ODOT contract 260030 bid tabulation
WYA-US 23-09.28 (SIGNING). Let by Ohio DOT on January 15, 2026, WYA. 3 bids received; low bid $252,068 by Cleveland Barricading Systems LLC, -25% against the engineer's estimate of $337,000.
- Owner
- Ohio DOT
- Letting
- 15 JAN 2026
- Pay items
- 24
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Cleveland Barricading Systems LLC | $252,068 | Low | -25% |
| 2 | Lake Erie Construction Company | $318,425 | +26% | -6.0% |
| 3 | M P Dory Co | $388,930 | +54% | +15% |
Engineer's estimate: $337,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Cleveland Barricading Systems LLC | 2. Lake Erie Construction Company | 3. M P Dory Co |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $1,025.00 | $650.00 | $1.00 |
| 2 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 | $1.00 |
| 3 | Ground rod (625E32000) | EACH | 3 | $650.00 | $320.00 | $600.00 |
| 4 | Ground mounted structural beam support, W8X18 (630E07000) | FT | 45.60 | $43.50 | $55.00 | $37.00 |
| 5 | Ground mounted structural beam support, W10X22 (630E07500) | FT | 107.60 | $55.00 | $65.00 | $45.00 |
| 6 | Ground mounted structural beam support, W10X12 (630E07600) | FT | 138.30 | $34.00 | $40.00 | $26.00 |
| 7 | Breakaway structural beam connection (630E09000) | EACH | 6 | $950.00 | $965.00 | $850.00 |
| 8 | Overhead sign support, type TC-12.31, design 6 (630E72320) | EACH | 2 | $28,000 | $31,800 | $27,000 |
| 9 | Overhead sign support, type TC-12.31, design 10 (630E72330) | EACH | 1 | $39,000 | $43,200 | $37,000 |
| 10 | Sign, ground mounted extrusheet (630E80200) | SF | 595 | $25.25 | $24.00 | $27.50 |
| 11 | Sign, overhead extrusheet (630E80224) | SF | 376 | $27.00 | $24.75 | $28.50 |
| 12 | Sign backing assembly (630E82000) | EACH | 3 | $131.00 | $185.00 | $250.00 |
| 13 | Ground mounted structural beam support foundation (630E84500) | EACH | 14 | $1,100.00 | $925.00 | $1,500.00 |
| 14 | Rigid overhead sign support foundation (630E84510) | EACH | 3 | $8,000.00 | $10,400 | $10,000 |
| 15 | Removal of ground mounted major sign and disposal (630E85400) | EACH | 1 | $160.00 | $165.00 | $25.00 |
| 16 | Removal of ground mounted post support and disposal (630E86002) | EACH | 2 | $155.00 | $15.00 | $25.00 |
| 17 | US route shield symbol marking, type B125 (814E00012) | EACH | 16 | $1,325.00 | $3,750.00 | $7,500.00 |
| 18 | Cardinal direction (north, south, west & east) marking, type B125 (814E00016) | EACH | 16 | $650.00 | $550.00 | $750.00 |
| 19 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 50 | $110.00 | $60.00 | $100.00 |
| 20 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $1,100.00 | $1,500.00 | $5,000.00 |
| 21 | Maintaining traffic (614E11000) | LS | 1 | $13,650 | $30,450 | $12,000 |
| 22 | Field office, type B (619E16010) | MNTH | 2 | $1,250.00 | $740.00 | $1,000.00 |
| 23 | Construction layout stakes and surveying (623E10000) | LS | 1 | $3,000.00 | $1,250.00 | $5,000.00 |
| 24 | Mobilization (624E10000) | LS | 1 | $12,000 | $13,225 | $40,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of January 15, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.