ODOT contract 250513 bid tabulation
HUR-SR 303-02.42 (CULVERT REPLACEMENT). Let by Ohio DOT on October 23, 2025, HUR. 8 bids received; low bid $213,607 by Great Lakes Demolition Company, -6.3% against the engineer's estimate of $228,000.
- Owner
- Ohio DOT
- Letting
- 23 OCT 2025
- Pay items
- 49
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Great Lakes Demolition Company | $213,607 | Low | -6.0% |
| 2 | Crawford Construction Company Inc | $218,770 | +2.0% | -4.0% |
| 3 | BCC Ohio Inc | $250,990 | +18% | +10% |
| 4 | Adena Corporation | $254,280 | +19% | +12% |
| 5 | Buckeye Excavating & Construction Inc | $255,224 | +19% | +12% |
| 6 | Eclipse Co LLC | $266,959 | +25% | +17% |
| 7 | Stanley Miller Construction Company | $289,642 | +36% | +27% |
| 8 | Madex Construction Co | $335,346 | +57% | +47% |
Engineer's estimate: $228,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Great Lakes Demolition Company | 2. Crawford Construction Company Inc | 3. BCC Ohio Inc | 4. Adena Corporation | 5. Buckeye Excavating & Construction Inc | 6. Eclipse Co LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $8,500.00 | $2,900.00 | $20,768 | $22,133 | $13,200 | $16,500 |
| 2 | Headwall removed (202E20010) | EACH | 2 | $250.00 | $360.00 | $774.00 | $299.81 | $1,500.00 | $1,365.45 |
| 3 | Pavement removed (202E23000) | SY | 289 | $20.00 | $15.00 | $14.86 | $20.00 | $11.00 | $20.26 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 67 | $25.00 | $44.00 | $30.81 | $39.31 | $48.00 | $83.28 |
| 5 | Excavation (203E10000) | CY | 31 | $20.00 | $70.00 | $128.95 | $11.78 | $42.00 | $65.73 |
| 6 | Embankment (203E20000) | CY | 219 | $25.00 | $20.00 | $35.09 | $26.71 | $49.00 | $58.85 |
| 7 | Subgrade compaction (204E10000) | SY | 323 | $3.00 | $2.00 | $3.87 | $2.26 | $1.50 | $2.58 |
| 8 | Guardrail, type MGS (606E15050) | FT | 150 | $25.00 | $27.00 | $24.57 | $28.29 | $24.00 | $25.74 |
| 9 | Anchor assembly, MGS type E (606E26150) | EACH | 3 | $2,700.00 | $2,740.00 | $2,693.25 | $3,522.85 | $2,700.00 | $2,821.50 |
| 10 | Anchor assembly, MGS type T (606E26550) | EACH | 1 | $1,500.00 | $1,500.00 | $1,449.00 | $2,136.19 | $1,450.00 | $1,518.00 |
| 11 | Monument assembly, type C (623E38500) | EACH | 1 | $1,650.00 | $2,670.00 | $2,250.75 | $2,732.31 | $2,000.00 | $1,804.25 |
| 12 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $1,000.00 | $845.00 | $840.00 | $1,107.91 | $800.00 | $499.27 |
| 13 | Post construction survey monument verification and report (623E51000) | LS | 1 | $1,000.00 | $845.00 | $840.00 | $1,107.91 | $800.00 | $499.27 |
| 14 | Riprap, type D (601E11000) | SY | 8 | $125.00 | $344.00 | $833.06 | $408.73 | $500.00 | $444.87 |
| 15 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 427 | $70.00 | $103.00 | $75.96 | $58.95 | $61.00 | $72.39 |
| 16 | Rock channel protection, type A with filter (601E32000) | CY | 44 | $140.00 | $190.00 | $157.95 | $140.37 | $172.00 | $216.79 |
| 17 | Rock channel protection, type C with filter (601E32200) | CY | 2 | $500.00 | $250.00 | $778.50 | $338.46 | $211.00 | $265.82 |
| 18 | Soil analysis test (659E00100) | EACH | 2 | $200.00 | $25.00 | $76.20 | $100.00 | $225.00 | $141.75 |
| 19 | Topsoil (659E00300) | CY | 101 | $35.00 | $42.60 | $71.70 | $40.53 | $30.00 | $68.03 |
| 20 | Seeding and mulching (659E10000) | SY | 912 | $3.50 | $4.30 | $4.15 | $3.68 | $6.00 | $4.35 |
| 21 | Repair seeding and mulching (659E14000) | SY | 46 | $1.00 | $0.90 | $0.95 | $1.00 | $10.00 | $0.99 |
| 22 | Inter-seeding (659E15000) | SY | 46 | $1.00 | $0.10 | $0.11 | $1.00 | $10.00 | $0.11 |
| 23 | Commercial fertilizer (659E20000) | TON | 0.12 | $1,000.00 | $625.00 | $656.25 | $1,219.92 | $500.00 | $687.50 |
| 24 | Lime (659E31000) | ACRE | 0.19 | $100.00 | $50.00 | $52.53 | $308.21 | $400.00 | $55.00 |
| 25 | Water (659E35000) | MGAL | 5.04 | $1.00 | $1.25 | $1.31 | $1.00 | $50.00 | $1.38 |
| 26 | Slope erosion protection mat, type B (670E00520) | SY | 46 | $15.00 | $4.80 | $5.04 | $3.76 | $6.00 | $5.28 |
| 27 | Erosion control (832E30000) | EACH | 2,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 28 | Aggregate drains (605E31100) | FT | 48 | $15.00 | $20.00 | $8.43 | $7.46 | $20.00 | $10.49 |
| 29 | 24" conduit, type B (611E10400) | FT | 75 | $160.00 | $164.00 | $249.41 | $344.72 | $455.00 | $218.94 |
| 30 | 24" conduit, type C (611E10600) | FT | 20 | $85.00 | $90.00 | $186.36 | $117.99 | $450.00 | $167.87 |
| 31 | Manhole, no. 3 (611E99574) | EACH | 1 | $4,250.00 | $5,150.00 | $11,040 | $6,881.15 | $8,000.00 | $4,571.97 |
| 32 | Pavement planing, asphalt concrete (varies 0" to 3 (254E01000) | SY | 146 | $30.00 | $33.00 | $21.00 | $45.11 | $58.00 | $45.31 |
| 33 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 76 | $300.00 | $298.00 | $367.50 | $302.40 | $283.00 | $275.00 |
| 34 | Aggregate base (304E20000) | CY | 86 | $70.00 | $100.00 | $137.55 | $92.54 | $80.00 | $80.69 |
| 35 | Tack coat (407E10000) | GAL | 50 | $4.00 | $2.41 | $1.81 | $17.25 | $2.25 | $2.48 |
| 36 | Asphalt concrete surface course, 9.5 MM, type A (4 (442E22001) | CY | 39 | $375.00 | $437.00 | $525.00 | $434.50 | $412.00 | $390.50 |
| 37 | RPM (621E00100) | EACH | 3 | $1,000.00 | $834.00 | $924.00 | $585.58 | $800.00 | $858.00 |
| 38 | Raised pavement marker removed (621E54000) | EACH | 3 | $100.00 | $60.00 | $20.64 | $30.45 | $100.00 | $55.00 |
| 39 | Barrier reflector, type 2, bidirectional (626E00110) | EACH | 6 | $15.00 | $16.00 | $15.75 | $15.22 | $16.00 | $16.50 |
| 40 | Edge line, 6", type 1 (642E00104) | MI | 0.09 | $7,000.00 | $24,000 | $5,366.67 | $9,057.00 | $6,300.00 | $5,500.00 |
| 41 | Center line, type 1 (642E00300) | MI | 0.04 | $13,000 | $67,000 | $5,250.00 | $18,622 | $12,600 | $5,500.00 |
| 42 | Detour signing (614E12420) | LS | 1 | $4,500.00 | $3,900.00 | $4,794.30 | $4,281.76 | $4,000.00 | $14,351 |
| 43 | Portable changeable message sign, as per plan (614E18601) | SNMT | 2 | $1,200.00 | $1,872.00 | $924.00 | $1,262.51 | $1,050.00 | $1,417.50 |
| 44 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $6,500.00 | $1,725.00 | $1,452.00 | $10,019 | $3,500.00 | $5,748.08 |
| 45 | Concrete masonry (602E20000) | CY | 1 | $2,850.00 | $2,620.00 | $3,570.00 | $2,405.56 | $4,500.00 | $4,453.24 |
| 46 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $2,000.00 | $3,470.00 | $3,098.62 | $5,685.98 | $2,700.00 | $3,836.42 |
| 47 | Maintaining traffic (614E11000) | LS | 1 | $6,500.00 | $3,800.00 | $4,540.80 | $9,780.36 | $7,000.00 | $2,215.83 |
| 48 | Construction layout stakes and surveying (623E10000) | LS | 1 | $4,500.00 | $4,000.00 | $2,760.00 | $5,122.66 | $6,000.00 | $4,636.49 |
| 49 | Mobilization (624E10000) | LS | 1 | $24,500 | $12,000 | $8,123.85 | $14,766 | $14,000 | $29,542 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 23, 2025. Compiled by Mirage Metrics.