ODOT contract 250268 bid tabulation

D12-SIGN FY2025 (SIGNING). Let by Ohio DOT on May 8, 2025, District 12. 2 bids received; low bid $332,150 by Lake Erie Construction Company, -3.7% against the engineer's estimate of $345,000.

Owner
Ohio DOT
Letting
08 MAY 2025
Pay items
23
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Lake Erie Construction Company$332,150Low-4.0%
2M P Dory Co$343,821+4.0%0.0%
ODOT contract 250268: bids by rank

Engineer's estimate: $345,000.

Bid tabulation

LinePay itemUnitQuantity1. Lake Erie Construction Company2. M P Dory Co
1Overhead sign support, type TC-12.31, design 12 (630E72340)EACH1$41,850$37,500
2Overhead sign support, installation only, as per plan (630E74601)EACH1$7,500.00$5,250.00
3Sign attachment assembly (630E75000)EACH87$795.00$800.00
4Sign hanger assembly, span wire (630E79000)EACH4$425.00$400.00
5Sign support assembly, bridge mounted, type 1 (630E79600)EACH2$1,950.00$1,250.00
6Sign, ground mounted extrusheet (630E80200)SF917$22.00$22.50
7Sign, overhead extrusheet (630E80224)SF4,206$22.00$23.00
8Sign erected, extrusheet, as per plan (630E81201)SF293.50$14.00$13.00
9Rigid overhead sign support foundation (630E84510)EACH4$9,875.00$10,000
10Removal of ground mounted sign and disposal (630E84900)EACH6$15.00$25.00
11Removal of ground mounted sign and reerection (630E85100)EACH1$75.00$135.00
12Removal of ground mounted major sign and disposal (630E85400)EACH3$375.00$500.00
13Removal of structure mounted sign and disposal (630E86310)EACH1$320.00$500.00
14Removal of overhead mounted sign and disposal, as per plan (630E87401)EACH27$250.00$300.00
15Removal of pole mounted sign and reerection (630E87520)EACH2$180.00$150.00
16Removal of overhead sign support and disposal, as per plan (630E89703)EACH1$1,850.00$2,000.00
17Signing, misc.: removal of sign support foundation (630E97700)EACH2$875.00$1,500.00
18Signing, misc.: support foundation repair (630E97700)EACH1$7,500.00$7,500.00
19Law enforcement officer with patrol car for assistance (614E11110)HR100$60.00$115.00
20Signing, misc.: additional signs, ground mounted, (630E97800)SF100$10.00$5.00
21Premium for contract performance bond and for payment bond (103E05000)LS1$1,500.00$3,500.00
22Maintaining traffic (614E11000)LS1$11,300$2,500.00
23Mobilization (624E10000)LS1$12,100$25,000
ODOT contract 250268: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of May 8, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.