ODOT contract 250506 bid tabulation
WAR-SR 123-09.66 (CHIP SEAL). Let by Ohio DOT on October 23, 2025, WAR. 5 bids received; low bid $499,119 by Shelly Company, -13% against the engineer's estimate of $572,000.
- Owner
- Ohio DOT
- Letting
- 23 OCT 2025
- Pay items
- 20
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly Company | $499,119 | Low | -13% |
| 2 | Henry W Bergman Inc | $582,332 | +17% | +2.0% |
| 3 | SC Construction & Materials LLC | $642,249 | +29% | +12% |
| 4 | Russell Standard Corporation and Subsidiary | $727,891 | +46% | +27% |
| 5 | Runway Incorporated | $761,008 | +52% | +33% |
Engineer's estimate: $572,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly Company | 2. Henry W Bergman Inc | 3. SC Construction & Materials LLC | 4. Russell Standard Corporation and Subsidiary | 5. Runway Incorporated |
|---|---|---|---|---|---|---|---|---|
| 1 | Guardrail removed (202E38000) | FT | 150 | $10.00 | $11.00 | $6.00 | $3.05 | $2.52 |
| 2 | Anchor assembly removed, type A, as per plan (202E42001) | EACH | 2 | $600.00 | $660.00 | $400.00 | $525.00 | $414.75 |
| 3 | Guardrail, type MGS with long posts (606E15100) | FT | 100 | $33.25 | $37.00 | $45.00 | $38.25 | $30.87 |
| 4 | Anchor assembly, MGS type E, soft stop (606E26150) | EACH | 2 | $2,600.00 | $2,900.00 | $2,950.00 | $4,500.00 | $3,491.25 |
| 5 | Pavement repair (253E02000) | CY | 250 | $375.00 | $655.00 | $475.00 | $685.00 | $1,273.83 |
| 6 | Aggregate, single chip seal, type A (422E11000) | SY | 78,369 | $1.10 | $0.40 | $1.25 | $1.10 | $1.19 |
| 7 | Emulsion, chip seal (422E25000) | GAL | 31,348 | $3.07 | $5.00 | $3.25 | $3.40 | $3.08 |
| 8 | Fog seal (886E11000) | GAL | 11,755 | $3.20 | $4.00 | $2.75 | $3.20 | $2.93 |
| 9 | RPM (621E00100) | EACH | 590 | $38.00 | $47.00 | $40.00 | $45.00 | $43.68 |
| 10 | Raised pavement marker removed (621E54000) | EACH | 590 | $16.25 | $19.00 | $25.00 | $14.75 | $18.25 |
| 11 | Barrier reflector, type 2, BI-directional (626E00110) | EACH | 4 | $15.00 | $20.00 | $12.00 | $25.00 | $15.45 |
| 12 | Edge line, 6", type 1, as per plan (642E00105) | MI | 10.24 | $745.00 | $850.00 | $1,050.00 | $750.00 | $767.35 |
| 13 | Center line, type 1, as per plan (642E00301) | MI | 5.12 | $1,050.00 | $1,200.00 | $1,155.00 | $2,550.00 | $1,081.50 |
| 14 | Removal of pavement marking (644E30030) | MI | 15.36 | $1,100.00 | $1,700.00 | $1,640.00 | $3,250.00 | $1,133.00 |
| 15 | Work zone center line, class I, 642 paint (614E21100) | MI | 15.09 | $915.00 | $1,050.00 | $1,205.00 | $3,000.00 | $942.45 |
| 16 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 30.18 | $880.00 | $1,000.00 | $1,070.00 | $1,500.00 | $906.40 |
| 17 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $4,000.00 | $10,000 | $7,500.00 | $7,500.00 | $15,000 |
| 18 | Maintaining traffic (614E11000) | LS | 1 | $42,000 | $10,000 | $75,000 | $55,000 | $57,876 |
| 19 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $5,750.00 | $5,000.00 | $1,000.00 | $1,855.00 | $3,045.00 |
| 20 | Mobilization (624E10000) | LS | 1 | $20,000 | $20,000 | $65,000 | $51,000 | $22,125 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 23, 2025. Compiled by Mirage Metrics.