ODOT contract 250497 bid tabulation
GEA-SR 88/US 422-02.05/15.52 (FOUR LANE RESURFACING). Let by Ohio DOT on October 23, 2025, GEA. 5 bids received; low bid $1,595,505 by Ronyak Paving Inc, +4.8% against the engineer's estimate of $1,523,000.
- Owner
- Ohio DOT
- Letting
- 23 OCT 2025
- Pay items
- 56
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Ronyak Paving Inc | $1,595,505 | Low | +5.0% |
| 2 | Karvo Companies Inc | $1,684,336 | +6.0% | +11% |
| 3 | Kokosing Construction Company Inc | $1,743,243 | +9.0% | +14% |
| 4 | Shelly & Sands Inc | $2,007,788 | +26% | +32% |
| 5 | Shelly Company | $2,086,661 | +31% | +37% |
Engineer's estimate: $1,523,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ronyak Paving Inc | 2. Karvo Companies Inc | 3. Kokosing Construction Company Inc | 4. Shelly & Sands Inc | 5. Shelly Company |
|---|---|---|---|---|---|---|---|---|
| 1 | Walk removed (202E30000) | SF | 80 | $6.00 | $10.00 | $1.50 | $10.00 | $10.00 |
| 2 | Curb removed (202E32000) | FT | 30 | $22.00 | $35.00 | $11.00 | $20.00 | $20.00 |
| 3 | Linear grading, as per plan (209E60201) | STA | 295 | $10.00 | $40.00 | $70.00 | $100.00 | $70.00 |
| 4 | 4" concrete walk (608E10000) | SF | 60 | $40.00 | $25.00 | $19.50 | $30.00 | $30.00 |
| 5 | Monument assembly adjusted to grade, as per plan (623E39501) | EACH | 14 | $1,275.00 | $1,000.00 | $775.00 | $1,500.00 | $1,500.00 |
| 6 | Monument assembly reconstructed to grade, as per plan (623E39601) | EACH | 2 | $1,725.00 | $2,500.00 | $825.00 | $1,850.00 | $1,850.00 |
| 7 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 8 | Catch basin adjusted to grade, as per plan (611E98631) | EACH | 37 | $1,400.00 | $1,350.00 | $1,100.00 | $3,000.00 | $3,000.00 |
| 9 | Catch basin reconstructed to grade (611E98634) | EACH | 6 | $2,500.00 | $2,000.00 | $1,425.00 | $3,500.00 | $3,500.00 |
| 10 | Inlet adjusted to grade, as per plan (611E99151) | EACH | 49 | $1,300.00 | $1,000.00 | $1,100.00 | $4,000.00 | $4,000.00 |
| 11 | Inlet reconstructed to grade (611E99154) | EACH | 7 | $2,000.00 | $1,500.00 | $1,425.00 | $8,000.00 | $8,000.00 |
| 12 | Manhole adjusted to grade, as per plan (611E99655) | EACH | 4 | $1,575.00 | $1,250.00 | $1,100.00 | $1,700.00 | $1,700.00 |
| 13 | Special - miscellaneous metal (611E99820) | LB | 6,000 | $4.00 | $1.50 | $2.50 | $6.00 | $6.00 |
| 14 | Partial depth pavement repair (441) (251E01000) | SY | 915 | $95.00 | $75.00 | $104.00 | $70.00 | $65.00 |
| 15 | Pavement repair, as per plan (253E02001) | CY | 15 | $625.00 | $350.00 | $1,400.00 | $1,450.00 | $800.00 |
| 16 | Non-tracking tack coat (407E20000) | GAL | 10,622 | $2.00 | $2.25 | $2.75 | $3.05 | $3.00 |
| 17 | Fine graded polymer asphalt concrete, type B, (448) (424E14000) | CY | 2,987 | $235.00 | $262.00 | $282.00 | $254.00 | $250.00 |
| 18 | Asphalt concrete surface course, type 1, (449), as per plan (441E70101) | CY | 34 | $700.00 | $575.00 | $650.00 | $800.00 | $825.00 |
| 19 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 23 | $350.00 | $735.00 | $650.00 | $900.00 | $700.00 |
| 20 | Curb, type 6 (609E26000) | FT | 30 | $95.00 | $35.00 | $59.00 | $25.00 | $25.00 |
| 21 | Compacted aggregate, as per plan (617E10101) | CY | 101 | $165.00 | $125.00 | $80.00 | $270.00 | $110.00 |
| 22 | Longitudinal joint adhesive (875E10000) | LB | 5,836 | $2.00 | $1.00 | $0.69 | $0.80 | $3.50 |
| 23 | Pavement planing, asphalt concrete, class A, (1.0" (897E01010) | SY | 109,515 | $1.50 | $1.35 | $1.45 | $1.50 | $1.25 |
| 24 | RPM (621E00100) | EACH | 584 | $38.33 | $40.00 | $38.33 | $37.00 | $38.50 |
| 25 | Raised pavement marker removed (621E54000) | EACH | 584 | $1.00 | $0.50 | $2.00 | $5.00 | $7.00 |
| 26 | Edge line, 6" (646E10010) | MI | 10.50 | $3,070.00 | $3,070.00 | $3,070.00 | $2,600.00 | $3,070.00 |
| 27 | Lane line, 6" (646E10110) | MI | 5.31 | $1,630.00 | $1,630.00 | $1,630.00 | $2,155.00 | $1,630.00 |
| 28 | Center line (646E10200) | MI | 2.55 | $3,999.00 | $3,999.00 | $3,999.00 | $3,750.00 | $3,999.00 |
| 29 | Channelizing line, 8" (646E10300) | FT | 105 | $1.69 | $1.69 | $1.69 | $3.75 | $1.70 |
| 30 | Stop line (646E10400) | FT | 158 | $13.00 | $13.00 | $13.00 | $12.00 | $13.00 |
| 31 | Crosswalk line, 12" (646E10510) | FT | 765 | $6.00 | $6.00 | $6.00 | $10.00 | $6.00 |
| 32 | Lane arrow (646E20300) | EACH | 7 | $166.00 | $166.00 | $166.00 | $150.00 | $166.00 |
| 33 | Special - inventory existing pavement markings (690E98400) | LS | 1 | $1,000.00 | $1,000.00 | $1,000.00 | $600.00 | $1,000.00 |
| 34 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 160 | $125.00 | $100.00 | $115.00 | $100.00 | $100.00 |
| 35 | Asphalt concrete for maintaining traffic (614E13000) | CY | 10 | $250.00 | $50.00 | $150.00 | $500.00 | $115.00 |
| 36 | Portable changeable message sign, as per plan (614E18601) | SNMT | 8 | $900.00 | $1,082.61 | $900.00 | $1,232.00 | $900.00 |
| 37 | Work zone lane line, class I, 6", 642 paint (614E20110) | MI | 5.31 | $655.00 | $655.00 | $655.00 | $530.00 | $655.00 |
| 38 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 5.31 | $645.00 | $645.00 | $645.00 | $530.00 | $645.00 |
| 39 | Work zone center line, class I, 642 paint (614E21100) | MI | 2.55 | $1,175.00 | $1,175.00 | $1,175.00 | $900.00 | $1,175.00 |
| 40 | Work zone center line, class III, 642 paint (614E21550) | MI | 2.55 | $1,095.00 | $1,095.00 | $1,095.00 | $900.00 | $1,095.00 |
| 41 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 10.50 | $675.00 | $675.00 | $675.00 | $650.00 | $675.00 |
| 42 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 10.50 | $655.00 | $655.00 | $655.00 | $650.00 | $655.00 |
| 43 | Work zone channelizing line, class I, 8", 642 paint (614E23200) | FT | 105 | $0.65 | $0.65 | $0.65 | $0.60 | $0.65 |
| 44 | Work zone channelizing line, class III, 8", 642 paint (614E23680) | FT | 105 | $0.60 | $0.60 | $0.60 | $0.60 | $0.60 |
| 45 | Work zone stop line, class I, 642 paint (614E26200) | FT | 158 | $3.15 | $3.15 | $3.15 | $3.00 | $3.15 |
| 46 | Work zone stop line, class III, 642 paint (614E26610) | FT | 158 | $3.00 | $3.00 | $3.00 | $3.00 | $3.00 |
| 47 | Work zone crosswalk line, class I, 12", 642 paint (614E27050) | FT | 765 | $1.25 | $1.25 | $1.25 | $3.60 | $1.25 |
| 48 | Work zone crosswalk line, class III, 12", 642 paint (614E27250) | FT | 765 | $1.00 | $1.00 | $1.00 | $3.60 | $1.00 |
| 49 | Work zone arrow, class I, 642 paint (614E30200) | EACH | 7 | $50.00 | $50.00 | $50.00 | $80.00 | $50.00 |
| 50 | Work zone arrow, class III, 642 paint (614E30650) | EACH | 7 | $45.00 | $45.00 | $45.00 | $80.00 | $45.00 |
| 51 | Signing, misc.: additional signs, ground mounted, (630E97800) | SF | 300 | $30.00 | $10.00 | $30.00 | $34.60 | $30.00 |
| 52 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $10,486 | $25,750 | $7,000.00 | $6,500.00 | $10,000 |
| 53 | Maintaining traffic (614E11000) | LS | 1 | $81,250 | $120,748 | $106,500 | $168,602 | $255,750 |
| 54 | Field office, type B, as per plan (619E16011) | MNTH | 6 | $2,000.00 | $2,400.00 | $3,000.00 | $3,500.00 | $3,500.00 |
| 55 | Construction layout stakes and surveying (623E10000) | LS | 1 | $4,495.00 | $8,750.00 | $9,000.00 | $7,500.00 | $10,000 |
| 56 | Mobilization (624E10000) | LS | 1 | $85,000 | $117,879 | $87,150 | $40,000 | $100,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 23, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.