ODOT contract 260469 bid tabulation
MOT-Johnson Station Rd Bridge (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on October 29, 2026, MOT. 6 bids received; low bid $1,306,719 by Double Z Construction Company, -13% against the engineer's estimate of $1,510,000.
- Owner
- Ohio DOT
- Letting
- 29 OCT 2026
- Pay items
- 74
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Double Z Construction Company | $1,306,719 | Low | -13% |
| 2 | Eagle Bridge Co | $1,523,584 | +17% | +1.0% |
| 3 | Brumbaugh Construction Inc | $1,550,000 | +19% | +3.0% |
| 4 | Sunesis Construction Co | $1,612,906 | +23% | +7.0% |
| 5 | Complete General Construction Company | $2,049,360 | +57% | +36% |
| 6 | Alan Stone Co Inc | $2,110,167 | +61% | +40% |
Engineer's estimate: $1,510,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Double Z Construction Company | 2. Eagle Bridge Co | 3. Brumbaugh Construction Inc | 4. Sunesis Construction Co | 5. Complete General Construction Company | 6. Alan Stone Co Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $10,000 | $10,000 | $8,000.00 | $18,500 | $25,000 | $55,000 |
| 2 | Pavement removed (202E23000) | SY | 190 | $40.00 | $20.00 | $15.00 | $21.00 | $85.00 | $35.00 |
| 3 | Guardrail removed (202E38000) | FT | 191 | $8.00 | $8.00 | $6.00 | $9.00 | $10.00 | $3.50 |
| 4 | Gate removed (202E75250) | EACH | 2 | $200.00 | $250.00 | $300.00 | $551.00 | $275.00 | $450.00 |
| 5 | Removal misc.:, as per plan (202E98100) | EACH | 1 | $100.00 | $250.00 | $200.00 | $551.00 | $5,000.00 | $500.00 |
| 6 | Excavation (203E10000) | CY | 55 | $40.00 | $130.00 | $25.00 | $26.00 | $40.00 | $20.00 |
| 7 | Embankment (203E20000) | CY | 57 | $70.00 | $100.00 | $25.00 | $20.00 | $39.00 | $140.00 |
| 8 | Subgrade compaction (204E10000) | SY | 253 | $10.00 | $15.00 | $2.00 | $6.00 | $11.00 | $10.00 |
| 9 | Proof rolling (204E45000) | HR | 2 | $200.00 | $150.00 | $150.00 | $429.00 | $400.00 | $280.00 |
| 10 | Guardrail, type MGS (606E15050) | FT | 150 | $22.40 | $48.50 | $35.00 | $35.00 | $35.00 | $25.00 |
| 11 | Rounded end section (606E20050) | EACH | 2 | $110.00 | $100.00 | $80.00 | $75.00 | $75.00 | $130.00 |
| 12 | Anchor assembly, type A (606E25000) | EACH | 2 | $1,785.00 | $2,275.00 | $2,600.00 | $2,500.00 | $2,500.00 | $2,000.00 |
| 13 | Bridge terminal assembly, type 4 (606E35140) | EACH | 3 | $1,160.00 | $1,850.00 | $2,300.00 | $2,200.00 | $2,200.00 | $1,300.00 |
| 14 | Right-of-way monument, type B (623E40520) | EACH | 3 | $475.00 | $900.00 | $900.00 | $300.00 | $1,000.00 | $620.00 |
| 15 | Soil analysis test (659E00100) | EACH | 1 | $100.00 | $450.00 | $200.00 | $200.00 | $60.00 | $230.00 |
| 16 | Topsoil (659E00300) | CY | 107 | $70.00 | $20.00 | $50.00 | $26.00 | $30.00 | $55.00 |
| 17 | Seeding and mulching, class 4A (659E00550) | SY | 964 | $8.00 | $6.00 | $5.00 | $3.00 | $4.72 | $3.00 |
| 18 | Repair seeding and mulching (659E14000) | SY | 49 | $9.00 | $3.00 | $2.00 | $2.00 | $4.00 | $15.00 |
| 19 | Inter-seeding (659E15000) | SY | 49 | $9.00 | $3.00 | $2.00 | $2.00 | $2.00 | $7.00 |
| 20 | Commercial fertilizer (659E20000) | TON | 0.14 | $850.00 | $1,500.00 | $1,000.00 | $350.00 | $600.00 | $690.00 |
| 21 | Lime (659E31000) | ACRE | 0.20 | $30.00 | $1.00 | $5.00 | $60.00 | $5.00 | $930.00 |
| 22 | Water (659E35000) | MGAL | 6 | $10.00 | $10.00 | $10.00 | $2.00 | $0.10 | $110.00 |
| 23 | Erosion control (832E30000) | EACH | 1,366 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 24 | Pavement planing, asphalt concrete (T=3") (254E01000) | SY | 911 | $5.10 | $5.10 | $20.00 | $26.00 | $26.00 | $15.00 |
| 25 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 43 | $375.00 | $375.00 | $500.00 | $545.00 | $545.00 | $550.00 |
| 26 | Aggregate base (304E20000) | CY | 43 | $160.00 | $200.00 | $80.00 | $139.00 | $195.00 | $160.00 |
| 27 | Non-tracking tack coat (407E20000) | GAL | 47 | $1.00 | $1.00 | $20.00 | $5.00 | $4.50 | $6.50 |
| 28 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 33 | $450.00 | $450.00 | $525.00 | $742.00 | $742.00 | $470.00 |
| 29 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 45 | $405.00 | $405.00 | $500.00 | $444.00 | $443.50 | $400.00 |
| 30 | Curb, type 6 (609E26000) | FT | 67 | $65.00 | $65.00 | $65.00 | $175.00 | $80.00 | $170.00 |
| 31 | Compacted aggregate (617E10100) | CY | 12 | $165.00 | $150.00 | $75.00 | $209.00 | $275.00 | $430.00 |
| 32 | Edge line, 6" (646E10010) | MI | 0.15 | $15,000 | $15,000 | $15,000 | $20,846 | $20,846 | $24,000 |
| 33 | Center line (646E10200) | MI | 0.08 | $15,000 | $15,000 | $15,000 | $44,666 | $44,666 | $51,000 |
| 34 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 4 | $2,036.48 | $2,100.00 | $2,500.00 | $2,036.00 | $2,050.00 | $3,200.00 |
| 35 | Special - work zone traffic signal (614E11300) | EACH | 2 | $15,000 | $17,500 | $15,000 | $19,950 | $29,500 | $22,500 |
| 36 | Work zone edge line, class I, 4" (614E22000) | MI | 0.14 | $17,850 | $10,000 | $18,000 | $35,715 | $35,715 | $17,000 |
| 37 | Work zone stop line, class I (614E26000) | FT | 60 | $10.00 | $10.00 | $10.00 | $5.00 | $5.00 | $30.00 |
| 38 | Pavement for maintaining traffic, class A (615E20000) | SY | 72 | $230.00 | $200.00 | $300.00 | $204.00 | $425.00 | $220.00 |
| 39 | Portable barrier, unanchored (622E41100) | FT | 116 | $45.00 | $30.00 | $65.00 | $48.00 | $48.00 | $55.00 |
| 40 | Portable barrier, anchored (622E41110) | FT | 457 | $45.00 | $40.00 | $75.00 | $60.00 | $61.00 | $50.00 |
| 41 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $55,000 | $90,000 | $150,000 | $50,734 | $135,000 | $95,000 |
| 42 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $25,000 | $70,000 | $40,000 | $55,776 | $135,000 | $120,000 |
| 43 | Unclassified excavation (503E21300) | LS | 1 | $55,000 | $72,000 | $20,000 | $120,017 | $125,000 | $35,000 |
| 44 | Pile driving equipment mobilization (505E11100) | LS | 1 | $22,000 | $30,000 | $15,000 | $6,368.00 | $30,000 | $95,000 |
| 45 | 12" cast-in-place reinforced concrete piles, driven (507E00500) | FT | 1,350 | $28.00 | $5.00 | $6.00 | $53.00 | $50.00 | $55.00 |
| 46 | 12" cast-in-place reinforced concrete piles, furnished (507E00550) | FT | 1,530 | $68.00 | $115.00 | $90.00 | $82.00 | $70.00 | $210.00 |
| 47 | Steel points or shoes (507E93300) | EACH | 36 | $450.00 | $475.00 | $500.00 | $540.00 | $367.50 | $65.00 |
| 48 | Epoxy coated steel reinforcement (509E10000) | LB | 25,598 | $2.50 | $1.95 | $1.50 | $2.00 | $2.75 | $2.00 |
| 49 | Class QC2 concrete, superstructure (511E31610) | CY | 53 | $1,500.00 | $2,000.00 | $2,000.00 | $1,459.00 | $1,800.00 | $1,900.00 |
| 50 | Class QC1 concrete, abutment not including footing (511E44110) | CY | 97 | $1,000.00 | $825.00 | $900.00 | $982.00 | $1,375.00 | $900.00 |
| 51 | Class QC1 concrete, footing (511E46510) | CY | 84 | $650.00 | $725.00 | $750.00 | $620.00 | $850.00 | $640.00 |
| 52 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 34 | $100.00 | $90.00 | $50.00 | $19.00 | $100.00 | $70.00 |
| 53 | Prestressed concrete composite box beam bridge members, level 1, CB21-36 (515E12040) | EACH | 11 | $19,000 | $20,000 | $23,000 | $23,302 | $25,500 | $17,000 |
| 54 | 2" preformed expansion joint filler (516E13900) | SF | 31 | $20.00 | $15.00 | $5.00 | $12.00 | $20.00 | $3.50 |
| 55 | Semi-integral abutment expansion joint seal (516E14020) | FT | 79 | $35.00 | $40.00 | $50.00 | $55.00 | $55.00 | $100.00 |
| 56 | Elastomeric bearing with internal laminates only (neoprene) (516E43100) | EACH | 44 | $145.00 | $150.00 | $210.00 | $206.00 | $150.00 | $100.00 |
| 57 | Jacking and temporary support of superstructure (516E47000) | LS | 1 | $20,000 | $10,000 | $40,000 | $33,730 | $45,000 | $50,000 |
| 58 | Railing (deep beam rail with steel tubular backup and type 2 steel posts and anchor bolts) (517E72300) | FT | 114 | $172.00 | $181.25 | $190.00 | $185.00 | $220.00 | $200.00 |
| 59 | Deep beam bridge retrofit railing (517E75600) | FT | 114 | $118.50 | $154.25 | $150.00 | $145.00 | $145.00 | $140.00 |
| 60 | Porous backfill with geotextile fabric (518E21200) | CY | 68 | $135.00 | $150.00 | $100.00 | $133.00 | $195.00 | $230.00 |
| 61 | Special - steel drip strip (518E22300) | FT | 141 | $22.00 | $20.00 | $15.00 | $17.00 | $16.50 | $40.00 |
| 62 | 6" perforated corrugated plastic pipe (518E40000) | FT | 98 | $15.00 | $20.00 | $12.00 | $10.00 | $17.00 | $10.00 |
| 63 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 40 | $20.00 | $20.00 | $12.00 | $29.00 | $29.00 | $10.00 |
| 64 | Dynamic load testing (523E20000) | EACH | 4 | $2,600.00 | $4,500.00 | $4,500.00 | $4,853.00 | $7,000.00 | $3,400.00 |
| 65 | Reinforced concrete approach slabs (T=13") (526E15000) | SY | 147 | $435.00 | $425.00 | $450.00 | $436.00 | $595.00 | $710.00 |
| 66 | Structure grounding system (625E33000) | EACH | 2 | $10,000 | $5,500.00 | $14,000 | $6,829.00 | $13,000 | $20,000 |
| 67 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $8,000.00 | $25,000 | $15,000 | $9,209.00 | $13,000 | $20,000 |
| 68 | Maintaining traffic (614E11000) | LS | 1 | $5,000.00 | $10,000 | $60,000 | $6,166.00 | $25,000 | $76,000 |
| 69 | Field office, type A (619E16000) | MNTH | 8 | $1,800.00 | $2,750.00 | $800.00 | $2,265.00 | $1,500.00 | $1,500.00 |
| 70 | Construction layout stakes and surveying (623E10000) | LS | 1 | $12,000 | $10,000 | $15,000 | $20,000 | $17,500 | $40,000 |
| 71 | Mobilization (624E10000) | LS | 1 | $40,000 | $75,000 | $32,947 | $68,110 | $102,000 | $120,000 |
| 100 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 168 | $120.00 | $100.00 | $115.00 | $221.00 | $95.00 | $140.00 |
| 101 | Removal of ground mounted sign and disposal (630E84900) | EACH | 4 | $17.02 | $11.00 | $50.00 | $17.00 | $25.00 | $35.00 |
| 102 | Removal of ground mounted post support and disposal (630E86002) | EACH | 4 | $22.70 | $13.00 | $50.00 | $23.00 | $50.00 | $35.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 29, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.