ODOT contract 250486 bid tabulation
BEL-SR 147-04.90 (TWO LANE RESURFACING). Let by Ohio DOT on October 23, 2025, BEL. 3 bids received; low bid $3,495,534 by Shelly & Sands Inc, +5.8% against the engineer's estimate of $3,303,000.
- Owner
- Ohio DOT
- Letting
- 23 OCT 2025
- Pay items
- 46
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly & Sands Inc | $3,495,534 | Low | +6.0% |
| 2 | NLS Paving, Inc | $3,995,934 | +14% | +21% |
| 3 | Cast & Baker Corporation | $4,527,214 | +30% | +37% |
Engineer's estimate: $3,303,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly & Sands Inc | 2. NLS Paving, Inc | 3. Cast & Baker Corporation |
|---|---|---|---|---|---|---|
| 1 | Wearing course removed (202E23500) | SY | 2,199 | $17.00 | $15.00 | $7.00 |
| 2 | Walk removed (202E30000) | SF | 1,056 | $7.00 | $20.00 | $6.50 |
| 3 | Preparing subgrade for shoulder paving, as per plan (209E72051) | MI | 13.46 | $650.00 | $1,850.00 | $2,110.00 |
| 4 | Fence, misc.: temporary orange plastic constructio (607E98000) | FT | 1,156 | $3.75 | $5.00 | $4.00 |
| 5 | Curb ramp (608E52000) | SF | 955 | $45.00 | $50.00 | $45.00 |
| 6 | Detectable warning, as per plan (608E53021) | SF | 101 | $71.00 | $65.00 | $72.00 |
| 7 | Seeding, misc.: curb ramp grading restoration (659E98000) | SY | 42 | $17.00 | $75.00 | $18.00 |
| 8 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 |
| 9 | Aggregate drains (605E31100) | FT | 125 | $50.00 | $15.00 | $20.00 |
| 10 | Catch basin adjusted to grade (611E98630) | EACH | 3 | $1,800.00 | $2,150.00 | $1,800.00 |
| 11 | Manhole adjusted to grade (611E99654) | EACH | 4 | $1,880.00 | $1,500.00 | $2,000.00 |
| 12 | Partial depth pavement repair (asphalt concrete base) (251E01042) | CY | 50 | $550.00 | $600.00 | $750.00 |
| 13 | Pavement repair (253E02000) | CY | 125 | $550.00 | $600.00 | $615.00 |
| 14 | Pavement repair, as per plan (253E02001) | CY | 165 | $600.00 | $625.00 | $675.00 |
| 15 | Pavement planing, asphalt concrete, 2 1/4" (254E01000) | SY | 152,366 | $3.00 | $3.20 | $4.50 |
| 16 | Non-tracking tack coat (407E20000) | GAL | 21,332 | $3.50 | $3.25 | $4.25 |
| 17 | Prime coat, as per plan (408E10001) | GAL | 6,317 | $4.75 | $4.50 | $8.00 |
| 18 | Asphalt concrete surface course, type 1, (446), PG70-22M (441E10100) | CY | 5,390 | $210.00 | $245.00 | $278.00 |
| 19 | Asphalt concrete intermediate course, type 1, (448) (441E50200) | CY | 4,232 | $185.00 | $220.00 | $262.00 |
| 20 | Asphalt concrete surface course, type 1, (449), (driveways), as per plan (441E70501) | CY | 76 | $550.00 | $675.00 | $485.00 |
| 21 | Compacted aggregate, as per plan (617E10101) | CY | 987 | $60.00 | $95.00 | $150.00 |
| 22 | Shoulder preparation, as per plan (617E20001) | SY | 15,793 | $0.85 | $0.25 | $1.35 |
| 23 | Rumble stripes, center line (asphalt concrete) (618E43000) | MI | 4.47 | $1,650.00 | $2,425.00 | $2,000.00 |
| 24 | Longitudinal joint preparation (874E21000) | MI | 4.47 | $7,500.00 | $6,500.00 | $10,000 |
| 25 | RPM (621E00100) | EACH | 791 | $40.00 | $37.75 | $40.00 |
| 26 | Raised pavement marker removed (621E54000) | EACH | 791 | $9.00 | $8.00 | $11.00 |
| 27 | Edge line, 6" (646E10010) | MI | 13.50 | $3,350.00 | $3,350.00 | $3,500.00 |
| 28 | Center line (646E10200) | MI | 8.80 | $3,670.00 | $3,670.00 | $3,925.00 |
| 29 | Channelizing line, 8" (646E10300) | FT | 65 | $2.00 | $2.00 | $2.15 |
| 30 | Stop line (646E10400) | FT | 245 | $12.00 | $12.00 | $13.00 |
| 31 | Crosswalk line, 12" (646E10510) | FT | 1,026 | $6.00 | $5.95 | $6.50 |
| 32 | Crosswalk line, 24" (646E10520) | FT | 369 | $12.00 | $12.00 | $12.00 |
| 33 | Transverse/diagonal line (646E10600) | FT | 98 | $7.00 | $7.00 | $7.50 |
| 34 | Island marking (646E10800) | SF | 48 | $6.00 | $6.00 | $6.45 |
| 35 | Lane arrow (646E20300) | EACH | 2 | $166.00 | $166.00 | $175.00 |
| 36 | Two way left turn arrow (646E20370) | EACH | 7 | $222.00 | $222.00 | $235.00 |
| 37 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 120 | $120.00 | $95.00 | $100.00 |
| 38 | Work zone marking sign (614E12460) | EACH | 48 | $86.00 | $86.00 | $95.00 |
| 39 | Work zone center line, class II, 642 paint (614E21500) | MI | 26.40 | $950.00 | $600.00 | $800.00 |
| 40 | Work zone center line, class III, 642 paint (614E21550) | MI | 26.40 | $865.00 | $850.00 | $925.00 |
| 41 | Work zone channelizing line, class III, 8", 642 paint (614E23680) | FT | 195 | $3.25 | $3.15 | $3.50 |
| 42 | Work zone stop line, class III, 642 paint (614E26610) | FT | 831 | $5.50 | $5.45 | $6.00 |
| 43 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $16,500 | $20,285 | $32,000 |
| 44 | Maintaining traffic (614E11000) | LS | 1 | $239,000 | $215,000 | $165,000 |
| 45 | Field office, type B (619E16010) | MNTH | 5 | $1,250.00 | $2,000.00 | $6,000.00 |
| 46 | Mobilization (624E10000) | LS | 1 | $73,272 | $170,000 | $50,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 23, 2025. Compiled by Mirage Metrics.