ODOT contract 260454 bid tabulation
ADA-SR 247-14.51/15.56 (BRIDGE REPLACEMENT (2 BRIDGES)). Let by Ohio DOT on October 29, 2026, ADA. 5 bids received; low bid $4,877,413 by D G M Inc, -16% against the engineer's estimate of $5,785,000.
- Owner
- Ohio DOT
- Letting
- 29 OCT 2026
- Pay items
- 134
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | D G M Inc | $4,877,413 | Low | -16% |
| 2 | Double Z Construction Company | $5,103,924 | +5.0% | -12% |
| 3 | Alan Stone Co Inc | $5,154,401 | +6.0% | -11% |
| 4 | KT Holden Construction LLC | $5,286,695 | +8.0% | -9.0% |
| 5 | Complete General Construction Company | $6,334,424 | +30% | +9.0% |
Engineer's estimate: $5,785,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D G M Inc | 2. Double Z Construction Company | 3. Alan Stone Co Inc | 4. KT Holden Construction LLC | 5. Complete General Construction Company |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $20,000 | $30,000 | $11,000 | $25,970 | $50,000 |
| 2 | Pavement removed (202E23000) | SY | 969 | $8.00 | $24.00 | $10.00 | $15.50 | $35.00 |
| 3 | Concrete slope protection removed (202E32800) | SY | 113 | $15.00 | $20.00 | $20.00 | $9.50 | $75.00 |
| 4 | Guardrail removed (202E38000) | FT | 788 | $1.00 | $6.00 | $4.50 | $6.40 | $2.40 |
| 5 | Anchor assembly removed, type A (202E42000) | EACH | 8 | $250.00 | $250.00 | $580.00 | $475.00 | $350.00 |
| 6 | Excavation (203E10000) | CY | 1,224 | $25.00 | $25.00 | $15.00 | $27.40 | $29.00 |
| 7 | Embankment (203E20000) | CY | 1,940 | $30.00 | $40.00 | $15.00 | $24.75 | $22.50 |
| 8 | Granular embankment, as per plan (203E35001) | CY | 200 | $120.00 | $80.00 | $50.00 | $80.00 | $80.00 |
| 9 | Subgrade compaction (204E10000) | SY | 1,535 | $6.00 | $8.00 | $5.50 | $3.30 | $8.00 |
| 10 | Excavation of subgrade (204E13000) | CY | 656 | $22.00 | $25.00 | $40.00 | $46.00 | $45.00 |
| 11 | Granular material, type B (204E30010) | CY | 1,265 | $90.00 | $73.00 | $85.00 | $65.50 | $65.00 |
| 12 | Proof rolling (204E45000) | HR | 3 | $100.00 | $200.00 | $250.00 | $380.00 | $400.00 |
| 13 | Geotextile fabric (204E50000) | SY | 1,501 | $2.00 | $2.00 | $1.50 | $1.20 | $8.00 |
| 14 | Guardrail, type MGS (606E15050) | FT | 625 | $43.00 | $41.00 | $30.00 | $34.24 | $22.00 |
| 15 | Rounded end section (606E20050) | EACH | 1 | $80.00 | $75.00 | $95.00 | $60.00 | $110.00 |
| 16 | Anchor assembly, MGS type E (606E26150) | EACH | 7 | $3,850.00 | $3,750.00 | $3,200.00 | $2,320.00 | $2,580.00 |
| 17 | Anchor assembly, MGS type T (606E26550) | EACH | 1 | $2,750.00 | $2,450.00 | $1,600.00 | $1,200.00 | $1,430.00 |
| 18 | MGS bridge terminal assembly, type TST-2 (606E34600) | EACH | 8 | $3,300.00 | $3,150.00 | $3,300.00 | $2,350.00 | $2,675.00 |
| 19 | Special - geotextile fabric, 712.09 type A (690E12010) | SY | 390 | $3.00 | $3.00 | $2.00 | $3.00 | $10.00 |
| 20 | Inspection and compaction testing of unbound materials (878E25000) | LS | 1 | $10,000 | $40,000 | $25,000 | $56,126 | $16,000 |
| 21 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 487 | $90.00 | $110.00 | $85.00 | $120.00 | $80.00 |
| 22 | Paved gutter, type 1-2, as per plan (601E37501) | FT | 179 | $105.00 | $100.00 | $120.00 | $125.20 | $135.00 |
| 23 | Topsoil (659E00300) | CY | 333 | $15.00 | $55.00 | $30.00 | $62.00 | $25.00 |
| 24 | Seeding and mulching (659E10000) | SY | 2,997 | $3.00 | $6.00 | $2.50 | $2.35 | $2.15 |
| 25 | Repair seeding and mulching (659E14000) | SY | 150 | $0.05 | $2.50 | $1.00 | $1.00 | $2.15 |
| 26 | Inter-seeding (659E15000) | SY | 150 | $0.05 | $2.50 | $0.01 | $0.01 | $0.55 |
| 27 | Commercial fertilizer (659E20000) | TON | 0.42 | $1,500.00 | $1,250.00 | $1,800.00 | $1,500.00 | $600.00 |
| 28 | Lime (659E31000) | ACRE | 0.62 | $300.00 | $150.00 | $230.00 | $200.00 | $0.10 |
| 29 | Water (659E35000) | MGAL | 17 | $1.00 | $1.00 | $1.00 | $1.00 | $0.10 |
| 30 | Sodding unstaked (660E30000) | SY | 60 | $30.00 | $40.00 | $25.00 | $20.00 | $12.00 |
| 31 | Ditch erosion protection mat, type B (670E00720) | SY | 79 | $3.00 | $2.50 | $3.00 | $2.75 | $2.10 |
| 32 | Erosion control (832E30000) | EACH | 26,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 33 | Aggregate drains (605E31100) | FT | 170 | $30.00 | $22.00 | $20.00 | $20.40 | $15.00 |
| 34 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 50 | $25.00 | $20.00 | $10.00 | $37.00 | $30.00 |
| 35 | 6" conduit, type E (611E01400) | FT | 810 | $25.00 | $12.00 | $5.00 | $6.90 | $15.00 |
| 36 | 6" conduit, type F (611E01500) | FT | 160 | $25.00 | $16.00 | $5.50 | $21.40 | $15.00 |
| 37 | Precast reinforced concrete outlet (611E99710) | EACH | 15 | $350.00 | $450.00 | $470.00 | $456.00 | $750.00 |
| 38 | Pavement planing, asphalt concrete (approx. 3" dep (254E01000) | SY | 882 | $25.00 | $24.00 | $20.00 | $24.00 | $35.00 |
| 39 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 342 | $335.00 | $320.00 | $320.00 | $320.00 | $500.00 |
| 40 | Aggregate base (304E20000) | CY | 245 | $105.00 | $105.00 | $100.00 | $115.00 | $95.00 |
| 41 | Non-tracking tack coat (407E20000) | GAL | 345 | $4.30 | $4.30 | $6.50 | $4.30 | $5.00 |
| 42 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 183 | $477.00 | $455.00 | $360.00 | $455.00 | $760.00 |
| 43 | Asphalt concrete intermediate course, type 1, (449) (441E70200) | CY | 25 | $477.00 | $455.00 | $590.00 | $455.00 | $725.00 |
| 44 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 3 | $530.00 | $510.00 | $550.00 | $510.00 | $1,500.00 |
| 45 | RPM (621E00100) | EACH | 7 | $475.00 | $429.80 | $600.00 | $200.00 | $475.00 |
| 46 | Barrier reflector, type 3, (bidirectional) (626E00112) | EACH | 32 | $15.00 | $11.67 | $20.00 | $10.00 | $14.15 |
| 47 | Ground mounted support, no. 3 post (630E03100) | FT | 32.50 | $22.00 | $34.24 | $20.00 | $15.00 | $18.00 |
| 48 | Street name sign support, no. 3 post (630E08520) | FT | 12 | $25.00 | $34.24 | $20.00 | $35.00 | $22.00 |
| 49 | Sign post reflector (630E08600) | EACH | 1 | $50.00 | $71.85 | $65.00 | $32.00 | $45.00 |
| 50 | Sign, flat sheet (630E80100) | SF | 37.30 | $30.00 | $35.74 | $35.00 | $35.00 | $20.00 |
| 51 | Removal of ground mounted sign and disposal (630E84900) | EACH | 6 | $20.00 | $17.02 | $40.00 | $23.00 | $15.00 |
| 52 | Removal of ground mounted post support and disposal (630E86002) | EACH | 3 | $20.00 | $22.70 | $40.00 | $57.50 | $20.00 |
| 53 | Edge line, 6", type 1 (642E00104) | MI | 0.34 | $3,500.00 | $5,830.00 | $3,700.00 | $5,830.00 | $3,200.00 |
| 54 | Center line, type 1 (642E00300) | MI | 0.17 | $6,200.00 | $4,195.00 | $6,900.00 | $4,195.00 | $5,900.00 |
| 55 | Traffic compacted surface, type A or B (410E12000) | CY | 25 | $75.00 | $75.00 | $110.00 | $66.00 | $90.00 |
| 56 | Increased barrier delineation (614E11630) | FT | 1,670 | $1.75 | $1.25 | $2.00 | $1.73 | $2.00 |
| 57 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 8 | $2,000.00 | $2,640.00 | $2,600.00 | $2,145.28 | $2,640.00 |
| 58 | Asphalt concrete for maintaining traffic (614E13000) | CY | 25 | $150.00 | $180.00 | $620.00 | $346.60 | $250.00 |
| 59 | Barrier reflector, type 3, bidirectional (614E13314) | EACH | 34 | $25.00 | $20.00 | $80.00 | $10.76 | $62.00 |
| 60 | Object marker, two way (614E13360) | EACH | 69 | $25.00 | $15.00 | $55.00 | $19.73 | $42.00 |
| 61 | Work zone center line, class I, 740.06, type I (614E21200) | MI | 0.36 | $16,500 | $11,977 | $19,000 | $11,977 | $15,250 |
| 62 | Work zone edge line, class I, 4", 740.06, type I (614E22200) | MI | 0.85 | $11,500 | $7,251.25 | $14,000 | $7,251.25 | $10,850 |
| 63 | Work zone dotted line, class I, 4", 740.06, type I (614E24400) | FT | 186 | $3.00 | $2.56 | $3.50 | $2.56 | $2.75 |
| 64 | Work zone stop line, class I, 740.06, type I (614E26400) | FT | 71 | $20.00 | $6.75 | $20.00 | $6.75 | $14.00 |
| 65 | Pavement for maintaining traffic, class A, as per plan (615E20001) | SY | 265 | $130.00 | $190.00 | $150.00 | $232.00 | $325.00 |
| 66 | Water (616E10000) | MGAL | 8 | $1.00 | $50.00 | $120.00 | $36.00 | $100.00 |
| 67 | Portable barrier, unanchored (622E41100) | FT | 1,670 | $20.00 | $27.00 | $25.00 | $28.40 | $28.00 |
| 68 | Structure removed, over 20 foot span, as per plan (202E11003) | LS | 1 | $107,500 | $90,000 | $173,000 | $245,490 | $150,000 |
| 69 | Approach slab removed (202E22900) | SY | 111 | $35.00 | $45.00 | $110.00 | $130.00 | $95.00 |
| 70 | Wearing course removed (202E23500) | SY | 593 | $8.00 | $10.00 | $10.00 | $10.45 | $17.50 |
| 71 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $120,800 | $85,000 | $48,000 | $73,650 | $150,000 |
| 72 | Unclassified excavation, as per plan (503E21301) | LS | 1 | $34,000 | $75,000 | $50,000 | $148,210 | $122,000 |
| 73 | Rock excavation (503E31100) | CY | 17 | $75.00 | $260.00 | $200.00 | $157.00 | $115.00 |
| 74 | Epoxy coated steel reinforcement (509E10000) | LB | 80,096 | $1.50 | $1.80 | $1.70 | $2.10 | $2.00 |
| 75 | Class QC2 concrete with QC/QA, superstructure (511E33418) | CY | 125 | $900.00 | $800.00 | $750.00 | $573.00 | $595.00 |
| 76 | Semi-integral diaphragm guide (511E33500) | EACH | 2 | $2,500.00 | $4,500.00 | $4,800.00 | $4,070.00 | $7,000.00 |
| 77 | Class QC2 concrete with QC/QA, bridge deck (511E34446) | CY | 127 | $1,610.00 | $1,800.00 | $1,200.00 | $1,254.00 | $1,600.00 |
| 78 | Class QC1 concrete with QC/QA, abutment including footing (511E43512) | CY | 291 | $690.00 | $800.00 | $700.00 | $933.00 | $900.00 |
| 79 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 637 | $35.00 | $28.00 | $40.00 | $28.00 | $28.00 |
| 80 | Type 2 waterproofing (512E33000) | SY | 260 | $22.00 | $25.00 | $40.00 | $25.50 | $25.50 |
| 81 | Draped strand prestressed concrete bridge I-beam members, level 3, type WF66-49 (515E15120) | EACH | 4 | $109,000 | $91,000 | $125,000 | $89,965 | $82,000 |
| 82 | Intermediate diaphragms (515E20000) | EACH | 9 | $2,750.00 | $3,700.00 | $2,600.00 | $4,330.00 | $9,500.00 |
| 83 | 2" preformed expansion joint filler (516E13900) | SF | 109 | $20.00 | $20.00 | $5.50 | $7.00 | $14.00 |
| 84 | Semi-integral abutment expansion joint seal (516E14020) | FT | 127 | $50.00 | $35.00 | $30.00 | $76.70 | $50.00 |
| 85 | Elastomeric bearing with internal laminates and load plate (516E44100) | EACH | 8 | $4,000.00 | $4,000.00 | $2,100.00 | $3,704.00 | $3,500.00 |
| 86 | Railing (three steel tube bridge railing) (517E70100) | FT | 323 | $510.00 | $500.00 | $550.00 | $466.00 | $485.00 |
| 87 | Porous backfill with geotextile fabric (518E21200) | CY | 170 | $120.00 | $140.00 | $100.00 | $135.65 | $150.00 |
| 88 | Special - steel drip strip (518E22300) | FT | 289 | $20.00 | $25.00 | $25.00 | $20.70 | $16.25 |
| 89 | 6" perforated corrugated plastic pipe (518E40000) | FT | 211 | $20.00 | $12.00 | $10.00 | $8.00 | $20.00 |
| 90 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 124 | $20.00 | $14.00 | $20.00 | $27.97 | $35.00 |
| 91 | Drilled shafts, 30" diameter, into bedrock (524E94604) | FT | 253 | $365.00 | $485.00 | $150.00 | $408.70 | $750.00 |
| 92 | Drilled shafts, 36" diameter, above bedrock (524E94702) | FT | 40 | $360.00 | $500.00 | $1,100.00 | $114.30 | $495.00 |
| 93 | Reinforced concrete approach slabs with QC/QA (T=1 (526E30010) | SY | 240 | $400.00 | $460.00 | $600.00 | $423.45 | $475.00 |
| 94 | Type A installation (526E90010) | FT | 83 | $235.00 | $240.00 | $350.00 | $255.35 | $390.00 |
| 95 | Structure grounding system (625E33000) | EACH | 1 | $20,500 | $20,820 | $47,000 | $9,575.00 | $15,000 |
| 96 | Thermal integrity profiling (tip) test (894E10000) | EACH | 20 | $1,600.00 | $1,500.00 | $6,500.00 | $3,000.00 | $5,500.00 |
| 97 | Structure removed, over 20 foot span, as per plan (202E11003) | LS | 1 | $93,000 | $85,000 | $170,000 | $212,596 | $150,000 |
| 98 | Approach slab removed (202E22900) | SY | 111 | $35.00 | $45.00 | $140.00 | $130.00 | $95.00 |
| 99 | Wearing course removed (202E23500) | SY | 464 | $8.00 | $10.00 | $15.00 | $11.90 | $17.50 |
| 100 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $111,500 | $85,000 | $58,000 | $60,030 | $175,000 |
| 101 | Unclassified excavation, as per plan (503E21301) | LS | 1 | $35,500 | $85,000 | $50,000 | $149,550 | $175,000 |
| 102 | Rock excavation (503E31100) | CY | 54 | $50.00 | $225.00 | $250.00 | $137.00 | $95.00 |
| 103 | Epoxy coated steel reinforcement (509E10000) | LB | 63,635 | $1.50 | $1.80 | $1.70 | $2.00 | $2.75 |
| 104 | Class QC2 concrete with QC/QA, superstructure (511E33418) | CY | 97 | $900.00 | $800.00 | $890.00 | $610.50 | $625.00 |
| 105 | Semi-integral diaphragm guide (511E33500) | EACH | 2 | $2,500.00 | $4,500.00 | $4,300.00 | $4,070.00 | $7,500.00 |
| 106 | Class QC2 concrete with QC/QA, bridge deck (511E34446) | CY | 88 | $1,750.00 | $2,200.00 | $1,500.00 | $1,319.00 | $1,900.00 |
| 107 | Class QC1 concrete with QC/QA, abutment including footing (511E43512) | CY | 290 | $690.00 | $800.00 | $700.00 | $889.00 | $950.00 |
| 108 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 505 | $35.00 | $28.00 | $40.00 | $28.00 | $28.00 |
| 109 | Type 2 waterproofing (512E33000) | SY | 292 | $22.00 | $25.00 | $40.00 | $25.50 | $25.50 |
| 110 | Draped strand prestressed concrete bridge I-beam members, level 3, type WF42-49 (515E15080) | EACH | 4 | $93,000 | $68,000 | $85,000 | $67,313 | $97,750 |
| 111 | Intermediate diaphragms (515E20000) | EACH | 9 | $2,500.00 | $2,600.00 | $2,500.00 | $4,052.00 | $7,000.00 |
| 112 | 2" preformed expansion joint filler (516E13900) | SF | 84 | $20.00 | $20.00 | $5.50 | $7.50 | $15.00 |
| 113 | Semi-integral abutment expansion joint seal (516E14020) | FT | 123 | $50.00 | $35.00 | $30.00 | $78.35 | $50.00 |
| 114 | Elastomeric bearing with internal laminates and load plate (516E44100) | EACH | 8 | $4,000.00 | $4,000.00 | $3,700.00 | $3,705.75 | $3,500.00 |
| 115 | Railing (three steel tube bridge railing) (517E70100) | FT | 189 | $515.00 | $500.00 | $550.00 | $474.00 | $490.00 |
| 116 | Porous backfill with geotextile fabric (518E21200) | CY | 157 | $120.00 | $140.00 | $100.00 | $136.15 | $150.00 |
| 117 | Special - steel drip strip (518E22300) | FT | 214 | $20.00 | $25.00 | $30.00 | $20.95 | $16.25 |
| 118 | 6" perforated corrugated plastic pipe (518E40000) | FT | 196 | $20.00 | $12.00 | $10.00 | $8.00 | $15.00 |
| 119 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 59 | $20.00 | $14.00 | $20.00 | $30.50 | $30.00 |
| 120 | Drilled shafts, 30" diameter, into bedrock (524E94604) | FT | 183 | $355.00 | $530.00 | $200.00 | $470.50 | $750.00 |
| 121 | Drilled shafts, 36" diameter, above bedrock (524E94702) | FT | 53 | $350.00 | $525.00 | $720.00 | $127.20 | $495.00 |
| 122 | Reinforced concrete approach slabs with QC/QA (T=1 (526E30010) | SY | 240 | $400.00 | $460.00 | $560.00 | $437.60 | $475.00 |
| 123 | Type A installation (526E90010) | FT | 88 | $235.00 | $240.00 | $330.00 | $251.65 | $390.00 |
| 124 | Structure grounding system (625E33000) | EACH | 1 | $20,500 | $20,820 | $47,000 | $9,575.00 | $14,000 |
| 125 | Thermal integrity profiling (tip) test (894E10000) | EACH | 17 | $1,600.00 | $1,500.00 | $3,900.00 | $3,000.00 | $5,500.00 |
| 126 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $75,000 | $26,000 | $40,000 | $79,300 | $34,000 |
| 127 | Maintaining traffic (614E11000) | LS | 1 | $190,000 | $140,000 | $201,000 | $31,614 | $195,000 |
| 128 | Field office, type B (619E16010) | MNTH | 6 | $1,250.00 | $2,500.00 | $1,800.00 | $1,510.00 | $500.00 |
| 129 | Construction layout stakes and surveying (623E10000) | LS | 1 | $25,000 | $43,500 | $77,000 | $56,500 | $58,500 |
| 130 | Mobilization (624E10000) | LS | 1 | $100,000 | $200,000 | $65,000 | $217,320 | $315,000 |
| 200 | Storm water pollution prevention plan (832E15000) | LS | 1 | $4,000.00 | $3,500.00 | $6,100.00 | $4,000.00 | $3,600.00 |
| 201 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $11,000 | $13,000 | $15,000 | $10,080 | $7,840.00 |
| 202 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $13,000 | $13,000 | $15,000 | $12,600 | $10,000 |
| 203 | Detour signing (614E12420) | LS | 1 | $4,000.00 | $8,000.00 | $4,400.00 | $5,000.00 | $3,500.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 29, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.