ODOT contract 250487 bid tabulation

BRO-US 62-27.42 (CULVERT REPLACEMENT). Let by Ohio DOT on October 23, 2025, BRO. 5 bids received; low bid $1,244,448 by John R Jurgensen Company, +25% against the engineer's estimate of $994,000.

Owner
Ohio DOT
Letting
23 OCT 2025
Pay items
48
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1John R Jurgensen Company$1,244,448Low+25%
2Fillmore Construction$984,259-21%-1.0%
3Alan Stone Co Inc$1,310,404+5.0%+32%
4Axis Civil Construction LLC$1,356,796+9.0%+36%
5Sunesis Construction Co$1,446,728+16%+46%
ODOT contract 250487: bids by rank

Engineer's estimate: $994,000.

Bid tabulation

LinePay itemUnitQuantity1. John R Jurgensen Company2. Fillmore Construction3. Alan Stone Co Inc4. Axis Civil Construction LLC5. Sunesis Construction Co
1Clearing and grubbing (201E11000)LS1$16,816$10,000$16,000$40,000$20,171
2Pavement removed (202E23000)SY1,804$9.56$5.00$3.50$10.00$4.16
3Guardrail removed (202E38000)FT599$6.00$2.00$5.50$6.00$4.52
4Special - fill and plug existing conduit (202E70000)FT48$761.98$100.00$230.00$400.00$340.90
5Excavation (203E10000)CY531$20.13$20.00$10.00$28.50$16.38
6Embankment (203E20000)CY9,700$25.90$30.00$40.00$32.50$51.14
7Subgrade compaction (204E10000)SY2,888$1.50$3.50$4.50$2.00$2.70
8Proof rolling (204E45000)HR2$228.16$200.00$280.00$1,500.00$297.33
9Reference monument, type A (623E40500)EACH4$828.60$1,500.00$1,100.00$850.00$878.63
10Rock channel protection, type A with geotextile fabric (601E32004)CY51$243.41$160.00$140.00$128.00$181.36
11Topsoil (659E00300)CY776$40.02$20.00$30.00$38.00$13.61
12Seeding and mulching (659E10000)SY5,646$1.72$1.45$1.00$0.90$2.33
13Commercial fertilizer (659E20000)TON0.76$750.00$1,400.00$640.00$1,250.00$750.00
14Lime (659E31000)ACRE1.17$75.00$450.00$920.00$150.00$75.00
15Water (659E35000)MGAL30$3.00$1.00$110.00$1.00$3.00
16Slope erosion protection (670E00500)SY1,343$2.25$2.00$2.00$2.50$2.25
17Storm water pollution prevention plan (832E15000)LS1$2,855.00$3,500.00$3,300.00$2,500.00$2,855.00
18Storm water pollution prevention inspections (832E15002)LS1$2,910.00$2,500.00$6,100.00$9,550.00$2,140.08
19Storm water pollution prevention inspection software (832E15010)LS1$10,469$7,500.00$13,000$12,500$10,436
20Erosion control (832E30000)EACH33,250$1.00$1.00$1.00$1.00$1.00
21Cofferdams and excavation bracing (503E11100)LS1$8,497.29$7,500.00$500.00$16,000$68,222
22Unclassified excavation (503E21100)CY15$104.32$100.00$100.00$300.00$29.12
23Concrete masonry (602E20000)CY8.10$3,876.06$1,500.00$2,600.00$2,400.00$1,502.84
24Aggregate drains (605E31100)FT345$39.08$10.00$30.00$21.00$10.70
256" conduit, type E (611E01400)FT50$49.39$50.00$9.00$25.00$14.48
266" conduit, type F (611E01500)FT50$49.39$50.00$15.00$25.00$14.48
2784" conduit, type A (for pipe allowable materials, (611E28000)FT159$900.64$1,000.00$400.00$980.00$634.72
28Asphalt concrete base, PG64-22, (449) (301E56000)CY691$225.00$180.00$240.00$215.00$213.33
29Aggregate base (304E20000)CY478$71.65$80.00$70.00$90.00$76.90
30Tack coat (407E10000)GAL536$5.00$5.00$5.00$6.00$5.12
31Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100)CY119$350.00$220.00$330.00$320.00$262.13
32Asphalt concrete intermediate course, type 2, (449) (441E70300)CY131$300.00$200.00$290.00$265.00$218.41
33Compacted aggregate (617E10100)CY25$263.55$200.00$100.00$80.00$177.36
34RPM (621E00100)EACH9$323.00$372.00$370.00$270.00$323.00
35Raised pavement marker removed (621E54000)EACH9$26.19$20.00$35.00$32.00$5.00
36Edge line, 6" (644E00104)MI0.24$14,167$16,292$16,000$9,700.00$14,167
37Center line (644E00300)MI0.12$20,950$24,092$24,000$9,700.00$20,950
38Pavement repair (253E02000)CY100$350.00$100.00$270.00$210.00$541.49
39Detour signing (614E12420)LS1$6,550.00$6,550.00$7,500.00$6,550.00$7,841.76
40Asphalt concrete for maintaining traffic (614E13000)CY100$150.00$300.00$280.00$220.00$319.12
41Water (616E10000)MGAL31$100.00$1.00$110.00$1.00$15.77
42Premium for contract performance bond and for payment bond (103E05000)LS1$5,791.29$7,500.00$10,000$15,000$8,371.49
43Maintaining traffic (614E11000)LS1$19,236$10,000$20,000$15,000$7,791.76
44Construction layout stakes and surveying (623E10000)LS1$5,060.74$7,500.00$25,000$15,000$10,190
45Preconstruction survey monument verification and report (623E50000)LS1$2,220.89$5,000.00$2,000.00$800.00$800.00
46Post construction survey monument verification and report (623E51000)LS1$2,220.89$5,000.00$2,000.00$800.00$800.00
47Mobilization (624E10000)LS1$50,000$10,000$68,000$50,000$48,646
48Special - calendar days of contract time for opening to traffic (unit price field should reflect number of days bid) (614E15000)DLR4,500$35.00$10.00$40.00$45.00$40.00
ODOT contract 250487: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of October 23, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy