ODOT contract 250514 bid tabulation
MAH-/TRU SIGN FY2026 (Systematic) (SIGNING). Let by Ohio DOT on October 23, 2025, MAH. 2 bids received; low bid $1,928,550 by Lake Erie Construction Company, -7.8% against the engineer's estimate of $2,091,000.
- Owner
- Ohio DOT
- Letting
- 23 OCT 2025
- Pay items
- 39
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Lake Erie Construction Company | $1,928,550 | Low | -8.0% |
| 2 | Cleveland Barricading Systems LLC | $2,129,611 | +10% | +2.0% |
Engineer's estimate: $2,091,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Lake Erie Construction Company | 2. Cleveland Barricading Systems LLC |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $2,250.00 | $1,500.00 |
| 2 | Erosion control (832E30000) | EACH | 3,000 | $1.00 | $1.00 |
| 3 | Ground mounted support, no. 2 post (630E02100) | FT | 1,669 | $9.00 | $6.45 |
| 4 | Ground mounted support, no. 3 post, as per plan (630E03101) | FT | 45,108 | $9.75 | $7.60 |
| 5 | Ground mounted support, no. 3 post, as per plan (630E03101) | FT | 171 | $12.00 | $11.85 |
| 6 | Ground mounted structural beam support, S4X7.7 (630E06400) | FT | 60 | $40.00 | $29.00 |
| 7 | Ground mounted structural beam support, W10X22 (630E07500) | FT | 48 | $64.00 | $63.00 |
| 8 | Ground mounted structural beam support, W10X12 (630E07600) | FT | 36 | $50.00 | $39.50 |
| 9 | One way support, no. 3 post (630E08004) | FT | 94 | $13.00 | $103.00 |
| 10 | Sign post reflector (630E08600) | EACH | 954 | $30.00 | $18.85 |
| 11 | Sign post reflector (630E08600) | EACH | 1,047 | $30.00 | $18.50 |
| 12 | Sign post reflector (630E08600) | EACH | 824 | $30.00 | $18.50 |
| 13 | Sign post reflector (630E08600) | EACH | 72 | $30.00 | $18.50 |
| 14 | Breakaway structural beam connection (630E09000) | EACH | 8 | $780.00 | $525.00 |
| 15 | Sign attachment assembly (630E75000) | EACH | 193 | $785.00 | $495.00 |
| 16 | Sign hanger assembly, span wire (630E79000) | EACH | 19 | $425.00 | $400.00 |
| 17 | Sign hanger assembly, mast arm (630E79100) | EACH | 50 | $320.00 | $415.00 |
| 18 | Sign support assembly, pole mounted (630E79500) | EACH | 624 | $85.00 | $97.00 |
| 19 | Sign, flat sheet (630E80100) | SF | 29,453 | $13.00 | $13.65 |
| 20 | Sign, ground mounted extrusheet (630E80200) | SF | 15,084 | $22.00 | $21.30 |
| 21 | Sign, overhead extrusheet (630E80224) | SF | 7,845 | $22.00 | $23.00 |
| 22 | Sign backing assembly (630E82000) | EACH | 62 | $180.00 | $170.00 |
| 23 | Ground mounted structural beam support foundation (630E84500) | EACH | 8 | $1,050.00 | $1,250.00 |
| 24 | Removal of ground mounted sign and disposal (630E84900) | EACH | 4,661 | $8.00 | $14.35 |
| 25 | Removal of ground mounted sign and reerection (630E85100) | EACH | 64 | $59.00 | $74.00 |
| 26 | Removal of ground mounted sign and reerection, as per plan (630E85101) | EACH | 81 | $65.00 | $72.50 |
| 27 | Removal of ground mounted major sign and disposal (630E85400) | EACH | 170 | $185.00 | $450.00 |
| 28 | Removal of ground mounted post support and disposal (630E86002) | EACH | 3,784 | $11.00 | $16.00 |
| 29 | Removal of ground mounted wooden box beam support (630E86292) | EACH | 8 | $225.00 | $230.00 |
| 30 | Removal of overhead mounted sign and disposal (630E87400) | EACH | 164 | $150.00 | $280.00 |
| 31 | Removal of overhead mounted sign and disposal, as per plan (630E87401) | EACH | 1 | $1,200.00 | $1,415.00 |
| 32 | Removal of pole mounted sign and disposal (630E87500) | EACH | 607 | $35.00 | $25.50 |
| 33 | Removal of miscellaneous traffic control item, pos (630E89902) | EACH | 5 | $95.00 | $20.00 |
| 34 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 40 | $65.00 | $115.00 |
| 35 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $10,000 | $8,400.00 |
| 36 | Maintaining traffic (614E11000) | LS | 1 | $7,500.00 | $157,000 |
| 37 | Field office, type B (619E16010) | MNTH | 6 | $500.00 | $1,500.00 |
| 38 | Construction layout stakes and surveying (623E10000) | LS | 1 | $7,450.00 | $43,500 |
| 39 | Mobilization (624E10000) | LS | 1 | $30,000 | $85,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 23, 2025. Compiled by Mirage Metrics.