ODOT contract 250498 bid tabulation
HAN-SR 37-06.47 (TWO LANE RESURFACING). Let by Ohio DOT on October 23, 2025, HAN. 4 bids received; low bid $2,483,258 by Shelly Company, -8.4% against the engineer's estimate of $2,710,000.
- Owner
- Ohio DOT
- Letting
- 23 OCT 2025
- Pay items
- 36
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly Company | $2,483,258 | Low | -8.0% |
| 2 | Bluffton Paving Inc | $2,566,712 | +3.0% | -5.0% |
| 3 | M & B Asphalt Co Inc | $2,592,903 | +4.0% | -4.0% |
| 4 | Kokosing Construction Company Inc | $2,607,427 | +5.0% | -4.0% |
Engineer's estimate: $2,710,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly Company | 2. Bluffton Paving Inc | 3. M & B Asphalt Co Inc | 4. Kokosing Construction Company Inc |
|---|---|---|---|---|---|---|---|
| 1 | Wearing course removed (202E23500) | SY | 5,690 | $4.50 | $4.00 | $5.00 | $5.50 |
| 2 | Walk removed (202E30000) | SF | 730 | $6.00 | $17.00 | $6.00 | $6.00 |
| 3 | Curb and gutter removed (202E32500) | FT | 85 | $13.50 | $20.00 | $13.50 | $13.50 |
| 4 | Curb ramp (608E52000) | SF | 984 | $18.00 | $30.00 | $18.00 | $18.00 |
| 5 | Combination curb and gutter, type 2 (609E12000) | FT | 10 | $80.00 | $75.00 | $80.00 | $80.00 |
| 6 | Topsoil (659E00300) | CY | 1 | $150.00 | $1,000.00 | $200.00 | $150.00 |
| 7 | Seeding and mulching (659E10000) | SY | 22 | $10.00 | $50.00 | $12.00 | $10.00 |
| 8 | Commercial fertilizer (659E20000) | TON | 0.10 | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 9 | Water (659E35000) | MGAL | 0.12 | $50.00 | $100.00 | $50.00 | $50.00 |
| 10 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 11 | Pavement repair (253E02000) | CY | 650 | $240.00 | $295.00 | $300.00 | $300.00 |
| 12 | Pavement planing, asphalt concrete, 1.25" depth (254E01000) | SY | 211,391 | $1.40 | $1.36 | $1.40 | $1.15 |
| 13 | Patching planed surface (254E01600) | SY | 4,228 | $5.00 | $5.00 | $7.00 | $1.25 |
| 14 | Aggregate base (304E20000) | CY | 64 | $200.00 | $25.00 | $100.00 | $30.00 |
| 15 | Non-tracking tack coat (407E20000) | GAL | 18,451 | $2.25 | $2.20 | $2.60 | $3.00 |
| 16 | Asphalt concrete surface course, type 1, (446), PG64-22 (441E10000) | CY | 7,338 | $200.00 | $210.80 | $195.00 | $200.00 |
| 17 | Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000) | CY | 197 | $325.00 | $326.00 | $415.00 | $380.00 |
| 18 | Compacted aggregate, as per plan (617E10101) | CY | 1,751 | $67.00 | $53.60 | $75.00 | $30.00 |
| 19 | Rumble stripes, edge line (asphalt concrete) (618E41000) | MI | 11.92 | $895.00 | $750.00 | $1,200.00 | $885.00 |
| 20 | Longitudinal joint adhesive (875E10000) | LB | 1,130 | $0.65 | $3.25 | $0.50 | $0.70 |
| 21 | RPM (621E00100) | EACH | 824 | $38.75 | $37.75 | $40.00 | $35.00 |
| 22 | Raised pavement marker removed (621E54000) | EACH | 824 | $6.00 | $5.50 | $4.00 | $2.00 |
| 23 | Edge line, 6", type 1 (642E00104) | MI | 26.08 | $850.00 | $800.00 | $850.00 | $800.00 |
| 24 | Center line, type 1 (642E00300) | MI | 13.52 | $850.00 | $950.00 | $850.00 | $950.00 |
| 25 | Stop line (644E00500) | FT | 183 | $8.00 | $8.00 | $8.00 | $8.00 |
| 26 | Crosswalk line, 12" (644E00620) | FT | 182 | $4.00 | $4.00 | $4.00 | $4.00 |
| 27 | Crosswalk line, 24" (644E00630) | FT | 126 | $8.00 | $8.00 | $8.00 | $8.00 |
| 28 | School symbol marking, 96" (644E01110) | EACH | 2 | $250.00 | $700.00 | $250.00 | $700.00 |
| 29 | Parking lot stall marking (644E01200) | FT | 896 | $1.50 | $3.00 | $1.50 | $3.00 |
| 30 | Dotted line, 6" (644E01510) | FT | 100 | $1.00 | $3.00 | $1.00 | $3.00 |
| 31 | Work zone marking sign (614E12460) | EACH | 90 | $85.00 | $90.00 | $85.00 | $104.71 |
| 32 | Work zone center line, class I (614E21000) | MI | 13.52 | $850.00 | $950.00 | $850.00 | $950.00 |
| 33 | Work zone center line, class II (614E21400) | MI | 27.04 | $500.00 | $500.00 | $400.00 | $50.00 |
| 34 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $6,000.00 | $20,000 | $20,000 | $10,400 |
| 35 | Maintaining traffic (614E11000) | LS | 1 | $60,000 | $74,800 | $80,000 | $207,775 |
| 36 | Mobilization (624E10000) | LS | 1 | $70,000 | $30,000 | $100,000 | $130,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 23, 2025. Compiled by Mirage Metrics.