipe (518E40000) | FT | 244 | $12.00 | $6.00 | $10.00 | $8.00 | $4.27 |
| 116 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 49 | $20.00 | $6.00 | $10.00 | $18.00 | $28.25 |
| 117 | Dynamic load testing, as per plan (523E20001) | EACH | 4 | $4,500.00 | $4,000.00 | $4,000.00 | $5,000.00 | $5,250.26 |
| 118 | Restrike, as per plan (523E20501) | EACH | 4 | $750.00 | $1,500.00 | $3,000.00 | $3,200.00 | $1,885.26 |
| 119 | Reinforced concrete approach slabs with QC/QA (T=1 (526E15011) | SY | 427 | $165.00 | $135.25 | $200.00 | $250.00 | $171.20 |
| 120 | Type A installation (526E90010) | FT | 199 | $125.00 | $126.11 | $125.00 | $210.00 | $129.25 |
| 121 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $60,000 | $27,000 | $70,000 | $36,000 | $30,807 |
| 122 | Maintaining traffic (614E11000) | LS | 1 | $7,500.00 | $2,195.00 | $5,000.00 | $14,000 | $4,909.33 |
| 123 | Field office, type B (619E16010) | MNTH | 9 | $2,750.00 | $2,750.00 | $1,000.00 | $3,800.00 | $1,837.78 |
| 124 | Construction layout stakes and surveying (623E10000) | LS | 1 | $20,000 | $5,000.00 | $25,000 | $40,000 | $40,000 |
| 125 | Mobilization (624E10000) | LS | 1 | $215,000 | $224,500 | $96,976 | $300,000 | $100,925 |
| 200 | Steel points or shoes (507E93300) | EACH | 96 | $550.00 | $515.00 | $600.00 | $400.00 | $502.97 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 29, 2026. Compiled by Mirage Metrics.