ODOT contract 254029 bid tabulation
LAW-SR 140-00.09 (CULVERT REPLACEMENT). Let by Ohio DOT on October 23, 2025, LAW. 2 bids received; low bid $678,613 by Axis Civil Construction LLC, +19% against the engineer's estimate of $571,000.
- Owner
- Ohio DOT
- Letting
- 23 OCT 2025
- Pay items
- 61
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Axis Civil Construction LLC | $678,613 | Low | +19% |
| 2 | Alan Stone Co Inc | $716,538 | +6.0% | +25% |
Engineer's estimate: $571,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Axis Civil Construction LLC | 2. Alan Stone Co Inc |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $10,000 | $25,000 |
| 2 | Pavement removed (202E23000) | SY | 1,224 | $11.00 | $23.54 |
| 3 | Pipe removed, 24" and under (202E35100) | FT | 28 | $35.00 | $27.48 |
| 4 | Pipe removed, over 24", as per plan (202E35201) | FT | 39 | $160.00 | $69.32 |
| 5 | Excavation (203E10000) | CY | 418 | $34.00 | $33.98 |
| 6 | Embankment (203E20000) | CY | 203 | $34.00 | $32.20 |
| 7 | Subgrade compaction (204E10000) | SY | 1,518 | $2.00 | $4.62 |
| 8 | Granular material, type B (204E30010) | CY | 257 | $225.00 | $125.00 |
| 9 | Proof rolling (204E45000) | HR | 1 | $3,200.00 | $220.00 |
| 10 | Guardrail, type MGS (606E15050) | FT | 337.50 | $22.52 | $27.51 |
| 11 | Anchor assembly, MGS type E (MASH 2016) (606E26150) | EACH | 3 | $2,280.00 | $2,632.36 |
| 12 | Anchor assembly, MGS type T (606E26550) | EACH | 1 | $1,050.00 | $1,216.89 |
| 13 | Monument assembly, type C (623E38500) | EACH | 3 | $2,250.00 | $976.30 |
| 14 | Rock channel protection, type B with geotextile fabric (601E32104) | CY | 46 | $135.00 | $217.13 |
| 15 | Topsoil (659E00300) | CY | 180 | $55.00 | $45.00 |
| 16 | Seeding and mulching (659E10000) | SY | 1,624 | $2.25 | $4.27 |
| 17 | Commercial fertilizer (659E20000) | TON | 0.22 | $1,250.00 | $979.41 |
| 18 | Lime (659E31000) | ACRE | 0.34 | $150.00 | $400.06 |
| 19 | Water (659E35000) | MGAL | 9 | $1.00 | $12.97 |
| 20 | Erosion control (832E30000) | EACH | 53,151 | $1.00 | $1.00 |
| 21 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $32,000 | $500.00 |
| 22 | Unclassified excavation (503E21100) | CY | 277 | $85.00 | $133.56 |
| 23 | Epoxy coated steel reinforcement (509E10000) | LB | 3,980 | $2.70 | $2.34 |
| 24 | Class QC1 concrete, retaining/wingwall not including footing (511E46010) | CY | 8 | $2,550.00 | $5,000.00 |
| 25 | Class QC1 concrete, footing (511E46510) | CY | 24 | $1,150.00 | $594.21 |
| 26 | Class QC1 concrete, headwall (511E46610) | CY | 1 | $3,500.00 | $2,217.94 |
| 27 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 45 | $85.00 | $32.64 |
| 28 | Type 2 waterproofing (512E33000) | SY | 53 | $38.39 | $33.35 |
| 29 | Type 3 waterproofing (512E33010) | SY | 55 | $50.00 | $45.45 |
| 30 | 1" preformed expansion joint filler (516E13600) | SF | 25 | $10.00 | $11.36 |
| 31 | Porous backfill with geotextile fabric (518E21200) | CY | 7 | $550.00 | $136.31 |
| 32 | Aggregate drains (605E31100) | FT | 152 | $18.00 | $19.72 |
| 33 | 6" conduit, type E (611E01400) | FT | 30 | $25.00 | $15.14 |
| 34 | 6" conduit, type F (611E01500) | FT | 30 | $25.00 | $21.09 |
| 35 | 12" conduit, type D (611E04900) | FT | 40 | $65.00 | $79.47 |
| 36 | 8' X 4' conduit, type A, 706.05 (611E94800) | FT | 44 | $1,650.00 | $1,500.00 |
| 37 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 237 | $255.00 | $364.15 |
| 38 | Aggregate base (304E20000) | CY | 246 | $160.00 | $103.74 |
| 39 | Tack coat (407E10000) | GAL | 187 | $6.00 | $4.72 |
| 40 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 131 | $340.00 | $377.56 |
| 41 | Compacted aggregate (617E10100) | CY | 25 | $120.00 | $110.46 |
| 42 | RPM (621E00100) | EACH | 5 | $700.00 | $232.88 |
| 43 | Raised pavement marker removed (621E54000) | EACH | 5 | $50.00 | $24.15 |
| 44 | Barrier reflector, type 3 (BI-directional) (626E00112) | EACH | 7 | $10.00 | $11.32 |
| 45 | Ground mounted support, no. 3 post (630E03100) | FT | 34.60 | $14.00 | $19.90 |
| 46 | Sign, flat sheet (630E80100) | SF | 19.30 | $28.00 | $34.43 |
| 47 | Removal of ground mounted sign and disposal (630E84900) | EACH | 3 | $15.00 | $31.14 |
| 48 | Removal of ground mounted post support and disposal (630E86002) | EACH | 3 | $15.00 | $37.13 |
| 49 | Edge line, 6", type 1 (642E00104) | MI | 0.16 | $5,675.00 | $6,518.69 |
| 50 | Center line, type 1 (642E00300) | MI | 0.08 | $11,250 | $11,359 |
| 51 | Pavement repair (253E02000) | CY | 50 | $220.00 | $332.62 |
| 52 | Detour signing (614E12420) | LS | 1 | $6,500.00 | $6,930.90 |
| 53 | Asphalt concrete for maintaining traffic (614E13000) | CY | 25 | $225.00 | $253.46 |
| 54 | Water (616E10000) | MGAL | 2 | $1.00 | $1.00 |
| 55 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $8,500.00 | $12,000 |
| 56 | Maintaining traffic (614E11000) | LS | 1 | $7,500.00 | $6,500.00 |
| 57 | Field office, type A (619E16000) | MNTH | 2 | $3,200.00 | $1,478.33 |
| 58 | Construction layout stakes and surveying (623E10000) | LS | 1 | $15,000 | $18,000 |
| 59 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $800.00 | $2,000.00 |
| 60 | Post construction survey monument verification and report (623E51000) | LS | 1 | $800.00 | $2,000.00 |
| 61 | Mobilization (624E10000) | LS | 1 | $40,000 | $72,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 23, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.