ODOT contract 250268 bid tabulation
D12-SIGN FY2025 (SIGNING). Let by Ohio DOT on May 8, 2025, District 12. 2 bids received; low bid $332,150 by Lake Erie Construction Company, -3.7% against the engineer's estimate of $345,000.
- Owner
- Ohio DOT
- Letting
- 08 MAY 2025
- Pay items
- 23
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Lake Erie Construction Company | $332,150 | Low | -4.0% |
| 2 | M P Dory Co | $343,821 | +4.0% | 0.0% |
Engineer's estimate: $345,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Lake Erie Construction Company | 2. M P Dory Co |
|---|---|---|---|---|---|
| 1 | Overhead sign support, type TC-12.31, design 12 (630E72340) | EACH | 1 | $41,850 | $37,500 |
| 2 | Overhead sign support, installation only, as per plan (630E74601) | EACH | 1 | $7,500.00 | $5,250.00 |
| 3 | Sign attachment assembly (630E75000) | EACH | 87 | $795.00 | $800.00 |
| 4 | Sign hanger assembly, span wire (630E79000) | EACH | 4 | $425.00 | $400.00 |
| 5 | Sign support assembly, bridge mounted, type 1 (630E79600) | EACH | 2 | $1,950.00 | $1,250.00 |
| 6 | Sign, ground mounted extrusheet (630E80200) | SF | 917 | $22.00 | $22.50 |
| 7 | Sign, overhead extrusheet (630E80224) | SF | 4,206 | $22.00 | $23.00 |
| 8 | Sign erected, extrusheet, as per plan (630E81201) | SF | 293.50 | $14.00 | $13.00 |
| 9 | Rigid overhead sign support foundation (630E84510) | EACH | 4 | $9,875.00 | $10,000 |
| 10 | Removal of ground mounted sign and disposal (630E84900) | EACH | 6 | $15.00 | $25.00 |
| 11 | Removal of ground mounted sign and reerection (630E85100) | EACH | 1 | $75.00 | $135.00 |
| 12 | Removal of ground mounted major sign and disposal (630E85400) | EACH | 3 | $375.00 | $500.00 |
| 13 | Removal of structure mounted sign and disposal (630E86310) | EACH | 1 | $320.00 | $500.00 |
| 14 | Removal of overhead mounted sign and disposal, as per plan (630E87401) | EACH | 27 | $250.00 | $300.00 |
| 15 | Removal of pole mounted sign and reerection (630E87520) | EACH | 2 | $180.00 | $150.00 |
| 16 | Removal of overhead sign support and disposal, as per plan (630E89703) | EACH | 1 | $1,850.00 | $2,000.00 |
| 17 | Signing, misc.: removal of sign support foundation (630E97700) | EACH | 2 | $875.00 | $1,500.00 |
| 18 | Signing, misc.: support foundation repair (630E97700) | EACH | 1 | $7,500.00 | $7,500.00 |
| 19 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 100 | $60.00 | $115.00 |
| 20 | Signing, misc.: additional signs, ground mounted, (630E97800) | SF | 100 | $10.00 | $5.00 |
| 21 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $1,500.00 | $3,500.00 |
| 22 | Maintaining traffic (614E11000) | LS | 1 | $11,300 | $2,500.00 |
| 23 | Mobilization (624E10000) | LS | 1 | $12,100 | $25,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 8, 2025. Compiled by Mirage Metrics.