ODOT contract 250498 bid tabulation

HAN-SR 37-06.47 (TWO LANE RESURFACING). Let by Ohio DOT on October 23, 2025, HAN. 4 bids received; low bid $2,483,258 by Shelly Company, -8.4% against the engineer's estimate of $2,710,000.

Owner
Ohio DOT
Letting
23 OCT 2025
Pay items
36
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Shelly Company$2,483,258Low-8.0%
2Bluffton Paving Inc$2,566,712+3.0%-5.0%
3M & B Asphalt Co Inc$2,592,903+4.0%-4.0%
4Kokosing Construction Company Inc$2,607,427+5.0%-4.0%
ODOT contract 250498: bids by rank

Engineer's estimate: $2,710,000.

Bid tabulation

LinePay itemUnitQuantity1. Shelly Company2. Bluffton Paving Inc3. M & B Asphalt Co Inc4. Kokosing Construction Company Inc
1Wearing course removed (202E23500)SY5,690$4.50$4.00$5.00$5.50
2Walk removed (202E30000)SF730$6.00$17.00$6.00$6.00
3Curb and gutter removed (202E32500)FT85$13.50$20.00$13.50$13.50
4Curb ramp (608E52000)SF984$18.00$30.00$18.00$18.00
5Combination curb and gutter, type 2 (609E12000)FT10$80.00$75.00$80.00$80.00
6Topsoil (659E00300)CY1$150.00$1,000.00$200.00$150.00
7Seeding and mulching (659E10000)SY22$10.00$50.00$12.00$10.00
8Commercial fertilizer (659E20000)TON0.10$1,500.00$1,500.00$1,500.00$1,500.00
9Water (659E35000)MGAL0.12$50.00$100.00$50.00$50.00
10Erosion control (832E30000)EACH1,000$1.00$1.00$1.00$1.00
11Pavement repair (253E02000)CY650$240.00$295.00$300.00$300.00
12Pavement planing, asphalt concrete, 1.25" depth (254E01000)SY211,391$1.40$1.36$1.40$1.15
13Patching planed surface (254E01600)SY4,228$5.00$5.00$7.00$1.25
14Aggregate base (304E20000)CY64$200.00$25.00$100.00$30.00
15Non-tracking tack coat (407E20000)GAL18,451$2.25$2.20$2.60$3.00
16Asphalt concrete surface course, type 1, (446), PG64-22 (441E10000)CY7,338$200.00$210.80$195.00$200.00
17Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000)CY197$325.00$326.00$415.00$380.00
18Compacted aggregate, as per plan (617E10101)CY1,751$67.00$53.60$75.00$30.00
19Rumble stripes, edge line (asphalt concrete) (618E41000)MI11.92$895.00$750.00$1,200.00$885.00
20Longitudinal joint adhesive (875E10000)LB1,130$0.65$3.25$0.50$0.70
21RPM (621E00100)EACH824$38.75$37.75$40.00$35.00
22Raised pavement marker removed (621E54000)EACH824$6.00$5.50$4.00$2.00
23Edge line, 6", type 1 (642E00104)MI26.08$850.00$800.00$850.00$800.00
24Center line, type 1 (642E00300)MI13.52$850.00$950.00$850.00$950.00
25Stop line (644E00500)FT183$8.00$8.00$8.00$8.00
26Crosswalk line, 12" (644E00620)FT182$4.00$4.00$4.00$4.00
27Crosswalk line, 24" (644E00630)FT126$8.00$8.00$8.00$8.00
28School symbol marking, 96" (644E01110)EACH2$250.00$700.00$250.00$700.00
29Parking lot stall marking (644E01200)FT896$1.50$3.00$1.50$3.00
30Dotted line, 6" (644E01510)FT100$1.00$3.00$1.00$3.00
31Work zone marking sign (614E12460)EACH90$85.00$90.00$85.00$104.71
32Work zone center line, class I (614E21000)MI13.52$850.00$950.00$850.00$950.00
33Work zone center line, class II (614E21400)MI27.04$500.00$500.00$400.00$50.00
34Premium for contract performance bond and for payment bond (103E05000)LS1$6,000.00$20,000$20,000$10,400
35Maintaining traffic (614E11000)LS1$60,000$74,800$80,000$207,775
36Mobilization (624E10000)LS1$70,000$30,000$100,000$130,000
ODOT contract 250498: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of October 23, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy