ODOT contract 250487 bid tabulation
BRO-US 62-27.42 (CULVERT REPLACEMENT). Let by Ohio DOT on October 23, 2025, BRO. 5 bids received; low bid $1,244,448 by John R Jurgensen Company, +25% against the engineer's estimate of $994,000.
- Owner
- Ohio DOT
- Letting
- 23 OCT 2025
- Pay items
- 48
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | John R Jurgensen Company | $1,244,448 | Low | +25% |
| 2 | Fillmore Construction | $984,259 | -21% | -1.0% |
| 3 | Alan Stone Co Inc | $1,310,404 | +5.0% | +32% |
| 4 | Axis Civil Construction LLC | $1,356,796 | +9.0% | +36% |
| 5 | Sunesis Construction Co | $1,446,728 | +16% | +46% |
Engineer's estimate: $994,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. John R Jurgensen Company | 2. Fillmore Construction | 3. Alan Stone Co Inc | 4. Axis Civil Construction LLC | 5. Sunesis Construction Co |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $16,816 | $10,000 | $16,000 | $40,000 | $20,171 |
| 2 | Pavement removed (202E23000) | SY | 1,804 | $9.56 | $5.00 | $3.50 | $10.00 | $4.16 |
| 3 | Guardrail removed (202E38000) | FT | 599 | $6.00 | $2.00 | $5.50 | $6.00 | $4.52 |
| 4 | Special - fill and plug existing conduit (202E70000) | FT | 48 | $761.98 | $100.00 | $230.00 | $400.00 | $340.90 |
| 5 | Excavation (203E10000) | CY | 531 | $20.13 | $20.00 | $10.00 | $28.50 | $16.38 |
| 6 | Embankment (203E20000) | CY | 9,700 | $25.90 | $30.00 | $40.00 | $32.50 | $51.14 |
| 7 | Subgrade compaction (204E10000) | SY | 2,888 | $1.50 | $3.50 | $4.50 | $2.00 | $2.70 |
| 8 | Proof rolling (204E45000) | HR | 2 | $228.16 | $200.00 | $280.00 | $1,500.00 | $297.33 |
| 9 | Reference monument, type A (623E40500) | EACH | 4 | $828.60 | $1,500.00 | $1,100.00 | $850.00 | $878.63 |
| 10 | Rock channel protection, type A with geotextile fabric (601E32004) | CY | 51 | $243.41 | $160.00 | $140.00 | $128.00 | $181.36 |
| 11 | Topsoil (659E00300) | CY | 776 | $40.02 | $20.00 | $30.00 | $38.00 | $13.61 |
| 12 | Seeding and mulching (659E10000) | SY | 5,646 | $1.72 | $1.45 | $1.00 | $0.90 | $2.33 |
| 13 | Commercial fertilizer (659E20000) | TON | 0.76 | $750.00 | $1,400.00 | $640.00 | $1,250.00 | $750.00 |
| 14 | Lime (659E31000) | ACRE | 1.17 | $75.00 | $450.00 | $920.00 | $150.00 | $75.00 |
| 15 | Water (659E35000) | MGAL | 30 | $3.00 | $1.00 | $110.00 | $1.00 | $3.00 |
| 16 | Slope erosion protection (670E00500) | SY | 1,343 | $2.25 | $2.00 | $2.00 | $2.50 | $2.25 |
| 17 | Storm water pollution prevention plan (832E15000) | LS | 1 | $2,855.00 | $3,500.00 | $3,300.00 | $2,500.00 | $2,855.00 |
| 18 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $2,910.00 | $2,500.00 | $6,100.00 | $9,550.00 | $2,140.08 |
| 19 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $10,469 | $7,500.00 | $13,000 | $12,500 | $10,436 |
| 20 | Erosion control (832E30000) | EACH | 33,250 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 21 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $8,497.29 | $7,500.00 | $500.00 | $16,000 | $68,222 |
| 22 | Unclassified excavation (503E21100) | CY | 15 | $104.32 | $100.00 | $100.00 | $300.00 | $29.12 |
| 23 | Concrete masonry (602E20000) | CY | 8.10 | $3,876.06 | $1,500.00 | $2,600.00 | $2,400.00 | $1,502.84 |
| 24 | Aggregate drains (605E31100) | FT | 345 | $39.08 | $10.00 | $30.00 | $21.00 | $10.70 |
| 25 | 6" conduit, type E (611E01400) | FT | 50 | $49.39 | $50.00 | $9.00 | $25.00 | $14.48 |
| 26 | 6" conduit, type F (611E01500) | FT | 50 | $49.39 | $50.00 | $15.00 | $25.00 | $14.48 |
| 27 | 84" conduit, type A (for pipe allowable materials, (611E28000) | FT | 159 | $900.64 | $1,000.00 | $400.00 | $980.00 | $634.72 |
| 28 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 691 | $225.00 | $180.00 | $240.00 | $215.00 | $213.33 |
| 29 | Aggregate base (304E20000) | CY | 478 | $71.65 | $80.00 | $70.00 | $90.00 | $76.90 |
| 30 | Tack coat (407E10000) | GAL | 536 | $5.00 | $5.00 | $5.00 | $6.00 | $5.12 |
| 31 | Asphalt concrete surface course, type 1, (449), PG70-22M (441E70100) | CY | 119 | $350.00 | $220.00 | $330.00 | $320.00 | $262.13 |
| 32 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 131 | $300.00 | $200.00 | $290.00 | $265.00 | $218.41 |
| 33 | Compacted aggregate (617E10100) | CY | 25 | $263.55 | $200.00 | $100.00 | $80.00 | $177.36 |
| 34 | RPM (621E00100) | EACH | 9 | $323.00 | $372.00 | $370.00 | $270.00 | $323.00 |
| 35 | Raised pavement marker removed (621E54000) | EACH | 9 | $26.19 | $20.00 | $35.00 | $32.00 | $5.00 |
| 36 | Edge line, 6" (644E00104) | MI | 0.24 | $14,167 | $16,292 | $16,000 | $9,700.00 | $14,167 |
| 37 | Center line (644E00300) | MI | 0.12 | $20,950 | $24,092 | $24,000 | $9,700.00 | $20,950 |
| 38 | Pavement repair (253E02000) | CY | 100 | $350.00 | $100.00 | $270.00 | $210.00 | $541.49 |
| 39 | Detour signing (614E12420) | LS | 1 | $6,550.00 | $6,550.00 | $7,500.00 | $6,550.00 | $7,841.76 |
| 40 | Asphalt concrete for maintaining traffic (614E13000) | CY | 100 | $150.00 | $300.00 | $280.00 | $220.00 | $319.12 |
| 41 | Water (616E10000) | MGAL | 31 | $100.00 | $1.00 | $110.00 | $1.00 | $15.77 |
| 42 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $5,791.29 | $7,500.00 | $10,000 | $15,000 | $8,371.49 |
| 43 | Maintaining traffic (614E11000) | LS | 1 | $19,236 | $10,000 | $20,000 | $15,000 | $7,791.76 |
| 44 | Construction layout stakes and surveying (623E10000) | LS | 1 | $5,060.74 | $7,500.00 | $25,000 | $15,000 | $10,190 |
| 45 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $2,220.89 | $5,000.00 | $2,000.00 | $800.00 | $800.00 |
| 46 | Post construction survey monument verification and report (623E51000) | LS | 1 | $2,220.89 | $5,000.00 | $2,000.00 | $800.00 | $800.00 |
| 47 | Mobilization (624E10000) | LS | 1 | $50,000 | $10,000 | $68,000 | $50,000 | $48,646 |
| 48 | Special - calendar days of contract time for opening to traffic (unit price field should reflect number of days bid) (614E15000) | DLR | 4,500 | $35.00 | $10.00 | $40.00 | $45.00 | $40.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 23, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.