ODOT contract 250500 bid tabulation
LAK-US 6-02.06 Super (BRIDGE REPAIR). Let by Ohio DOT on October 23, 2025, LAK. 3 bids received; low bid $7,000,047 by J D Williamson Construction Co Inc, +7.7% against the engineer's estimate of $6,500,000.
- Owner
- Ohio DOT
- Letting
- 23 OCT 2025
- Pay items
- 140
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | J D Williamson Construction Co Inc | $7,000,047 | Low | +8.0% |
| 2 | Ruhlin Company | $7,440,546 | +6.0% | +14% |
| 3 | Great Lakes Construction Co | $7,478,757 | +7.0% | +15% |
Engineer's estimate: $6,500,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. J D Williamson Construction Co Inc | 2. Ruhlin Company | 3. Great Lakes Construction Co |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $32,000 | $70,000 | $50,000 |
| 2 | Pavement removed (202E23000) | SY | 286 | $28.00 | $60.00 | $27.00 |
| 3 | Concrete barrier removed, as per plan (202E30701) | FT | 480 | $34.00 | $42.50 | $22.00 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 127 | $28.00 | $30.00 | $22.50 |
| 5 | Guardrail removed (202E38000) | FT | 2,048 | $2.00 | $2.00 | $2.00 |
| 6 | Guardrail removed, barrier design (202E38300) | FT | 78 | $3.00 | $3.50 | $3.50 |
| 7 | Anchor assembly removed, type A (202E42000) | EACH | 5 | $300.00 | $295.00 | $295.00 |
| 8 | Anchor assembly removed, type E (202E42010) | EACH | 2 | $150.00 | $145.00 | $145.00 |
| 9 | Anchor assembly removed, type T (202E42040) | EACH | 7 | $82.00 | $80.00 | $80.00 |
| 10 | Anchor assembly removed, barrier design (202E42210) | EACH | 2 | $150.00 | $150.00 | $150.00 |
| 11 | Bridge terminal assembly removed (202E47000) | EACH | 6 | $78.00 | $75.00 | $75.00 |
| 12 | Fence removed (202E75000) | FT | 95 | $4.00 | $3.80 | $3.80 |
| 13 | Excavation (203E10000) | CY | 721 | $29.00 | $42.00 | $55.00 |
| 14 | Embankment (203E20000) | CY | 188 | $22.00 | $80.00 | $20.00 |
| 15 | Subgrade compaction (204E10000) | SY | 1,782 | $4.50 | $3.75 | $3.50 |
| 16 | Excavation of subgrade (204E13000) | CY | 10 | $35.00 | $100.00 | $240.00 |
| 17 | Guardrail, type MGS (606E15050) | FT | 806 | $21.00 | $21.00 | $21.00 |
| 18 | Guardrail, type MGS half post spacing (606E15150) | FT | 62.50 | $29.00 | $28.40 | $28.40 |
| 19 | Guardrail, barrier design, type MGS (606E15550) | FT | 25 | $41.00 | $39.60 | $39.60 |
| 20 | Anchor assembly, MGS type B (606E26050) | EACH | 1 | $2,600.00 | $2,550.00 | $2,550.00 |
| 21 | Anchor assembly, MGS type E (606E26150) | EACH | 2 | $2,500.00 | $2,420.00 | $2,420.00 |
| 22 | Anchor assembly, MGS type T (606E26550) | EACH | 4 | $1,425.00 | $1,360.00 | $1,360.00 |
| 23 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 7 | $2,900.00 | $2,480.00 | $2,480.00 |
| 24 | Impact attenuator, type 1 (unidirectional) (606E60002) | EACH | 2 | $9,000.00 | $8,950.00 | $8,950.00 |
| 25 | Impact attenuator, type 2 (bidirectional), as per plan (606E60029) | EACH | 1 | $35,500 | $35,150 | $35,150 |
| 26 | Fence, type 47 (607E15000) | FT | 101 | $24.00 | $24.00 | $24.00 |
| 27 | Concrete barrier, single slope, type D (622E10160) | FT | 101 | $150.00 | $160.00 | $300.00 |
| 28 | Concrete barrier, type D, as per plan (622E24001) | FT | 349 | $280.00 | $260.00 | $185.00 |
| 29 | Concrete barrier end section, type D (622E25000) | EACH | 4 | $6,000.00 | $6,200.00 | $6,200.00 |
| 30 | Concrete barrier, end anchorage, reinforced, type D (622E25050) | EACH | 4 | $5,000.00 | $6,000.00 | $5,200.00 |
| 31 | Monument assembly adjusted to grade (623E39500) | EACH | 2 | $1,000.00 | $170.00 | $150.00 |
| 32 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $3,000.00 | $1,800.00 | $2,600.00 |
| 33 | Post construction survey monument verification and report (623E51000) | LS | 1 | $3,000.00 | $1,800.00 | $2,600.00 |
| 34 | Special - mailbox support (690E50000) | EACH | 1 | $150.00 | $160.00 | $160.00 |
| 35 | Special - mailbox support system, double (690E50200) | EACH | 1 | $300.00 | $295.00 | $295.00 |
| 36 | Special - mailbox removed and reset (690E50350) | EACH | 3 | $225.00 | $220.00 | $220.00 |
| 37 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 4 | $200.00 | $250.00 | $110.00 |
| 38 | Tied concrete block mat with type 2 underlayment (601E21060) | SY | 80 | $100.00 | $185.00 | $100.00 |
| 39 | Soil analysis test (659E00100) | EACH | 1 | $125.00 | $350.00 | $350.00 |
| 40 | Topsoil (659E00300) | CY | 301 | $50.00 | $58.00 | $58.00 |
| 41 | Seeding and mulching (659E10000) | SY | 2,709 | $2.60 | $1.25 | $1.25 |
| 42 | Repair seeding and mulching (659E14000) | SY | 136 | $0.95 | $2.00 | $2.00 |
| 43 | Inter-seeding (659E15000) | SY | 136 | $0.10 | $0.10 | $1.00 |
| 44 | Commercial fertilizer (659E20000) | TON | 0.38 | $660.00 | $1,500.00 | $1,500.00 |
| 45 | Lime (659E31000) | ACRE | 0.56 | $50.00 | $50.00 | $100.00 |
| 46 | Water (659E35000) | MGAL | 15 | $1.00 | $5.00 | $25.00 |
| 47 | Mowing (659E40000) | MSF | 0.02 | $50.00 | $10.00 | $1,000.00 |
| 48 | Ditch erosion protection (670E00700) | SY | 150 | $2.90 | $4.00 | $4.00 |
| 49 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 | $1.00 |
| 50 | 4" base pipe underdrains (605E06000) | FT | 623 | $22.00 | $20.00 | $20.50 |
| 51 | Aggregate drains (605E31100) | FT | 92 | $16.00 | $33.00 | $10.00 |
| 52 | 4" conduit, type F for underdrain outlet (611E00410) | FT | 44 | $30.00 | $10.00 | $42.00 |
| 53 | 12" conduit, type D (611E04900) | FT | 132 | $80.00 | $110.00 | $105.00 |
| 54 | Precast reinforced concrete outlet (611E99710) | EACH | 2 | $425.00 | $1,000.00 | $250.00 |
| 55 | Pavement planing, asphalt concrete, 1.5" (254E01000) | SY | 149 | $54.00 | $25.00 | $25.00 |
| 56 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 471 | $270.00 | $315.00 | $315.00 |
| 57 | Aggregate base (304E20000) | CY | 373 | $120.00 | $120.00 | $120.00 |
| 58 | Non-tracking tack coat (407E20000) | GAL | 318 | $3.00 | $4.00 | $4.00 |
| 59 | Asphalt concrete surface course, type 1, (449), as per plan (441E70101) | CY | 155 | $340.00 | $365.00 | $365.00 |
| 60 | Asphalt concrete surface course, 12.5 MM, type A (449), as per plan (442E22101) | CY | 10 | $950.00 | $800.00 | $800.00 |
| 61 | Asphalt concrete intermediate course, 12.5 MM, type A (449) (442E22300) | CY | 15 | $660.00 | $585.00 | $585.00 |
| 62 | Curb, type 4-C (609E24510) | FT | 126 | $30.00 | $55.00 | $65.00 |
| 63 | Valve box adjusted to grade (638E10800) | EACH | 3 | $750.00 | $1,900.00 | $200.00 |
| 64 | Light tower, misc.: remove and reset (625E13500) | EACH | 1 | $17,000 | $9,500.00 | $16,189 |
| 65 | RPM (621E00100) | EACH | 13 | $350.00 | $279.71 | $345.00 |
| 66 | Barrier reflector, type 1, BI-directional (626E00102) | EACH | 20 | $13.00 | $12.50 | $12.50 |
| 67 | Barrier reflector, type 1, one-way (626E00102) | EACH | 12 | $13.00 | $13.25 | $13.25 |
| 68 | Barrier reflector, type 2, BI-directional (626E00110) | EACH | 9 | $14.00 | $14.00 | $14.00 |
| 69 | Barrier reflector, type 2, one-way (626E00110) | EACH | 20 | $14.00 | $13.50 | $13.50 |
| 70 | Ground mounted support, no. 3 post (630E03100) | FT | 86 | $20.00 | $20.00 | $13.00 |
| 71 | Ground mounted support, no. 4 post (630E04100) | FT | 14 | $23.00 | $2.50 | $21.00 |
| 72 | Sign, flat sheet (630E80100) | SF | 5 | $30.00 | $30.00 | $26.00 |
| 73 | Removal of ground mounted sign and reerection (630E85100) | EACH | 6 | $66.00 | $65.00 | $98.00 |
| 74 | Removal of ground mounted post support and disposal (630E86002) | EACH | 5 | $20.00 | $20.00 | $118.00 |
| 75 | Removal of overhead mounted sign and reerection (630E87100) | EACH | 1 | $1,200.00 | $1,150.00 | $5,400.00 |
| 76 | Removal of overhead sign support and reerection, type TC-15.115 (630E89500) | EACH | 1 | $17,000 | $16,150 | $8,600.00 |
| 77 | School speed limit sign assembly, misc.: remove an (631E93250) | EACH | 1 | $5,500.00 | $2,444.97 | $5,500.00 |
| 78 | Edge line, 4" (646E10000) | MI | 0.40 | $6,000.00 | $5,834.50 | $7,000.00 |
| 79 | Center line (646E10200) | MI | 0.20 | $12,000 | $11,668 | $13,000 |
| 80 | School symbol marking, 72" (646E20100) | EACH | 1 | $850.00 | $835.51 | $1,200.00 |
| 81 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 750 | $115.00 | $85.00 | $105.00 |
| 82 | Increased barrier delineation (614E11630) | FT | 558 | $3.00 | $2.52 | $1.45 |
| 83 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 10 | $1,850.00 | $1,771.72 | $1,950.00 |
| 84 | Detour signing (614E12420) | LS | 1 | $25,000 | $18,783 | $15,350 |
| 85 | Work zone speed limit sign (614E12470) | EACH | 4 | $250.00 | $248.07 | $195.00 |
| 86 | Barrier reflector, type 1, one-way (614E13310) | EACH | 89 | $11.00 | $10.32 | $10.00 |
| 87 | Object marker, one way (614E13350) | EACH | 89 | $19.00 | $18.56 | $15.85 |
| 88 | Portable changeable message sign, as per plan (614E18601) | SNMT | 14 | $1,200.00 | $1,126.04 | $785.00 |
| 89 | Water (616E10000) | MGAL | 12 | $5.00 | $36.21 | $50.00 |
| 90 | Portable barrier, unanchored (622E41100) | FT | 3,680 | $25.00 | $37.50 | $30.00 |
| 91 | Special - maintain existing lighting (625E40000) | LS | 1 | $17,000 | $10,000 | $16,500 |
| 92 | Surface preparation of existing structural steel (514E00050) | SF | 3,582 | $12.00 | $18.08 | $12.00 |
| 93 | Field painting of existing structural steel, prime coat (514E00056) | SF | 3,582 | $5.00 | $3.52 | $5.00 |
| 94 | Field painting structural steel, intermediate coat (514E00060) | SF | 3,582 | $5.00 | $3.52 | $5.00 |
| 95 | Field painting structural steel, finish coat (514E00066) | SF | 3,582 | $5.00 | $3.52 | $5.00 |
| 96 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 6 | $175.00 | $200.86 | $175.00 |
| 97 | Final inspection repair (514E10000) | EACH | 3 | $500.00 | $351.51 | $500.00 |
| 98 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $712,000 | $705,000 | $892,000 |
| 99 | Approach slab removed (202E22900) | SY | 167 | $70.00 | $55.00 | $50.00 |
| 100 | Unclassified excavation (503E21100) | CY | 329 | $175.00 | $180.00 | $250.00 |
| 101 | Epoxy coated steel reinforcement (509E10000) | LB | 209,334 | $1.60 | $1.85 | $1.90 |
| 102 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 1,000 | $2.50 | $2.81 | $2.00 |
| 103 | Uncoated steel reinforcement (509E25000) | LB | 1,600 | $1.90 | $2.47 | $1.45 |
| 104 | No. 4 deformed GFRP reinforcement (509E30020) | FT | 13,528 | $1.70 | $1.98 | $1.40 |
| 105 | Dowel holes with nonshrink, nonmetallic grout, as per plan (510E10001) | EACH | 216 | $25.00 | $36.00 | $25.00 |
| 106 | Class QC2 concrete with QC/QA, bridge deck (511E34446) | CY | 525 | $1,100.00 | $925.00 | $1,300.00 |
| 107 | Class QC2 concrete with QC/QA, bridge deck (parapet), as per plan (511E34451) | CY | 137 | $1,150.00 | $1,150.00 | $750.00 |
| 108 | Class QC1 concrete with QC/QA, pier above footings (511E40512) | CY | 177 | $1,200.00 | $1,725.00 | $2,000.00 |
| 109 | Class QC1 concrete with QC/QA, abutment not including footing (511E44112) | CY | 83 | $900.00 | $1,025.00 | $1,350.00 |
| 110 | Class QC1 concrete with QC/QA, retaining/wingwall not including footing (511E46012) | CY | 43 | $900.00 | $1,100.00 | $1,600.00 |
| 111 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 1,553 | $34.00 | $42.00 | $40.00 |
| 112 | Type 2 waterproofing (512E33000) | SY | 30 | $29.00 | $95.00 | $25.00 |
| 113 | Structural steel members, level 2 (513E10240) | LB | 550,447 | $2.75 | $3.05 | $2.85 |
| 114 | Welded stud shear connectors (513E20000) | EACH | 9,400 | $4.30 | $4.30 | $4.30 |
| 115 | Field painting structural steel, intermediate coat (514E00060) | SF | 31,801 | $10.00 | $9.04 | $10.00 |
| 116 | Field painting structural steel, finish coat (514E00066) | SF | 31,801 | $5.00 | $9.04 | $5.00 |
| 117 | Structural expansion joint including elastomeric strip seal (516E11210) | FT | 85 | $750.00 | $778.40 | $825.00 |
| 118 | 2" preformed expansion joint filler (516E13900) | SF | 79 | $14.00 | $9.50 | $15.00 |
| 119 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44001) | EACH | 5 | $2,200.00 | $5,100.00 | $2,000.00 |
| 120 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44201) | EACH | 5 | $1,500.00 | $3,500.00 | $1,600.00 |
| 121 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44201) | EACH | 5 | $1,500.00 | $3,500.00 | $1,700.00 |
| 122 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44201) | EACH | 5 | $1,500.00 | $3,500.00 | $1,750.00 |
| 123 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44201) | EACH | 5 | $1,400.00 | $3,500.00 | $1,750.00 |
| 124 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44201) | EACH | 5 | $1,800.00 | $4,800.00 | $2,000.00 |
| 125 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44201) | EACH | 5 | $1,800.00 | $5,100.00 | $2,000.00 |
| 126 | Porous backfill with geotextile fabric (518E21200) | CY | 89 | $120.00 | $135.00 | $150.00 |
| 127 | 6" perforated corrugated plastic pipe (518E40000) | FT | 114 | $22.00 | $25.00 | $20.00 |
| 128 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 102 | $25.00 | $25.00 | $25.00 |
| 129 | Reinforced concrete approach slabs (T=15"), as per plan (526E25001) | SY | 209 | $375.00 | $500.00 | $525.00 |
| 130 | Type A installation (526E90010) | FT | 83 | $200.00 | $320.00 | $290.00 |
| 131 | Crushed aggregate slope protection (601E20000) | SY | 642 | $45.00 | $40.00 | $40.00 |
| 132 | Vandal protection fence, 6' straight, coated fabric, as per plan (607E39901) | FT | 742 | $110.00 | $109.95 | $97.50 |
| 133 | Structure grounding system, as per plan (625E33001) | EACH | 1 | $12,000 | $5,000.00 | $11,750 |
| 134 | Polymer modified asphalt expansion joint system, as per plan (846E00111) | CF | 35 | $735.00 | $630.00 | $735.00 |
| 135 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $70,000 | $65,000 | $75,000 |
| 136 | CPM progress schedule short duration projects (108E30000) | LS | 1 | $8,000.00 | $500.00 | $500.00 |
| 137 | Maintaining traffic (614E11000) | LS | 1 | $684,000 | $552,250 | $500,000 |
| 138 | Field office, type C, as per plan (619E16021) | MNTH | 10 | $5,000.00 | $3,750.00 | $4,750.00 |
| 139 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $50,000 | $70,000 | $44,000 |
| 140 | Mobilization (624E10000) | LS | 1 | $340,000 | $356,150 | $370,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 23, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way