ODOT contract 250218 bid tabulation

GAL-US 35-17.43 & VARIOUS (BRIDGE PAINTING). Let by Ohio DOT on April 24, 2025, GAL. 5 bids received; low bid $2,290,838 by Elite Contractors Inc, -18% against the engineer's estimate of $2,806,000.

Owner
Ohio DOT
Letting
24 APR 2025
Pay items
57
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Elite Contractors Inc$2,290,838Low-18%
2Euro Paint LLC$2,401,159+5.0%-14%
3360 Construction Company Inc$2,757,629+20%-2.0%
4Apbn Inc$3,254,294+42%+16%
5Corrosion Resistance LTD$3,682,130+61%+31%
ODOT contract 250218: bids by rank

Engineer's estimate: $2,806,000.

Bid tabulation

LinePay itemUnitQuantity1. Elite Contractors Inc2. Euro Paint LLC3. 360 Construction Company Inc4. Apbn Inc5. Corrosion Resistance LTD
1Edge line, 6", type 1 (642E00104)MI0.24$4,700.00$3,800.00$4,700.00$4,700.00$4,700.00
2Lane line, 6", type 1 (642E00204)MI0.40$4,500.00$3,950.00$4,500.00$4,500.00$4,500.00
3Center line, type 1 (642E00300)MI0.31$4,800.00$3,750.00$4,800.00$4,800.00$4,800.00
4Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380)EACH2$1,963.57$1,963.57$1,963.57$1,963.57$2,000.00
5Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384)EACH2$2,075.69$2,075.69$2,075.69$2,075.69$2,100.00
6Work zone lighting system (614E12740)EACH1$1,000.00$5,000.00$4,713.07$22,000$4,725.00
7Barrier reflector, type 1 (1 way) (614E13310)EACH10$11.26$11.26$11.26$11.26$11.26
8Barrier reflector, type 1 (bidirectional) (614E13310)EACH26$12.95$12.95$12.95$12.95$12.95
9Object marker, one way (614E13350)EACH10$18.69$18.69$18.69$18.69$18.69
10Object marker, two way (614E13360)EACH26$19.51$19.51$19.51$19.51$19.51
11Work zone center line, class I (614E21000)MI0.20$12,800$12,800$12,800$12,800$12,800
12Work zone edge line, class I, 6" (614E22010)MI0.58$12,800$12,800$12,800$12,800$12,800
13Work zone dotted line, class I (614E24000)FT840$1.00$1.00$1.00$1.00$1.00
14Work zone stop line, class I (614E26000)FT24$8.00$8.00$8.00$8.00$8.00
15Portable barrier, unanchored (622E41100)FT780$68.65$68.65$68.65$68.65$68.65
16Removal misc.: EX wood forms (202E98000)LS1$1,000.00$500.00$650.00$1,000.00$5,300.00
17Surface preparation of existing structural steel (514E00050)SF16,992$9.00$10.00$12.00$10.00$10.10
18Field painting of existing structural steel, prime coat (514E00056)SF16,992$2.00$2.95$4.00$4.00$2.40
19Field painting structural steel, intermediate coat (514E00060)SF16,992$2.00$2.95$3.00$4.00$3.75
20Field painting structural steel, finish coat (514E00066)SF16,992$2.00$2.95$2.00$4.00$4.50
21Grinding fins, tears, slivers on existing structural steel (514E00504)MNHR26$150.00$50.00$150.00$100.00$35.00
22Final inspection repair, as per plan (514E10001)EACH16$200.00$100.00$200.00$100.00$475.00
23Refurbish bearing device, as per plan (516E45305)EACH5$950.00$950.00$950.00$950.00$950.00
24Bearing device, rocker, as per plan (516E46201)EACH7$3,480.00$3,480.00$3,480.00$3,480.00$3,480.00
25Jacking and temporary support of superstructure, as per plan (516E47001)LS1$29,750$29,750$29,750$29,750$29,750
26Scupper, vertical extension (518E12700)EACH11$950.00$950.00$950.00$950.00$950.00
27Portions of structure removed, as per plan (202E11201)LS1$35,776$35,776$35,776$35,776$35,776
28Structural steel members, level UF, as per plan (513E10201)LB3,722$27.05$27.05$27.05$27.05$27.05
29Structural steel, misc.: repair of damaged main O (513E95000)FT2$250.00$250.00$250.00$250.00$250.00
30Surface preparation of existing structural steel (514E00050)SF52,548$9.00$10.05$9.50$10.00$12.70
31Field painting of existing structural steel, prime coat (514E00056)SF52,548$2.00$2.48$3.00$5.00$4.65
32Field painting structural steel, intermediate coat (514E00060)SF52,548$2.00$2.48$3.00$4.00$6.00
33Field painting structural steel, finish coat (514E00066)SF52,548$2.00$2.48$2.00$3.00$6.10
34Grinding fins, tears, slivers on existing structural steel (514E00504)MNHR55$150.00$50.00$150.00$100.00$35.00
35Final inspection repair, as per plan (514E10001)EACH33$200.00$100.00$200.00$100.00$375.00
36Refurbish bearing device, as per plan (516E45305)EACH17$950.00$950.00$950.00$950.00$950.00
37Bearing device, rocker, as per plan (516E46201)EACH12$3,180.00$3,180.00$3,180.00$3,180.00$3,180.00
38Jacking and temporary support of superstructure, as per plan (516E47001)LS1$67,300$67,300$67,300$67,300$67,300
39Scupper, vertical extension (518E12700)EACH23$950.00$950.00$950.00$950.00$950.00
40Structural steel members, level UF (513E10200)LB146$13.55$13.55$13.55$13.55$13.55
41Surface preparation of existing structural steel (514E00050)SF9,719$12.00$10.14$18.00$10.00$16.70
42Field painting of existing structural steel, prime coat (514E00056)SF9,719$3.00$3.00$4.00$5.00$4.80
43Field painting structural steel, intermediate coat (514E00060)SF9,719$3.00$3.00$3.00$5.00$5.80
44Field painting structural steel, finish coat (514E00066)SF9,719$3.00$3.00$2.00$5.00$8.65
45Grinding fins, tears, slivers on existing structural steel (514E00504)MNHR16$150.00$50.00$150.00$100.00$35.00
46Final inspection repair, as per plan (514E10001)EACH10$200.00$100.00$200.00$100.00$475.00
47Bearing device, misc.: sliding plate (516E46900)EACH10$3,735.00$3,735.00$3,735.00$3,735.00$3,735.00
48Jacking and temporary support of superstructure, as per plan (516E47001)LS1$23,550$23,550$23,550$23,550$23,550
49Surface preparation of existing structural steel (514E00050)SF16,849$10.00$9.00$15.00$10.00$18.70
50Field painting of existing structural steel, prime coat (514E00056)SF16,849$2.00$2.08$4.00$4.00$3.10
51Field painting structural steel, intermediate coat (514E00060)SF16,849$2.00$2.08$3.00$4.00$3.45
52Field painting structural steel, finish coat (514E00066)SF16,849$2.00$2.08$2.00$4.00$5.00
53Grinding fins, tears, slivers on existing structural steel (514E00504)MNHR18$150.00$50.00$150.00$100.00$35.00
54Final inspection repair, as per plan (514E10001)EACH11$200.00$100.00$200.00$100.00$475.00
55Premium for contract performance bond and for payment bond (103E05000)LS1$50,000$20,000$35,000$30,000$35,000
56Maintaining traffic (614E11000)LS1$100,000$64,731$152,000$335,483$175,000
57Mobilization (624E10000)LS1$100,000$125,970$100,000$212,974$178,000
ODOT contract 250218: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of April 24, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy