ODOT contract 250255 bid tabulation

LIC-SR 16-05.38 (MISCELLANEOUS). Let by Ohio DOT on May 8, 2025, LIC. 3 bids received; low bid $391,803 by M P Dory Co, +1.0% against the engineer's estimate of $388,000.

Owner
Ohio DOT
Letting
08 MAY 2025
Pay items
79
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1M P Dory Co$391,803Low+1.0%
2Jess Howard Electric Co$408,328+4.0%+5.0%
3Complete General Construction Company$455,649+16%+17%
ODOT contract 250255: bids by rank

Engineer's estimate: $388,000.

Bid tabulation

LinePay itemUnitQuantity1. M P Dory Co2. Jess Howard Electric Co3. Complete General Construction Company
1Clearing and grubbing (201E11000)LS1$5,125.00$5,394.78$4,000.00
2Pavement removed (202E23000)SY5$160.00$189.49$125.00
3Curb and gutter removed (202E32500)FT17$31.00$39.32$38.00
4Removal misc.: mulch removed (202E98000)LS1$460.00$605.30$1,200.00
5Removal misc.:parking block removal (202E98100)EACH1$46.00$178.98$400.00
6Excavation (203E10000)CY82$230.00$233.19$178.00
7Embankment (203E20000)CY24$230.00$237.07$68.00
8Soil analysis test (659E00100)EACH2$205.00$613.18$150.00
9Topsoil (659E00300)CY82$125.00$85.83$90.00
10Seeding and mulching, class 1 (659E00500)SY735$5.40$3.55$4.56
11Repair seeding and mulching (659E14000)SY37$1.00$11.99$4.56
12Inter-seeding (659E15000)SY37$0.01$11.99$4.56
13Commercial fertilizer (659E20000)TON0.07$1,540.00$3,910.14$1,250.00
14Lime (659E31000)ACRE0.15$205.00$1,859.87$150.00
15Water (659E35000)MGAL4$1.00$222.38$1.00
16Erosion control (832E30000)EACH15,000$1.00$1.00$1.00
176" conduit, type C (611E01100)FT25$36.00$42.10$155.00
1812" conduit, type B (611E04400)FT89$115.00$117.28$298.00
19Catch basin, no. 2-2B (611E98470)EACH1$2,700.00$2,921.08$4,200.00
20Catch basin adjusted to grade (611E98630)EACH2$1,025.00$1,118.44$2,500.00
21Inlet, misc.: replace catch basin top with 2-2A (611E99500)EACH2$640.00$723.70$3,400.00
22Inlet, misc.:yard drain, type B (611E99500)EACH4$1,740.00$2,559.22$3,200.00
23Pavement repair, as per plan (253E01001)SY4$640.00$690.80$950.00
24Aggregate base (304E20000)CY60$310.00$323.24$155.00
254" concrete walk (608E10000)SF3,676$14.50$13.73$10.00
26Curb ramp (608E52000)SF394$20.00$20.60$30.00
27Detectable warning (608E53020)SF100$36.00$38.17$42.00
28Combination curb and gutter, type 2 (609E12000)FT17$110.00$119.32$275.00
29Valve box adjusted to grade (638E10800)EACH4$460.00$506.58$780.00
30Service box adjusted to grade (638E10900)EACH1$614.00$763.20$945.00
31Ground mounted support, no. 3 post (630E03100)FT75$24.00$11.61$49.00
32Sign post reflector (630E08600)EACH1$50.00$200.04$250.00
33Sign support assembly, pole mounted (630E79500)EACH4$225.00$101.32$425.00
34Sign, flat sheet (630E80100)SF7.50$36.00$53.34$160.00
35Removal of ground mounted sign and reerection (630E85100)EACH12$35.00$69.91$175.00
36Removal of ground mounted post support and disposal (630E86002)EACH5$66.00$74.11$75.00
37Stop line (644E00500)FT53$9.40$18.03$8.50
38Crosswalk line, 12" (644E00620)FT219$4.40$5.24$4.00
39Transverse/diagonal line (644E00700)FT60$9.40$10.52$8.50
40Removal of pavement marking (644E30020)EACH2$670.00$1,513.18$605.00
41Conduit, 2", 725.04 (625E25400)FT195$40.00$31.25$25.00
42Conduit, 4", 725.04 (625E25600)FT16$66.00$180.70$68.00
43Trench (625E29000)FT207$18.50$26.57$18.00
44Pull box, 725.08, 24" (625E30706)EACH1$2,110.00$2,001.49$1,500.00
45Ground rod (625E32000)EACH10$400.00$340.30$300.00
46Underground warning marking tape (625E36010)FT207$1.20$0.75$1.75
47Arc flash calculations and label, traffic signal C (625E76000)EACH1$3,800.00$121.10$4,000.00
48Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate (632E05006)EACH4$1,270.00$1,651.09$1,200.00
49Vehicular signal head, (LED), 5-section, 12" lens, 1-way, polycarbonate (632E05086)EACH4$2,230.00$2,027.71$2,000.00
50Pedestrian signal head (LED), type D2, countdown, as per plan (632E20731)EACH6$690.00$626.64$700.00
51Covering of pedestrian signal head (632E25010)EACH6$33.00$64.31$35.00
52Pedestrian pushbutton, as per plan (632E26001)EACH6$500.00$317.41$325.00
53Signal cable, 5 conductor, no. 14 AWG (632E40500)FT1,281$5.00$3.41$3.00
54Signal cable, 7 conductor, no. 14 AWG (632E40700)FT724$5.50$4.58$4.00
55Pedestal foundation (632E64020)EACH6$1,750.00$1,144.21$1,700.00
56Test hole performed (632E64950)EACH6$500.00$1,277.77$700.00
57Loop detector lead-in cable (632E65200)FT1,257$3.20$2.05$2.25
58Power cable, 2 conductor, no. 6 AWG (632E68200)FT183$5.00$5.37$4.25
59Power cable, 3 conductor, no. 6 AWG (632E68300)FT30$7.50$19.78$5.25
60Power service, as per plan (632E70001)EACH1$500.00$1,516.02$2,000.00
61Conduit riser, 2" diameter (632E70400)EACH1$1,500.00$2,210.94$1,300.00
62Pedestal, 11', transformer base, as per plan (632E90001)EACH6$2,200.00$1,775.79$2,000.00
63Removal of traffic signal installation, as per plan (632E90101)EACH1$2,500.00$12,071$6,000.00
64Reuse of traffic control itemwireless equipment (632E90104)EACH1$500.00$76.34$1,000.00
65Reuse of controller, as per plan (632E90213)EACH1$2,585.00$1,655.28$1,600.00
66Signalization, misc.:power meter cabinet, base mou (632E90400)EACH1$5,700.00$5,133.96$6,000.00
67Signalization, misc.:unlash and relash messenger W (632E90400)EACH225$2.50$17.53$4.00
68GPS (global positioning system) clock assembly (633E45000)EACH1$650.00$2,037.47$650.00
69Cabinet foundation (633E67100)EACH1$5,280.00$4,322.80$5,000.00
70Controller work pad, as per plan (633E67201)EACH1$770.00$1,436.74$3,000.00
71Uninterruptible power supply (UPS), 1000 watt, as per plan (633E75001)EACH1$7,800.00$7,945.24$6,800.00
72Controller item, misc.:controller unit, type TS2/A (633E99000)EACH1$29,200$26,708$30,000
73Stop line radar detection, as per plan (809E69101)EACH4$9,500.00$9,094.00$8,800.00
74Law enforcement officer with patrol car for assistance (614E11110)HR40$90.00$101.33$81.00
75Premium for contract performance bond and for payment bond (103E05000)LS1$2,400.00$4,080.00$2,400.00
76Maintaining traffic (614E11000)LS1$2,000.00$7,763.20$30,000
77Construction layout stakes and surveying (623E10000)LS1$7,500.00$6,081.60$19,200
78Mobilization (624E10000)LS1$10,000$13,544$25,000
79Special - record construction drawings (690E98400)LS1$1,650.00$2,049.60$6,000.00
ODOT contract 250255: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of May 8, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy