ODOT contract 250512 bid tabulation

FRA-EXPO CENTER/OHC-FY2026 (PARKING AREAS). Let by Ohio DOT on October 23, 2025, FRA. 7 bids received; low bid $1,024,417 by Shelly Company, -17% against the engineer's estimate of $1,232,000.

Owner
Ohio DOT
Letting
23 OCT 2025
Pay items
31
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Shelly Company$1,024,417Low-17%
2Strawser Paving Co Inc$1,110,197+8.0%-10%
3Shelly & Sands Inc$1,115,455+9.0%-9.0%
4George J Igel & Co Inc$1,174,917+15%-5.0%
5Kokosing Construction Company Inc$1,208,218+18%-2.0%
6Fillmore Construction$1,427,550+39%+16%
7Alan Stone Co Inc$1,600,755+56%+30%
ODOT contract 250512: bids by rank

Engineer's estimate: $1,232,000.

Bid tabulation

LinePay itemUnitQuantity1. Shelly Company2. Strawser Paving Co Inc3. Shelly & Sands Inc4. George J Igel & Co Inc5. Kokosing Construction Company Inc6. Fillmore Construction
1Pavement removed, as per plan (202E23001)SY27,526$2.30$5.25$5.10$2.40$4.64$3.75
2Curb removed, as per plan (202E32001)FT2,221$4.25$18.00$8.50$5.50$23.00$10.00
3Subgrade compaction (204E10000)SY27,526$1.00$0.50$1.00$1.00$0.30$3.00
4Erosion control (832E30000)EACH1,000$1.00$1.00$1.00$1.00$1.00$1.00
5Pavement repair, as per plan (253E01001)SY66$84.00$55.00$70.00$82.00$223.00$150.00
6Pavement repair, as per plan (253E01001)SY226$85.00$68.00$75.00$66.00$225.00$200.00
7Pavement planing, asphalt CONCRETE1.5" (254E01000)SY10,336$3.00$1.80$2.00$1.75$4.50$2.00
8Asphalt concrete base, PG64-22, (449) (301E56000)CY2,296$151.00$163.00$165.00$192.00$147.00$184.00
9Non-tracking tack coat (407E20000)GAL2,399$4.00$5.00$3.50$4.75$2.65$3.50
10Asphalt concrete surface course, type 1, (446), PG64-22 (441E10000)CY1,585$203.00$226.75$190.00$251.00$208.00$226.00
11Curb, type 6 (609E26000)FT2,221$36.50$26.00$40.00$23.50$36.00$100.00
12Ground mounted support, no. 2 post (630E02100)FT126$16.00$15.00$20.25$19.50$16.00$16.00
13Ground mounted support, no. 3 post (630E03100)FT180$16.50$30.00$20.85$22.00$16.50$16.50
14Sign, flat sheet (630E80100)SF68.50$18.00$35.00$22.80$34.00$18.00$18.00
15Removal of ground mounted sign and disposal (630E84900)EACH14$25.00$35.00$31.50$65.00$125.00$25.00
16Removal of ground mounted sign and reerection (630E85100)EACH4$50.00$100.00$63.50$140.00$150.00$50.00
17Edge line, 4" (644E00100)MI0.01$25,000$25,000$25,000$25,000$25,000$25,000
18Parking lot stall marking (644E01200)FT19,012$1.89$1.89$1.89$1.90$1.89$1.89
19Handicap symbol marking (644E01600)EACH27$110.00$110.00$110.00$110.00$110.00$110.00
20Premium on railroads' protective public liability and property damage liability insurance (100E00300)LS1$4,500.00$3,750.00$3,310.00$5,000.00$4,000.00$8,500.00
21Premium for contract performance bond and for payment bond (103E05000)LS1$5,000.00$5,500.00$4,256.32$6,000.00$5,000.00$8,500.00
22Maintaining traffic (614E11000)LS1$5,000.00$1,500.00$10,500$5,000.00$24,474$17,500
23Construction layout stakes and surveying, as per plan (623E10001)LS1$9,500.00$1,500.00$5,000.00$3,700.00$318.88$17,500
24Mobilization (624E10000)LS1$27,500$2,500.00$30,000$52,500$60,000$25,000
100Topsoil (659E00300)CY51$135.00$75.00$75.00$50.00$185.00$100.00
101Seeding and mulching (659E10000)SY493$6.90$3.00$6.50$4.55$6.50$5.00
102Repair seeding and mulching (659E14000)SY24$10.00$1.00$6.50$5.00$6.50$5.00
103Inter-seeding (659E15000)SY24$10.00$1.00$6.50$5.00$6.50$5.00
104Commercial fertilizer (659E20000)TON0.07$800.00$1,000.00$800.00$2,850.00$1,250.00$5,000.00
105Lime (659E31000)ACRE0.10$20.00$500.00$20.00$2,000.00$150.00$5,000.00
106Water (659E35000)MGAL2$10.00$1.00$10.00$125.00$1.00$10.00
ODOT contract 250512: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of October 23, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy