ODOT contract 268021 bid tabulation
JEF-SR 7-32.95 (SLIDE REPAIR). Let by Ohio DOT on October 29, 2026, JEF. 3 bids received; low bid $3,442,043 by Buds Inc, +10% against the engineer's estimate of $3,128,000.
- Owner
- Ohio DOT
- Letting
- 29 OCT 2026
- Pay items
- 53
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Buds Inc | $3,442,043 | Low | +10% |
| 2 | Rock Supremacy LLC | $3,579,815 | +4.0% | +14% |
| 3 | Alan Stone Co Inc | $3,667,934 | +7.0% | +17% |
Engineer's estimate: $3,128,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Buds Inc | 2. Rock Supremacy LLC | 3. Alan Stone Co Inc |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $320,000 | $192,000 | $335,000 |
| 2 | Pavement removed (202E23000) | SY | 1,046 | $19.00 | $8.00 | $25.00 |
| 3 | Concrete barrier removed, as per plan (202E30701) | FT | 34 | $300.00 | $100.00 | $160.00 |
| 4 | Curb removed (202E32000) | FT | 19 | $25.00 | $90.00 | $45.00 |
| 5 | Guardrail removed (202E38000) | FT | 2,274 | $3.00 | $3.50 | $5.00 |
| 6 | Fence removed (202E75000) | FT | 2,178 | $5.25 | $8.00 | $3.50 |
| 7 | Excavation (203E10000) | CY | 1,100 | $37.00 | $64.00 | $45.00 |
| 8 | Subgrade compaction (204E10000) | SY | 2,159 | $4.00 | $10.00 | $3.00 |
| 9 | Guardrail, type MGS (606E15050) | FT | 37.50 | $60.00 | $58.00 | $130.00 |
| 10 | Anchor assembly, MGS type E (606E26150) | EACH | 1 | $3,000.00 | $5,500.00 | $3,000.00 |
| 11 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 1 | $3,000.00 | $5,500.00 | $2,900.00 |
| 12 | Concrete barrier, single slope, type D, as per plan (622E10161) | FT | 2,095 | $220.00 | $220.00 | $250.00 |
| 13 | Barrier transition, as per plan (622E10201) | EACH | 1 | $5,400.00 | $6,000.00 | $16,000 |
| 14 | Concrete barrier end section, type D (622E25000) | EACH | 1 | $4,500.00 | $5,500.00 | $13,000 |
| 15 | Scaling (862E00500) | HR | 380 | $900.00 | $385.00 | $480.00 |
| 16 | Slope drape, as per plan (862E00601) | SY | 10,130 | $140.00 | $127.00 | $115.00 |
| 17 | Excavation (862E00610) | CY | 1,800 | $37.00 | $64.00 | $65.00 |
| 18 | Trim blasting (862E00700) | SF | 4,000 | $17.10 | $19.50 | $40.00 |
| 19 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 28 | $3.00 | $145.00 | $65.00 |
| 20 | Seeding and mulching, as per plan (659E10001) | SY | 3,847 | $8.00 | $4.00 | $2.00 |
| 21 | Erosion control (832E30000) | EACH | 8,000 | $1.00 | $1.00 | $1.00 |
| 22 | Inlet, no. 3 for single slope barrier, type D, as per plan (611E99115) | EACH | 5 | $4,500.00 | $9,000.00 | $7,000.00 |
| 23 | Pavement planing, asphalt concrete (1 1/2") (254E01000) | SY | 984 | $12.00 | $23.00 | $15.00 |
| 24 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 270 | $300.00 | $330.00 | $280.00 |
| 25 | Aggregate base (304E20000) | CY | 361 | $200.00 | $125.00 | $140.00 |
| 26 | Tack coat (407E10000) | GAL | 196 | $4.00 | $4.00 | $4.00 |
| 27 | Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100) | CY | 95 | $460.00 | $515.00 | $430.00 |
| 28 | Curb, type 4-C, as per plan (609E24511) | FT | 19 | $65.00 | $150.00 | $180.00 |
| 29 | Rumble strips, shoulder (asphalt concrete) (618E40100) | FT | 2,214 | $6.00 | $3.50 | $10.00 |
| 30 | Barrier reflector, type 1 (one-way) (626E00102) | EACH | 23 | $13.00 | $15.00 | $10.00 |
| 31 | Barrier reflector, type 2 (one-way) (626E00110) | EACH | 2 | $16.00 | $20.00 | $15.00 |
| 32 | Ground mounted support, no. 2 post (630E02100) | FT | 13 | $21.00 | $60.00 | $15.00 |
| 33 | Removal of ground mounted sign and reerection (630E85100) | EACH | 1 | $110.00 | $150.00 | $85.00 |
| 34 | Removal of ground mounted post support and disposal (630E86002) | EACH | 1 | $40.00 | $100.00 | $10.00 |
| 35 | Wet reflective epoxy pavement marking, edge line, 6" (807E12010) | MI | 0.42 | $12,000 | $4,000.00 | $7,600.00 |
| 36 | Wet reflective epoxy pavement marking, lane line, 6" (807E12110) | MI | 0.77 | $8,000.00 | $4,000.00 | $7,200.00 |
| 37 | Grooving for 6" recessed pavement marking, (asphalt) (850E10010) | MI | 0.42 | $9,000.00 | $9,000.00 | $16,000 |
| 38 | Increased barrier delineation (614E11630) | FT | 3,140 | $1.20 | $2.00 | $2.00 |
| 39 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 2 | $2,200.00 | $4,000.00 | $2,800.00 |
| 40 | Work zone increased penalties sign (614E12484) | EACH | 4 | $125.00 | $250.00 | $280.00 |
| 41 | Asphalt concrete for maintaining traffic (614E13000) | CY | 10 | $200.00 | $325.00 | $360.00 |
| 42 | Barrier reflector, type 1 (one-way) (614E13310) | EACH | 64 | $15.00 | $30.00 | $10.00 |
| 43 | Object marker, one way (614E13350) | EACH | 64 | $20.00 | $35.00 | $20.00 |
| 44 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 0.81 | $1,800.00 | $3,000.00 | $5,023.64 |
| 45 | Work zone dotted line, class I, 6", 642 paint (614E24202) | FT | 770 | $1.00 | $1.30 | $2.00 |
| 46 | Water (616E10000) | MGAL | 10 | $1.00 | $100.00 | $0.10 |
| 47 | Portable barrier, unanchored (622E41100) | FT | 3,140 | $30.00 | $47.00 | $40.00 |
| 48 | Digital speed limit (DSL) sign assembly (808E18700) | SNMT | 18 | $800.00 | $850.00 | $650.00 |
| 49 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $35,000 | $65,800 | $35,000 |
| 50 | Maintaining traffic, as per plan (614E11001) | LS | 1 | $35,000 | $127,000 | $225,000 |
| 51 | Field office, type B (619E16010) | MNTH | 9 | $200.00 | $2,900.00 | $1,400.00 |
| 52 | Construction layout stakes and surveying (623E10000) | LS | 1 | $30,000 | $38,910 | $27,000 |
| 53 | Mobilization (624E10000) | LS | 1 | $123,000 | $398,000 | $300,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 29, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way