ODOT contract 260455 bid tabulation
ASD-OVERLAY VAR FY2027 (TWO LANE RESURFACING). Let by Ohio DOT on October 29, 2026, ASD. 2 bids received; low bid $6,659,917 by Kokosing Construction Company Inc, -9.1% against the engineer's estimate of $7,326,000.
- Owner
- Ohio DOT
- Letting
- 29 OCT 2026
- Pay items
- 106
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Kokosing Construction Company Inc | $6,659,917 | Low | -9.0% |
| 2 | Shelly & Sands Inc | $6,865,632 | +3.0% | -6.0% |
Engineer's estimate: $7,326,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Kokosing Construction Company Inc | 2. Shelly & Sands Inc |
|---|---|---|---|---|---|
| 1 | Walk removed (202E30000) | SF | 1,068 | $5.00 | $5.00 |
| 2 | Curb removed (202E32000) | FT | 128 | $12.50 | $12.50 |
| 3 | Guardrail removed (202E38000) | FT | 4,256.25 | $2.00 | $2.00 |
| 4 | Anchor assembly removed, type A (202E42000) | EACH | 16 | $200.00 | $200.00 |
| 5 | Anchor assembly removed, type E (202E42010) | EACH | 17 | $200.00 | $200.00 |
| 6 | Anchor assembly removed, type T (202E42040) | EACH | 17 | $150.00 | $150.00 |
| 7 | Bridge terminal assembly removed (202E47000) | EACH | 20 | $75.00 | $75.00 |
| 8 | Mailbox removed (202E53100) | EACH | 4 | $50.00 | $20.00 |
| 9 | Embankment, as per plan (203E20001) | CY | 988 | $65.00 | $65.00 |
| 10 | Reshaping under guardrail, as per plan (209E15001) | STA | 4.51 | $65.00 | $65.00 |
| 11 | Linear grading (209E60500) | MI | 0.30 | $2,000.00 | $8,000.00 |
| 12 | Preparing subgrade for shoulder paving, as per plan (209E72051) | MI | 19.91 | $2,000.00 | $2,500.00 |
| 13 | Grading mailbox approaches (209E80000) | EACH | 136 | $10.00 | $100.00 |
| 14 | Guardrail, type 5 (606E13000) | FT | 281.25 | $20.00 | $20.00 |
| 15 | Guardrail, type 5A (606E13050) | FT | 25 | $20.00 | $20.00 |
| 16 | Guardrail, type MGS (606E15050) | FT | 3,837.50 | $20.00 | $20.00 |
| 17 | Guardrail rebuilt, type 5 (606E16500) | FT | 50 | $8.50 | $8.50 |
| 18 | Raising type 5 guardrail (606E17000) | FT | 75 | $7.00 | $7.00 |
| 19 | Replace existing guardrail blockout (606E17700) | EACH | 4 | $13.00 | $13.00 |
| 20 | Anchor assembly, MGS type E, MASH 2016 (606E26150) | EACH | 32 | $2,450.00 | $2,450.00 |
| 21 | Anchor assembly, type T (606E26500) | EACH | 2 | $1,375.00 | $1,375.00 |
| 22 | Anchor assembly, MGS type T (606E26550) | EACH | 13 | $1,375.00 | $1,375.00 |
| 23 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 4 | $2,350.00 | $2,350.00 |
| 24 | Bridge terminal assembly, type 4 (606E35140) | EACH | 16 | $1,100.00 | $1,100.00 |
| 25 | 4" concrete walk (608E10000) | SF | 213 | $21.00 | $21.00 |
| 26 | Curb ramp (608E52000) | SF | 795 | $21.00 | $21.00 |
| 27 | Curb ramp, as per plan (608E52001) | SF | 51 | $36.00 | $36.00 |
| 28 | Curb, type 6 (609E26000) | FT | 27 | $35.00 | $35.00 |
| 29 | Monument assembly adjusted to grade, as per plan (623E39501) | EACH | 18 | $800.00 | $1,500.00 |
| 30 | Monument assembly reconstructed to grade, as per plan (623E39601) | EACH | 7 | $1,200.00 | $2,300.00 |
| 31 | Post construction survey monument verification and report (623E51000) | LS | 1 | $2,000.00 | $8,000.00 |
| 32 | Special - mailbox support system, single (690E50100) | EACH | 4 | $300.00 | $220.00 |
| 33 | Topsoil, as per plan (659E00301) | CY | 6 | $100.00 | $100.00 |
| 34 | Erosion control (832E30000) | EACH | 4,000 | $1.00 | $1.00 |
| 35 | Catch basin adjusted to grade (611E98630) | EACH | 1 | $1,200.00 | $800.00 |
| 36 | Partial depth pavement repair (asphalt concrete base), as per plan (251E01043) | CY | 858 | $240.00 | $425.00 |
| 37 | Pavement repair, as per plan (253E02001) | CY | 230 | $250.00 | $425.00 |
| 38 | Pavement planing, asphalt concrete (1.25") (254E01000) | SY | 2,657 | $2.00 | $9.00 |
| 39 | Pavement planing, asphalt concrete(1.5") (254E01000) | SY | 82,377 | $0.65 | $0.90 |
| 40 | Pavement planing, asphalt concrete(1.75") (254E01000) | SY | 217 | $0.65 | $4.00 |
| 41 | Pavement planing, asphalt concrete(2.0") (254E01000) | SY | 108,406 | $0.75 | $0.90 |
| 42 | Patching planed surface (254E01600) | SY | 9,685 | $2.00 | $3.00 |
| 43 | Tack coat (407E10000) | GAL | 27,019 | $2.90 | $2.20 |
| 44 | Prime coat, as per plan (408E10001) | GAL | 11,051 | $4.95 | $4.20 |
| 45 | Stabilized crushed aggregate (411E10000) | CY | 2 | $150.00 | $150.00 |
| 46 | Asphalt concrete surface course, 9.5 MM, type A (4 (442E00201) | CY | 6,740 | $215.00 | $206.00 |
| 47 | Asphalt concrete surface course, 9.5 MM, type A (4 (442E00201) | CY | 212 | $215.00 | $206.00 |
| 48 | Asphalt concrete intermediate course, 12.5 MM, type A (448) (442E20170) | CY | 9,058 | $200.00 | $189.00 |
| 49 | Asphalt concrete intermediate course, 12.5 MM, type A (449) (442E22300) | CY | 179 | $200.00 | $189.00 |
| 50 | Compacted aggregate (617E10100) | CY | 1,696.25 | $38.00 | $58.00 |
| 51 | Shoulder preparation (617E20000) | SY | 362 | $1.00 | $10.00 |
| 52 | Rumble stripes, edge line (asphalt concrete) (618E41000) | MI | 8.50 | $1,075.00 | $1,800.00 |
| 53 | Rumble stripes, center line (asphalt concrete) (618E43000) | MI | 4.25 | $1,075.00 | $1,100.00 |
| 54 | Special - cir 4 inches (690E98300) | SY | 106,720 | $4.50 | $4.50 |
| 55 | Special - additional additives (portland cement, L (690E98800) | TON | 239 | $300.00 | $566.50 |
| 56 | Special - corrective aggregate (690E98800) | TON | 178 | $60.00 | $120.00 |
| 57 | Special - emulsified asphalt (690E98900) | GAL | 166,008 | $3.80 | $3.80 |
| 58 | Longitudinal joint preparation (874E21000) | MI | 4.25 | $5,000.00 | $9,500.00 |
| 59 | Valve box adjusted to grade (638E10800) | EACH | 1 | $800.00 | $500.00 |
| 60 | RPM (621E00100) | EACH | 878 | $36.75 | $36.75 |
| 61 | Raised pavement marker removed (621E54000) | EACH | 884 | $1.00 | $8.00 |
| 62 | Barrier reflector, type 2, bidirectional (626E00110) | EACH | 131 | $13.00 | $13.00 |
| 63 | Ground mounted support, no. 3 post, as per plan (630E03101) | FT | 32 | $73.02 | $73.02 |
| 64 | Sign, flat sheet (630E80100) | SF | 17 | $74.52 | $74.52 |
| 65 | Rectangular rapid flashing beacon sign assembly, solar powered, as per plan (631E14001) | EACH | 2 | $8,259.85 | $8,259.85 |
| 66 | Edge line, 6", type 1 (642E00104) | MI | 23.52 | $930.00 | $930.00 |
| 67 | Center line, type 1 (642E00300) | MI | 11.76 | $930.00 | $930.00 |
| 68 | Channelizing line, 8" (644E00400) | FT | 50 | $5.00 | $5.00 |
| 69 | Stop line (644E00500) | FT | 122 | $12.00 | $12.00 |
| 70 | Crosswalk line, 24" (644E00630) | FT | 30 | $12.00 | $12.00 |
| 71 | Railroad symbol marking (644E01000) | EACH | 2 | $600.00 | $600.00 |
| 72 | School symbol marking, 96" (644E01110) | EACH | 2 | $400.00 | $400.00 |
| 73 | Removal of pavement marking (644E30000) | FT | 30 | $5.00 | $5.00 |
| 74 | Edge line, 6" (646E10010) | MI | 0.25 | $7,700.00 | $7,700.00 |
| 75 | Center line (646E10200) | MI | 0.20 | $7,700.00 | $7,700.00 |
| 76 | Ground rod (625E32000) | EACH | 2 | $302.57 | $302.57 |
| 77 | Pedestal foundation (632E64020) | EACH | 2 | $896.19 | $896.19 |
| 78 | Work zone marking sign (614E12460) | EACH | 87 | $65.00 | $90.36 |
| 79 | Asphalt concrete for maintaining traffic (614E13000) | CY | 50 | $125.00 | $300.00 |
| 80 | Work zone center line, class III, 642 paint (614E21550) | MI | 42.46 | $900.00 | $900.00 |
| 81 | Work zone stop line, class III, 642 paint (614E26610) | FT | 488 | $1.00 | $6.00 |
| 82 | Special - sawing and sealing bituminous concrete joints (516E31200) | FT | 77 | $28.44 | $28.44 |
| 83 | Deep beam bridge retrofit railing, as per plan (517E75601) | FT | 187.50 | $159.25 | $159.25 |
| 84 | Special - patching concrete bridge deck (519E12510) | SY | 9 | $883.50 | $883.50 |
| 85 | Special - sawing and sealing bituminous concrete joints (516E31200) | FT | 84 | $28.44 | $28.44 |
| 86 | Deep beam bridge retrofit railing (517E75600) | FT | 175 | $159.25 | $159.25 |
| 87 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 12 | $51.63 | $51.63 |
| 88 | Special - sawing and sealing bituminous concrete joints (516E31200) | FT | 64 | $28.44 | $28.44 |
| 89 | Patching concrete structure (519E11100) | SF | 104 | $130.52 | $130.52 |
| 90 | Pavement removed (202E23000) | SY | 13 | $97.96 | $97.96 |
| 91 | Deep beam bridge retrofit railing (517E75600) | FT | 87.50 | $159.25 | $159.25 |
| 92 | Polymer modified asphalt expansion joint system, as per plan (846E00111) | CF | 37 | $566.18 | $566.18 |
| 93 | Special - sawing and sealing bituminous concrete joints (516E31200) | FT | 72 | $28.44 | $28.44 |
| 94 | Special - sawing and sealing bituminous concrete joints (516E31200) | FT | 88 | $28.44 | $28.44 |
| 95 | Removal misc.:, exisitng joint seal (202E98200) | FT | 71 | $9.09 | $9.09 |
| 96 | Joint sealer (516E31000) | FT | 71 | $24.57 | $24.57 |
| 97 | Special - sawing and sealing bituminous concrete joints (516E31200) | FT | 71 | $28.44 | $28.44 |
| 98 | Deep beam bridge retrofit railing (517E75600) | FT | 137.50 | $169.00 | $169.00 |
| 99 | Special - patching concrete bridge deck (519E12510) | SY | 12 | $883.50 | $883.50 |
| 100 | Special - - railroad coordination (900E17000) | LS | 1 | $1,000.00 | $7,000.00 |
| 101 | Premium on railroads' protective public liability and property damage liability insurance (100E00300) | LS | 1 | $4,000.00 | $3,500.00 |
| 102 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $30,000 | $30,000 |
| 103 | Maintaining traffic (614E11000) | LS | 1 | $371,004 | $430,460 |
| 104 | Field office, type B (619E16010) | MNTH | 6 | $2,400.00 | $3,500.00 |
| 105 | Construction layout stakes and surveying (623E10000) | LS | 1 | $5,000.00 | $15,000 |
| 106 | Mobilization (624E10000) | LS | 1 | $330,000 | $175,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 29, 2026. Compiled by Mirage Metrics.