ODOT contract 250218 bid tabulation
GAL-US 35-17.43 & VARIOUS (BRIDGE PAINTING). Let by Ohio DOT on April 24, 2025, GAL. 5 bids received; low bid $2,290,838 by Elite Contractors Inc, -18% against the engineer's estimate of $2,806,000.
- Owner
- Ohio DOT
- Letting
- 24 APR 2025
- Pay items
- 57
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Elite Contractors Inc | $2,290,838 | Low | -18% |
| 2 | Euro Paint LLC | $2,401,159 | +5.0% | -14% |
| 3 | 360 Construction Company Inc | $2,757,629 | +20% | -2.0% |
| 4 | Apbn Inc | $3,254,294 | +42% | +16% |
| 5 | Corrosion Resistance LTD | $3,682,130 | +61% | +31% |
Engineer's estimate: $2,806,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Elite Contractors Inc | 2. Euro Paint LLC | 3. 360 Construction Company Inc | 4. Apbn Inc | 5. Corrosion Resistance LTD |
|---|---|---|---|---|---|---|---|---|
| 1 | Edge line, 6", type 1 (642E00104) | MI | 0.24 | $4,700.00 | $3,800.00 | $4,700.00 | $4,700.00 | $4,700.00 |
| 2 | Lane line, 6", type 1 (642E00204) | MI | 0.40 | $4,500.00 | $3,950.00 | $4,500.00 | $4,500.00 | $4,500.00 |
| 3 | Center line, type 1 (642E00300) | MI | 0.31 | $4,800.00 | $3,750.00 | $4,800.00 | $4,800.00 | $4,800.00 |
| 4 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 2 | $1,963.57 | $1,963.57 | $1,963.57 | $1,963.57 | $2,000.00 |
| 5 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 2 | $2,075.69 | $2,075.69 | $2,075.69 | $2,075.69 | $2,100.00 |
| 6 | Work zone lighting system (614E12740) | EACH | 1 | $1,000.00 | $5,000.00 | $4,713.07 | $22,000 | $4,725.00 |
| 7 | Barrier reflector, type 1 (1 way) (614E13310) | EACH | 10 | $11.26 | $11.26 | $11.26 | $11.26 | $11.26 |
| 8 | Barrier reflector, type 1 (bidirectional) (614E13310) | EACH | 26 | $12.95 | $12.95 | $12.95 | $12.95 | $12.95 |
| 9 | Object marker, one way (614E13350) | EACH | 10 | $18.69 | $18.69 | $18.69 | $18.69 | $18.69 |
| 10 | Object marker, two way (614E13360) | EACH | 26 | $19.51 | $19.51 | $19.51 | $19.51 | $19.51 |
| 11 | Work zone center line, class I (614E21000) | MI | 0.20 | $12,800 | $12,800 | $12,800 | $12,800 | $12,800 |
| 12 | Work zone edge line, class I, 6" (614E22010) | MI | 0.58 | $12,800 | $12,800 | $12,800 | $12,800 | $12,800 |
| 13 | Work zone dotted line, class I (614E24000) | FT | 840 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 14 | Work zone stop line, class I (614E26000) | FT | 24 | $8.00 | $8.00 | $8.00 | $8.00 | $8.00 |
| 15 | Portable barrier, unanchored (622E41100) | FT | 780 | $68.65 | $68.65 | $68.65 | $68.65 | $68.65 |
| 16 | Removal misc.: EX wood forms (202E98000) | LS | 1 | $1,000.00 | $500.00 | $650.00 | $1,000.00 | $5,300.00 |
| 17 | Surface preparation of existing structural steel (514E00050) | SF | 16,992 | $9.00 | $10.00 | $12.00 | $10.00 | $10.10 |
| 18 | Field painting of existing structural steel, prime coat (514E00056) | SF | 16,992 | $2.00 | $2.95 | $4.00 | $4.00 | $2.40 |
| 19 | Field painting structural steel, intermediate coat (514E00060) | SF | 16,992 | $2.00 | $2.95 | $3.00 | $4.00 | $3.75 |
| 20 | Field painting structural steel, finish coat (514E00066) | SF | 16,992 | $2.00 | $2.95 | $2.00 | $4.00 | $4.50 |
| 21 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 26 | $150.00 | $50.00 | $150.00 | $100.00 | $35.00 |
| 22 | Final inspection repair, as per plan (514E10001) | EACH | 16 | $200.00 | $100.00 | $200.00 | $100.00 | $475.00 |
| 23 | Refurbish bearing device, as per plan (516E45305) | EACH | 5 | $950.00 | $950.00 | $950.00 | $950.00 | $950.00 |
| 24 | Bearing device, rocker, as per plan (516E46201) | EACH | 7 | $3,480.00 | $3,480.00 | $3,480.00 | $3,480.00 | $3,480.00 |
| 25 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $29,750 | $29,750 | $29,750 | $29,750 | $29,750 |
| 26 | Scupper, vertical extension (518E12700) | EACH | 11 | $950.00 | $950.00 | $950.00 | $950.00 | $950.00 |
| 27 | Portions of structure removed, as per plan (202E11201) | LS | 1 | $35,776 | $35,776 | $35,776 | $35,776 | $35,776 |
| 28 | Structural steel members, level UF, as per plan (513E10201) | LB | 3,722 | $27.05 | $27.05 | $27.05 | $27.05 | $27.05 |
| 29 | Structural steel, misc.: repair of damaged main O (513E95000) | FT | 2 | $250.00 | $250.00 | $250.00 | $250.00 | $250.00 |
| 30 | Surface preparation of existing structural steel (514E00050) | SF | 52,548 | $9.00 | $10.05 | $9.50 | $10.00 | $12.70 |
| 31 | Field painting of existing structural steel, prime coat (514E00056) | SF | 52,548 | $2.00 | $2.48 | $3.00 | $5.00 | $4.65 |
| 32 | Field painting structural steel, intermediate coat (514E00060) | SF | 52,548 | $2.00 | $2.48 | $3.00 | $4.00 | $6.00 |
| 33 | Field painting structural steel, finish coat (514E00066) | SF | 52,548 | $2.00 | $2.48 | $2.00 | $3.00 | $6.10 |
| 34 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 55 | $150.00 | $50.00 | $150.00 | $100.00 | $35.00 |
| 35 | Final inspection repair, as per plan (514E10001) | EACH | 33 | $200.00 | $100.00 | $200.00 | $100.00 | $375.00 |
| 36 | Refurbish bearing device, as per plan (516E45305) | EACH | 17 | $950.00 | $950.00 | $950.00 | $950.00 | $950.00 |
| 37 | Bearing device, rocker, as per plan (516E46201) | EACH | 12 | $3,180.00 | $3,180.00 | $3,180.00 | $3,180.00 | $3,180.00 |
| 38 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $67,300 | $67,300 | $67,300 | $67,300 | $67,300 |
| 39 | Scupper, vertical extension (518E12700) | EACH | 23 | $950.00 | $950.00 | $950.00 | $950.00 | $950.00 |
| 40 | Structural steel members, level UF (513E10200) | LB | 146 | $13.55 | $13.55 | $13.55 | $13.55 | $13.55 |
| 41 | Surface preparation of existing structural steel (514E00050) | SF | 9,719 | $12.00 | $10.14 | $18.00 | $10.00 | $16.70 |
| 42 | Field painting of existing structural steel, prime coat (514E00056) | SF | 9,719 | $3.00 | $3.00 | $4.00 | $5.00 | $4.80 |
| 43 | Field painting structural steel, intermediate coat (514E00060) | SF | 9,719 | $3.00 | $3.00 | $3.00 | $5.00 | $5.80 |
| 44 | Field painting structural steel, finish coat (514E00066) | SF | 9,719 | $3.00 | $3.00 | $2.00 | $5.00 | $8.65 |
| 45 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 16 | $150.00 | $50.00 | $150.00 | $100.00 | $35.00 |
| 46 | Final inspection repair, as per plan (514E10001) | EACH | 10 | $200.00 | $100.00 | $200.00 | $100.00 | $475.00 |
| 47 | Bearing device, misc.: sliding plate (516E46900) | EACH | 10 | $3,735.00 | $3,735.00 | $3,735.00 | $3,735.00 | $3,735.00 |
| 48 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $23,550 | $23,550 | $23,550 | $23,550 | $23,550 |
| 49 | Surface preparation of existing structural steel (514E00050) | SF | 16,849 | $10.00 | $9.00 | $15.00 | $10.00 | $18.70 |
| 50 | Field painting of existing structural steel, prime coat (514E00056) | SF | 16,849 | $2.00 | $2.08 | $4.00 | $4.00 | $3.10 |
| 51 | Field painting structural steel, intermediate coat (514E00060) | SF | 16,849 | $2.00 | $2.08 | $3.00 | $4.00 | $3.45 |
| 52 | Field painting structural steel, finish coat (514E00066) | SF | 16,849 | $2.00 | $2.08 | $2.00 | $4.00 | $5.00 |
| 53 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 18 | $150.00 | $50.00 | $150.00 | $100.00 | $35.00 |
| 54 | Final inspection repair, as per plan (514E10001) | EACH | 11 | $200.00 | $100.00 | $200.00 | $100.00 | $475.00 |
| 55 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $50,000 | $20,000 | $35,000 | $30,000 | $35,000 |
| 56 | Maintaining traffic (614E11000) | LS | 1 | $100,000 | $64,731 | $152,000 | $335,483 | $175,000 |
| 57 | Mobilization (624E10000) | LS | 1 | $100,000 | $125,970 | $100,000 | $212,974 | $178,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 24, 2025. Compiled by Mirage Metrics.