ODOT contract 260469 bid tabulation

MOT-Johnson Station Rd Bridge (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on October 29, 2026, MOT. 6 bids received; low bid $1,306,719 by Double Z Construction Company, -13% against the engineer's estimate of $1,510,000.

Owner
Ohio DOT
Letting
29 OCT 2026
Pay items
74
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Double Z Construction Company$1,306,719Low-13%
2Eagle Bridge Co$1,523,584+17%+1.0%
3Brumbaugh Construction Inc$1,550,000+19%+3.0%
4Sunesis Construction Co$1,612,906+23%+7.0%
5Complete General Construction Company$2,049,360+57%+36%
6Alan Stone Co Inc$2,110,167+61%+40%
ODOT contract 260469: bids by rank

Engineer's estimate: $1,510,000.

Bid tabulation

LinePay itemUnitQuantity1. Double Z Construction Company2. Eagle Bridge Co3. Brumbaugh Construction Inc4. Sunesis Construction Co5. Complete General Construction Company6. Alan Stone Co Inc
1Clearing and grubbing (201E11000)LS1$10,000$10,000$8,000.00$18,500$25,000$55,000
2Pavement removed (202E23000)SY190$40.00$20.00$15.00$21.00$85.00$35.00
3Guardrail removed (202E38000)FT191$8.00$8.00$6.00$9.00$10.00$3.50
4Gate removed (202E75250)EACH2$200.00$250.00$300.00$551.00$275.00$450.00
5Removal misc.:, as per plan (202E98100)EACH1$100.00$250.00$200.00$551.00$5,000.00$500.00
6Excavation (203E10000)CY55$40.00$130.00$25.00$26.00$40.00$20.00
7Embankment (203E20000)CY57$70.00$100.00$25.00$20.00$39.00$140.00
8Subgrade compaction (204E10000)SY253$10.00$15.00$2.00$6.00$11.00$10.00
9Proof rolling (204E45000)HR2$200.00$150.00$150.00$429.00$400.00$280.00
10Guardrail, type MGS (606E15050)FT150$22.40$48.50$35.00$35.00$35.00$25.00
11Rounded end section (606E20050)EACH2$110.00$100.00$80.00$75.00$75.00$130.00
12Anchor assembly, type A (606E25000)EACH2$1,785.00$2,275.00$2,600.00$2,500.00$2,500.00$2,000.00
13Bridge terminal assembly, type 4 (606E35140)EACH3$1,160.00$1,850.00$2,300.00$2,200.00$2,200.00$1,300.00
14Right-of-way monument, type B (623E40520)EACH3$475.00$900.00$900.00$300.00$1,000.00$620.00
15Soil analysis test (659E00100)EACH1$100.00$450.00$200.00$200.00$60.00$230.00
16Topsoil (659E00300)CY107$70.00$20.00$50.00$26.00$30.00$55.00
17Seeding and mulching, class 4A (659E00550)SY964$8.00$6.00$5.00$3.00$4.72$3.00
18Repair seeding and mulching (659E14000)SY49$9.00$3.00$2.00$2.00$4.00$15.00
19Inter-seeding (659E15000)SY49$9.00$3.00$2.00$2.00$2.00$7.00
20Commercial fertilizer (659E20000)TON0.14$850.00$1,500.00$1,000.00$350.00$600.00$690.00
21Lime (659E31000)ACRE0.20$30.00$1.00$5.00$60.00$5.00$930.00
22Water (659E35000)MGAL6$10.00$10.00$10.00$2.00$0.10$110.00
23Erosion control (832E30000)EACH1,366$1.00$1.00$1.00$1.00$1.00$1.00
24Pavement planing, asphalt concrete (T=3") (254E01000)SY911$5.10$5.10$20.00$26.00$26.00$15.00
25Asphalt concrete base, PG64-22, (449) (301E56000)CY43$375.00$375.00$500.00$545.00$545.00$550.00
26Aggregate base (304E20000)CY43$160.00$200.00$80.00$139.00$195.00$160.00
27Non-tracking tack coat (407E20000)GAL47$1.00$1.00$20.00$5.00$4.50$6.50
28Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000)CY33$450.00$450.00$525.00$742.00$742.00$470.00
29Asphalt concrete intermediate course, type 2, (449) (441E70300)CY45$405.00$405.00$500.00$444.00$443.50$400.00
30Curb, type 6 (609E26000)FT67$65.00$65.00$65.00$175.00$80.00$170.00
31Compacted aggregate (617E10100)CY12$165.00$150.00$75.00$209.00$275.00$430.00
32Edge line, 6" (646E10010)MI0.15$15,000$15,000$15,000$20,846$20,846$24,000
33Center line (646E10200)MI0.08$15,000$15,000$15,000$44,666$44,666$51,000
34Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384)EACH4$2,036.48$2,100.00$2,500.00$2,036.00$2,050.00$3,200.00
35Special - work zone traffic signal (614E11300)EACH2$15,000$17,500$15,000$19,950$29,500$22,500
36Work zone edge line, class I, 4" (614E22000)MI0.14$17,850$10,000$18,000$35,715$35,715$17,000
37Work zone stop line, class I (614E26000)FT60$10.00$10.00$10.00$5.00$5.00$30.00
38Pavement for maintaining traffic, class A (615E20000)SY72$230.00$200.00$300.00$204.00$425.00$220.00
39Portable barrier, unanchored (622E41100)FT116$45.00$30.00$65.00$48.00$48.00$55.00
40Portable barrier, anchored (622E41110)FT457$45.00$40.00$75.00$60.00$61.00$50.00
41Portions of structure removed, over 20 foot span, as per plan (202E11203)LS1$55,000$90,000$150,000$50,734$135,000$95,000
42Cofferdams and excavation bracing, as per plan (503E11101)LS1$25,000$70,000$40,000$55,776$135,000$120,000
43Unclassified excavation (503E21300)LS1$55,000$72,000$20,000$120,017$125,000$35,000
44Pile driving equipment mobilization (505E11100)LS1$22,000$30,000$15,000$6,368.00$30,000$95,000
4512" cast-in-place reinforced concrete piles, driven (507E00500)FT1,350$28.00$5.00$6.00$53.00$50.00$55.00
4612" cast-in-place reinforced concrete piles, furnished (507E00550)FT1,530$68.00$115.00$90.00$82.00$70.00$210.00
47Steel points or shoes (507E93300)EACH36$450.00$475.00$500.00$540.00$367.50$65.00
48Epoxy coated steel reinforcement (509E10000)LB25,598$2.50$1.95$1.50$2.00$2.75$2.00
49Class QC2 concrete, superstructure (511E31610)CY53$1,500.00$2,000.00$2,000.00$1,459.00$1,800.00$1,900.00
50Class QC1 concrete, abutment not including footing (511E44110)CY97$1,000.00$825.00$900.00$982.00$1,375.00$900.00
51Class QC1 concrete, footing (511E46510)CY84$650.00$725.00$750.00$620.00$850.00$640.00
52Sealing of concrete surfaces (epoxy-urethane) (512E10100)SY34$100.00$90.00$50.00$19.00$100.00$70.00
53Prestressed concrete composite box beam bridge members, level 1, CB21-36 (515E12040)EACH11$19,000$20,000$23,000$23,302$25,500$17,000
542" preformed expansion joint filler (516E13900)SF31$20.00$15.00$5.00$12.00$20.00$3.50
55Semi-integral abutment expansion joint seal (516E14020)FT79$35.00$40.00$50.00$55.00$55.00$100.00
56Elastomeric bearing with internal laminates only (neoprene) (516E43100)EACH44$145.00$150.00$210.00$206.00$150.00$100.00
57Jacking and temporary support of superstructure (516E47000)LS1$20,000$10,000$40,000$33,730$45,000$50,000
58Railing (deep beam rail with steel tubular backup and type 2 steel posts and anchor bolts) (517E72300)FT114$172.00$181.25$190.00$185.00$220.00$200.00
59Deep beam bridge retrofit railing (517E75600)FT114$118.50$154.25$150.00$145.00$145.00$140.00
60Porous backfill with geotextile fabric (518E21200)CY68$135.00$150.00$100.00$133.00$195.00$230.00
61Special - steel drip strip (518E22300)FT141$22.00$20.00$15.00$17.00$16.50$40.00
626" perforated corrugated plastic pipe (518E40000)FT98$15.00$20.00$12.00$10.00$17.00$10.00
636" non-perforated corrugated plastic pipe, including specials (518E40010)FT40$20.00$20.00$12.00$29.00$29.00$10.00
64Dynamic load testing (523E20000)EACH4$2,600.00$4,500.00$4,500.00$4,853.00$7,000.00$3,400.00
65Reinforced concrete approach slabs (T=13") (526E15000)SY147$435.00$425.00$450.00$436.00$595.00$710.00
66Structure grounding system (625E33000)EACH2$10,000$5,500.00$14,000$6,829.00$13,000$20,000
67Premium for contract performance bond and for payment bond (103E05000)LS1$8,000.00$25,000$15,000$9,209.00$13,000$20,000
68Maintaining traffic (614E11000)LS1$5,000.00$10,000$60,000$6,166.00$25,000$76,000
69Field office, type A (619E16000)MNTH8$1,800.00$2,750.00$800.00$2,265.00$1,500.00$1,500.00
70Construction layout stakes and surveying (623E10000)LS1$12,000$10,000$15,000$20,000$17,500$40,000
71Mobilization (624E10000)LS1$40,000$75,000$32,947$68,110$102,000$120,000
100Rock channel protection, type C with geotextile fabric (601E32204)CY168$120.00$100.00$115.00$221.00$95.00$140.00
101Removal of ground mounted sign and disposal (630E84900)EACH4$17.02$11.00$50.00$17.00$25.00$35.00
102Removal of ground mounted post support and disposal (630E86002)EACH4$22.70$13.00$50.00$23.00$50.00$35.00
ODOT contract 260469: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of October 29, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy