D05-Guardrail FY2025 (GUARDRAIL REBUILDING). Let by Ohio DOT on April 24, 2025, District 5. 3 bids received; low bid $1,859,786 by M P Dory Co, -15% against the engineer's estimate of $2,190,000.
- Owner
- Ohio DOT
- Letting
- 24 APR 2025
- Pay items
- 41
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | M P Dory Co | $1,859,786 | Low | -15% |
| 2 | Lake Erie Construction Company | $1,927,325 | +4.0% | -12% |
| 3 | Cuyahoga Fence LLC | $2,085,751 | +12% | -5.0% |
Engineer's estimate: $2,190,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. M P Dory Co | 2. Lake Erie Construction Company | 3. Cuyahoga Fence LLC |
|---|---|---|---|---|---|---|
| 1 | Guardrail removed (202E38000) | FT | 13,200 | $1.80 | $1.60 | $2.00 |
| 2 | Guardrail removed, as per plan (202E38001) | FT | 6,250 | $2.00 | $2.80 | $2.25 |
| 3 | Anchor assembly removed, type A (202E42000) | EACH | 51 | $280.00 | $320.00 | $275.00 |
| 4 | Anchor assembly removed, type E (202E42010) | EACH | 48 | $150.00 | $150.00 | $150.00 |
| 5 | Anchor assembly removed, type T (202E42040) | EACH | 34 | $100.00 | $100.00 | $100.00 |
| 6 | Bridge terminal assembly removed (202E47000) | EACH | 16 | $85.00 | $80.00 | $150.00 |
| 7 | Guardrail, type MGS with long posts (606E15100) | FT | 24,400 | $19.50 | $19.40 | $22.50 |
| 8 | Guardrail, type MGS, long-span (606E17360) | FT | 593.75 | $21.00 | $22.00 | $22.00 |
| 9 | Guardrail post, steel, as per plan (606E19001) | EACH | 250 | $75.00 | $65.00 | $60.00 |
| 10 | Guardrail post, steel, as per plan (606E19001) | EACH | 65 | $75.00 | $95.00 | $90.00 |
| 11 | Anchor assembly, MGS type A (606E25550) | EACH | 1 | $1,750.00 | $1,520.00 | $1,950.00 |
| 12 | Anchor assembly, MGS type E (MASH 2016) (606E26150) | EACH | 72 | $2,400.00 | $2,380.00 | $2,400.00 |
| 13 | Anchor assembly, MGS type T (606E26550) | EACH | 56 | $1,000.00 | $1,325.00 | $1,100.00 |
| 14 | MGS bridge terminal assembly, type TST-2 (606E34600) | EACH | 4 | $1,600.00 | $2,380.00 | $3,150.00 |
| 15 | Bridge terminal assembly, type 4 (606E35140) | EACH | 12 | $850.00 | $980.00 | $1,100.00 |
| 16 | Special - reshaping berm (606E50000) | FT | 25,012 | $0.50 | $0.10 | $0.60 |
| 17 | Special - cable barrier with concrete line post foundation (606E55010) | FT | 10,090 | $19.75 | $22.00 | $28.00 |
| 18 | Special - cable barrier, anchor assembly (606E55150) | EACH | 10 | $3,750.00 | $3,950.00 | $3,500.00 |
| 19 | Guardrail, misc.: existing W-beam for shoulder SU (606E98000) | FT | 65 | $10.00 | $18.00 | $9.00 |
| 20 | Guardrail, misc.: shoulder support benching (606E98000) | FT | 6,250 | $6.00 | $7.00 | $7.00 |
| 21 | Special - mailbox removed and reset (690E50350) | EACH | 20 | $45.00 | $150.00 | $150.00 |
| 22 | Special - no mow strip (690E98300) | SY | 4,707 | $67.00 | $68.00 | $65.00 |
| 23 | Granular material, type B, as per plan (203E35111) | CY | 2,779 | $60.00 | $82.00 | $76.00 |
| 24 | Granular material, type B, as per plan (203E35111) | CY | 925 | $60.00 | $87.00 | $76.00 |
| 25 | Geotextile fabric, as per plan (204E50001) | SY | 1,388 | $2.00 | $2.50 | $2.00 |
| 26 | Seeding and mulching, class 2 (659E00510) | SY | 15,545 | $1.00 | $1.00 | $1.00 |
| 27 | Commercial fertilizer (659E20000) | TON | 2.09 | $1,275.00 | $300.00 | $1,500.00 |
| 28 | Lime (659E31000) | ACRE | 3.21 | $158.00 | $50.00 | $200.00 |
| 29 | Water (659E35000) | MGAL | 84 | $1.00 | $1.00 | $1.00 |
| 30 | Slope erosion protection (670E00500) | SY | 16,432 | $1.50 | $2.00 | $2.00 |
| 31 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 |
| 32 | Barrier reflector, type 2 BI-directional (626E00110) | EACH | 438 | $10.00 | $13.10 | $10.50 |
| 33 | Barrier reflector, type 6 (626E00118) | EACH | 113 | $10.00 | $15.00 | $15.00 |
| 34 | Ground mounted support, no. 3 post (630E03100) | FT | 900 | $8.00 | $12.50 | $11.00 |
| 35 | Removal of ground mounted sign and reerection (630E85100) | EACH | 79 | $35.00 | $55.00 | $60.00 |
| 36 | Removal of ground mounted post support and disposal (630E86002) | EACH | 60 | $15.00 | $15.00 | $15.00 |
| 37 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 40 | $80.00 | $60.00 | $100.00 |
| 38 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $11,500 | $6,389.00 | $20,000 |
| 39 | Maintaining traffic (614E11000) | LS | 1 | $10,000 | $28,500 | $25,000 |
| 40 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $20,000 | $500.00 | $25,000 |
| 41 | Mobilization (624E10000) | LS | 1 | $100,000 | $23,500 | $50,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 24, 2025. Compiled by Mirage Metrics.