ODOT contract 264027 bid tabulation
CLI-/GRE Inverts FY27 (CULVERT REPLACEMENT). Let by Ohio DOT on October 29, 2026, CLI. 3 bids received; low bid $791,078 by BCC Ohio Inc, +5.5% against the engineer's estimate of $750,000.
- Owner
- Ohio DOT
- Letting
- 29 OCT 2026
- Pay items
- 56
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | BCC Ohio Inc | $791,078 | Low | +5.0% |
| 2 | Madex Construction Co | $999,343 | +26% | +33% |
| 3 | Axis Civil Construction LLC | $1,013,487 | +28% | +35% |
Engineer's estimate: $750,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. BCC Ohio Inc | 2. Madex Construction Co | 3. Axis Civil Construction LLC |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $3,180.00 | $3,491.79 | $3,500.00 |
| 2 | Clearing and grubbing (201E11000) | LS | 1 | $9,927.00 | $3,491.79 | $6,500.00 |
| 3 | Clearing and grubbing (201E11000) | LS | 1 | $14,552 | $4,581.85 | $12,000 |
| 4 | Clearing and grubbing (201E11000) | LS | 1 | $10,707 | $14,164 | $6,000.00 |
| 5 | Clearing and grubbing (201E11000) | LS | 1 | $4,032.00 | $3,091.50 | $2,800.00 |
| 6 | Clearing and grubbing (201E11000) | LS | 1 | $10,482 | $3,491.79 | $6,000.00 |
| 7 | Headwall removed (202E20010) | EACH | 2 | $12,594 | $12,637 | $8,000.00 |
| 8 | Guardrail removed (202E38000) | FT | 630 | $2.10 | $6.95 | $3.00 |
| 9 | Anchor assembly removed, type A, as per plan (202E42001) | EACH | 3 | $341.25 | $405.26 | $450.00 |
| 10 | Anchor assembly removed, type T (202E42040) | EACH | 2 | $115.50 | $144.74 | $150.00 |
| 11 | Removal misc.: existing concrete field paving (202E98200) | FT | 66 | $228.98 | $286.46 | $180.00 |
| 12 | Reshaping under guardrail (209E15050) | MI | 0.20 | $5,160.00 | $12,356 | $3,800.00 |
| 13 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $13,447 | $12,824 | $6,000.00 |
| 14 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $20,975 | $19,984 | $20,000 |
| 15 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $55,562 | $15,650 | $20,000 |
| 16 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $12,384 | $24,504 | $3,500.00 |
| 17 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $10,014 | $9,898.73 | $4,000.00 |
| 18 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $12,465 | $11,684 | $12,000 |
| 19 | Guardrail, type MGS (606E15050) | FT | 220 | $24.15 | $26.63 | $24.50 |
| 20 | Guardrail, type MGS with long posts (606E15100) | FT | 320 | $29.82 | $33.58 | $33.50 |
| 21 | Anchor assembly, MGS type E (MASH 2016) (606E26150) | EACH | 3 | $3,066.00 | $3,473.68 | $2,800.00 |
| 22 | Anchor assembly, MGS type T (606E26550) | EACH | 2 | $1,533.00 | $1,736.84 | $1,400.00 |
| 23 | Barrier reflector, type 2 BI-directional (614E13312) | EACH | 8 | $13.91 | $16.21 | $13.00 |
| 24 | Barrier reflector, type 2 one-way (614E13312) | EACH | 8 | $13.91 | $16.21 | $12.50 |
| 25 | Right-of-way monument, type B (623E40520) | EACH | 10 | $699.00 | $578.95 | $400.00 |
| 26 | Rock channel protection, type A with filter (601E32000) | CY | 86 | $197.51 | $299.81 | $225.00 |
| 27 | Topsoil (659E00300) | CY | 994 | $18.45 | $5.79 | $40.00 |
| 28 | Seeding and mulching (659E10000) | SY | 8,954 | $2.10 | $0.58 | $2.00 |
| 29 | Commercial fertilizer (659E20000) | TON | 1.21 | $1,323.00 | $157.89 | $450.00 |
| 30 | Lime (659E31000) | ACRE | 1.85 | $42.00 | $78.95 | $250.00 |
| 31 | Water (659E35000) | MGAL | 48.40 | $1.04 | $0.79 | $1.00 |
| 32 | Erosion control (832E30000) | EACH | 9,000 | $1.00 | $1.00 | $1.00 |
| 33 | Field painting structural steel, intermediate coat (514E00060) | SF | 50 | $174.00 | $31.58 | $300.00 |
| 34 | Conduit, misc.: repair method A (611E97700) | SF | 330 | $38.68 | $104.21 | $170.00 |
| 35 | Conduit, misc.: repair method B (611E97700) | SF | 15 | $103.31 | $665.79 | $825.00 |
| 36 | Field painting structural steel, intermediate coat (514E00060) | SF | 50 | $174.00 | $31.58 | $300.00 |
| 37 | Field paving of existing pipe, 12-6"X7'-11" CMP PI (611E96550) | FT | 66 | $426.00 | $813.21 | $450.00 |
| 38 | Conduit, misc.: repair method A (611E97700) | SF | 50 | $101.25 | $115.79 | $225.00 |
| 39 | Conduit, misc.: repair method B (611E97700) | SF | 30 | $105.21 | $578.95 | $800.00 |
| 40 | Conduit, misc.: repair method C (611E97700) | SF | 15 | $625.61 | $694.74 | $1,600.00 |
| 41 | Field painting structural steel, intermediate coat (514E00060) | SF | 50 | $174.00 | $31.58 | $300.00 |
| 42 | Conduit, misc.: repair method A (611E97700) | SF | 150 | $73.00 | $104.21 | $170.00 |
| 43 | Conduit, misc.: repair method B (611E97700) | SF | 120 | $82.51 | $202.63 | $780.00 |
| 44 | Conduit, misc.: repair method C (611E97700) | SF | 20 | $529.34 | $694.74 | $1,050.00 |
| 45 | Patching concrete structure (519E11100) | SF | 12 | $153.13 | $289.47 | $225.00 |
| 46 | Field paving of existing pipe, 16-7"X10'-1" CMP PI (611E96550) | FT | 176 | $449.41 | $776.89 | $425.00 |
| 47 | Conduit, misc.: repair method A (611E97700) | SF | 250 | $48.57 | $104.21 | $170.00 |
| 48 | Concrete masonry (602E20000) | CY | 26.10 | $1,722.22 | $2,462.84 | $1,950.00 |
| 49 | Field paving of existing pipe, 11'-7"X7'-5" CMP PI (611E96550) | FT | 148 | $347.89 | $578.95 | $375.00 |
| 50 | Conduit, misc.: repair method A (611E97700) | SF | 200 | $53.75 | $104.21 | $170.00 |
| 51 | Conduit, misc.: repair method B (611E97700) | SF | 10 | $104.01 | $665.79 | $1,050.00 |
| 52 | Conduit, misc.:filling voids with expansive polyur (611E97600) | CY | 5 | $506.40 | $157.89 | $3,500.00 |
| 53 | Patching concrete structures with trowelable mortar (843E50000) | SF | 50 | $157.50 | $289.47 | $390.00 |
| 54 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $9,802.32 | $43,980 | $8,000.00 |
| 55 | Maintaining traffic (614E11000) | LS | 1 | $68,680 | $54,737 | $60,000 |
| 56 | Mobilization (624E10000) | LS | 1 | $62,488 | $89,385 | $42,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 29, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.