ODOT letting results, May 22, 2025
30 contracts let by Ohio DOT on May 22, 2025, $76,505,438 in low bids, a median of 2.5 bidders per contract. On the 30 with an engineer's estimate, the low bid came in under it 20 times; median low bid -8.0% against the estimate.
- Owner
- Ohio DOT
- Contracts
- 30
- Low bids, total
- $76,505,438
- Data through
- 12 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 250263 | UNI-US 42-03.91 (MINOR RECONSTRUCTION) | UNI | 6 | Shelly Company | $7,959,354 | $8,372,353 | +5.0% | -13% | ODOT |
| 250275 | FRA-IR 70-15.52 (FOUR LANE RESURFACING) | FRA | 3 | Shelly Company | $7,366,774 | $7,630,656 | +4.0% | +4.0% | ODOT |
| 250274 | ERI-SR 2-15.89 (MINOR RECONSTRUCTION) | ERI | 4 | Gerken Paving Inc | $6,104,814 | $6,307,134 | +3.0% | -3.0% | ODOT |
| 250287 | TUS-US 250-12.79 (FOUR LANE RESURFACING) | TUS | 4 | Shelly & Sands Inc | $5,027,975 | $5,133,405 | +2.0% | -9.0% | ODOT |
| 250288 | WAS-SR 26-18.45 (TWO LANE RESURFACING) | WAS | 1 | Shelly & Sands Inc | $4,844,844 | +5.0% | ODOT | ||
| 250289 | WAS-SR 807-00.00 (TWO LANE RESURFACING) | WAS | 1 | Shelly & Sands Inc | $4,795,095 | -6.0% | ODOT | ||
| 250286 | STA-IR 77-00.00 (FOUR LANE RESURFACING) | STA | 2 | Shelly Company | $4,326,599 | $4,747,000 | +10% | +12% | ODOT |
| 250281 | LAK-SR 2-14.38 (FOUR LANE RESURFACING) | LAK | 3 | Shelly Company | $3,768,846 | $3,775,000 | 0.0% | -8.0% | ODOT |
| 250285 | SEN-SR 4/SR 18-07.52/15.39 Resurf (TWO LANE RESURFACING) | SEN | 4 | Kokosing Construction Company Inc | $3,740,212 | $3,811,122 | +2.0% | -13% | ODOT |
| 250291 | WYA-US 23-00.00/04.03 (FOUR LANE RESURFACING) | WYA | 2 | Kokosing Construction Company Inc | $3,478,616 | $3,510,412 | +1.0% | -10% | ODOT |
| 250276 | HAM-BS FY 2026 (BRIDGE REPAIR) | HAM | 2 | Aad Contracting Inc | $3,172,616 | $3,084,871 | -3.0% | +2.0% | ODOT |
| 250277 | HAM-SR 264-10.42 (RELOCATION) | HAM | 5 | KT Holden Construction LLC | $2,212,186 | $2,294,651 | +4.0% | -14% | ODOT |
| 250284 | SCI-SR 125/SR 772-06.25/00.00 (TWO LANE RESURFACING) | SCI | 1 | Shelly Company | $2,163,145 | -6.0% | ODOT | ||
| 250282 | PIK-SR 124-14.96 (MINOR RECONSTRUCTION) | PIK | 4 | Allard Excavation LLC | $1,944,512 | $1,978,551 | +2.0% | -30% | ODOT |
| 250273 | COS-SR 93-00.75 (SLIDE REPAIR) | COS | 4 | Shelly & Sands Inc | $1,936,739 | $2,014,304 | +4.0% | -27% | ODOT |
| 250279 | JAC-SR 139/SR 776/SR 788-11.35/00.00/02.36 (TWO LANE RESURFACING) | JAC | 2 | Shelly & Sands Inc | $1,885,831 | $2,078,076 | +10% | -9.0% | ODOT |
| 258011 | ATH-Madison St Bridge (BRIDGE REPLACEMENT (1 BRIDGE)) | ATH | 5 | Alan Stone Co Inc | $1,869,559 | $1,895,253 | +1.0% | -11% | ODOT |
| 250272 | COL-US 30/VAR-25.09/VAR,TUS-IR 77-13.00 (SIGNING) | COL | 2 | M P Dory Co | $1,722,285 | $1,735,325 | +1.0% | -15% | ODOT |
| 250294 | D05-Spot Paving FY2026 (SPOT PATCHING / PAVEMENT REPAIR) | District 5 | 3 | Shelly Company | $1,477,240 | $1,505,000 | +2.0% | +8.0% | ODOT |
| 258009 | AUG-St Marys Indiana Walks SA22 (SIGNALIZATION) | AUG | 5 | Perram Electric Inc | $1,310,400 | $1,415,587 | +8.0% | -9.0% | ODOT |
| 250293 | D04-SP FY2025 (West) (SPOT PATCHING / PAVEMENT REPAIR) | District 4 | 2 | Barbicas Construction Company Inc | $1,273,386 | $1,475,000 | +16% | +2.0% | ODOT |
| 250278 | HAM-/WAR-US 22-16.04/00.00 Ped (SPOT SAFETY) | HAM | 2 | Complete General Construction Company | $863,798 | $992,621 | +15% | +15% | ODOT |
| 258008 | WAS-IR 77-00.31 (BRIDGE REPAIR) | WAS | 1 | Evers Steel Construction LLC | $798,085 | +56% | ODOT | ||
| 250292 | D04-SP FY2025 (East) (SPOT PATCHING / PAVEMENT REPAIR) | District 4 | 2 | Shelly & Sands Inc | $722,588 | $797,000 | +10% | +9.0% | ODOT |
| 250299 | WAY-SR 3/SR 301-07.15/01.60 (CULVERT REPLACEMENT) | WAY | 2 | Eclipse Co LLC | $523,203 | $586,064 | +12% | -11% | ODOT |
| 250297 | MRW-SR 61-SP-2025 (GENERAL) (TWO LANE RESURFACING) | MRW | 2 | Kokosing Construction Company Inc | $444,692 | $460,996 | +4.0% | -5.0% | ODOT |
| 254017 | WAY-US 250-27.50 (Culvert Replacement) | WAY | 3 | Crawford Construction Company Inc | $210,450 | $298,128 | +42% | +24% | ODOT |
| 250295 | D07-RPM FY25 (RAISED PAVEMENT MARKERS) | District 7 | 2 | A & A Safety Inc | $193,399 | $195,746 | +1.0% | -11% | ODOT |
| 250298 | ROS-Tar Hollow SF Culverts FY25 (CULVERT REPLACEMENT) | ROS | 5 | Parker Corporation | $193,222 | $194,816 | +1.0% | -18% | ODOT |
| 250296 | D12-TSG FY2025 (SIGNALIZATION) | District 12 | 3 | Perram Electric Inc | $174,974 | $223,923 | +28% | -24% | ODOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.