ODOT contract 258011 bid tabulation
ATH-Madison St Bridge (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on May 22, 2025, ATH. 5 bids received; low bid $1,869,559 by Alan Stone Co Inc, -11% against the engineer's estimate of $2,090,000.
- Owner
- Ohio DOT
- Letting
- 22 MAY 2025
- Pay items
- 80
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Alan Stone Co Inc | $1,869,559 | Low | -11% |
| 2 | D G M Inc | $1,895,253 | +1.0% | -9.0% |
| 3 | George J Igel & Co Inc | $2,049,514 | +10% | -2.0% |
| 4 | Shelly & Sands Inc | $2,390,862 | +28% | +14% |
| 5 | Double Z Construction Company | $2,399,818 | +28% | +15% |
Engineer's estimate: $2,090,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Alan Stone Co Inc | 2. D G M Inc | 3. George J Igel & Co Inc | 4. Shelly & Sands Inc | 5. Double Z Construction Company |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $28,000 | $35,000 | $5,000.00 | $7,000.00 | $30,000 |
| 2 | Pavement removed (202E23000) | SY | 265 | $15.00 | $4.00 | $8.25 | $10.00 | $30.00 |
| 3 | Walk removed (202E30000) | SF | 239 | $7.00 | $5.00 | $3.20 | $4.00 | $5.00 |
| 4 | Pipe removed, 24" and under (202E35100) | FT | 100 | $20.00 | $20.00 | $12.00 | $12.00 | $35.00 |
| 5 | Guardrail removed (202E38000) | FT | 63 | $20.00 | $1.00 | $5.00 | $10.00 | $8.00 |
| 6 | Excavation (203E10000) | CY | 276 | $60.00 | $30.00 | $40.00 | $27.00 | $40.00 |
| 7 | Embankment (203E20000) | CY | 844 | $15.00 | $25.00 | $27.00 | $45.00 | $50.00 |
| 8 | Subgrade compaction (204E10000) | SY | 370 | $8.50 | $8.00 | $9.00 | $5.00 | $14.00 |
| 9 | Proof rolling (204E45000) | HR | 1 | $520.00 | $75.00 | $135.00 | $220.00 | $200.00 |
| 10 | Guardrail, type MGS (606E15050) | FT | 13 | $25.00 | $35.00 | $23.00 | $30.00 | $23.00 |
| 11 | Anchor assembly, MGS type B (606E26050) | EACH | 1 | $3,000.00 | $3,000.00 | $2,750.00 | $2,500.00 | $2,750.00 |
| 12 | Anchor assembly, MGS type T (606E26550) | EACH | 1 | $1,800.00 | $1,700.00 | $1,650.00 | $1,500.00 | $1,650.00 |
| 13 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 1 | $3,200.00 | $3,000.00 | $2,900.00 | $2,500.00 | $2,900.00 |
| 14 | MGS bridge terminal assembly, type 1, as per plan (606E35003) | EACH | 1 | $3,200.00 | $3,000.00 | $2,900.00 | $2,850.00 | $2,900.00 |
| 15 | 4" concrete walk (608E10000) | SF | 218 | $25.00 | $15.00 | $19.00 | $20.00 | $32.00 |
| 16 | Detectable warning (608E53020) | SF | 10 | $30.00 | $40.00 | $72.00 | $15.00 | $30.00 |
| 17 | Curb, type 6 (609E26000) | FT | 17 | $110.00 | $50.00 | $68.00 | $150.00 | $90.00 |
| 18 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 6 | $180.00 | $120.00 | $190.00 | $130.00 | $200.00 |
| 19 | Soil analysis test (659E00100) | EACH | 2 | $160.00 | $50.00 | $150.00 | $150.00 | $150.00 |
| 20 | Topsoil (659E00300) | CY | 85 | $45.00 | $20.00 | $21.00 | $85.00 | $75.00 |
| 21 | Seeding and mulching (659E10000) | SY | 898 | $2.00 | $4.00 | $6.70 | $4.00 | $11.00 |
| 22 | Repair seeding and mulching (659E14000) | SY | 38 | $8.50 | $0.05 | $3.70 | $4.00 | $3.70 |
| 23 | Inter-seeding (659E15000) | SY | 38 | $8.50 | $0.05 | $3.70 | $4.00 | $3.70 |
| 24 | Commercial fertilizer (659E20000) | TON | 0.17 | $610.00 | $1,500.00 | $1,250.00 | $1,250.00 | $1,250.00 |
| 25 | Lime (659E31000) | ACRE | 0.16 | $880.00 | $300.00 | $150.00 | $150.00 | $150.00 |
| 26 | Water (659E35000) | MGAL | 4 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 27 | Erosion control (832E30000) | EACH | 15,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 28 | 12" conduit, type C (611E04600) | FT | 15 | $200.00 | $150.00 | $180.00 | $125.00 | $250.00 |
| 29 | 18" conduit, type B (611E07400) | FT | 74 | $240.00 | $150.00 | $275.00 | $195.00 | $365.00 |
| 30 | Catch basin, no. 3 (611E98150) | EACH | 1 | $5,500.00 | $4,000.00 | $5,000.00 | $5,000.00 | $4,900.00 |
| 31 | Catch basin, no. 2-2B (611E98470) | EACH | 1 | $4,800.00 | $7,500.00 | $4,150.00 | $4,350.00 | $4,100.00 |
| 32 | Manhole, no. 1 (611E99550) | EACH | 2 | $7,800.00 | $3,500.00 | $3,800.00 | $4,240.00 | $5,000.00 |
| 33 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 21 | $450.00 | $610.00 | $539.00 | $750.00 | $595.00 |
| 34 | Aggregate base (304E20000) | CY | 62 | $120.00 | $130.00 | $125.00 | $135.00 | $160.00 |
| 35 | Non-tracking tack coat (407E20000) | GAL | 10 | $6.00 | $3.90 | $4.00 | $3.50 | $3.90 |
| 36 | Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000) | CY | 7 | $920.00 | $675.00 | $1,152.00 | $1,500.00 | $655.00 |
| 37 | 6" non-reinforced concrete pavement, class QC 1P (452E10010) | SY | 16 | $230.00 | $200.00 | $180.00 | $245.00 | $160.00 |
| 38 | Ground mounted support, no. 3 post (630E03100) | FT | 42 | $25.00 | $20.00 | $20.00 | $25.00 | $32.00 |
| 39 | Sign, flat sheet (630E80100) | SF | 20.30 | $25.00 | $35.00 | $22.00 | $25.00 | $32.00 |
| 40 | Removal of ground mounted sign and disposal (630E84900) | EACH | 4 | $40.00 | $20.00 | $25.00 | $35.00 | $45.00 |
| 41 | Removal of ground mounted post support and disposal (630E86002) | EACH | 3 | $40.00 | $20.00 | $35.00 | $35.00 | $45.00 |
| 42 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 16 | $100.00 | $70.00 | $100.00 | $110.00 | $65.00 |
| 43 | Structure removed, over 20 foot span (202E11002) | LS | 1 | $50,000 | $96,000 | $132,000 | $75,885 | $90,000 |
| 44 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $4,000.00 | $140,000 | $88,000 | $316,500 | $350,000 |
| 45 | Unclassified excavation (503E21300) | LS | 1 | $46,000 | $25,000 | $160,500 | $180,000 | $175,000 |
| 46 | Rock excavation (503E31100) | CY | 64 | $95.00 | $50.00 | $62.05 | $80.00 | $240.00 |
| 47 | Epoxy coated steel reinforcement (509E10000) | LB | 63,658 | $2.00 | $1.20 | $1.75 | $2.00 | $1.75 |
| 48 | Semi-integral diaphragm guide, as per plan (511E33501) | EACH | 2 | $8,300.00 | $4,000.00 | $5,300.00 | $4,120.00 | $5,000.00 |
| 49 | Class QC2 concrete with QC/QA, bridge deck (511E34446) | CY | 156 | $910.00 | $1,215.00 | $1,400.00 | $1,150.00 | $1,290.00 |
| 50 | Class QC1 concrete with QC/QA, abutment not including footing (511E44112) | CY | 155 | $580.00 | $715.00 | $850.00 | $975.00 | $905.00 |
| 51 | Class QC1 concrete with QC/QA, footing (511E46512) | CY | 80 | $910.00 | $665.00 | $720.00 | $760.00 | $625.00 |
| 52 | Class QC2 concrete with QC/QA, sidewalk (511E51512) | CY | 19 | $1,400.00 | $690.00 | $590.00 | $820.00 | $740.00 |
| 53 | Sealing of concrete surfaces, as per plan (512E10001) | SY | 278 | $30.00 | $30.00 | $25.50 | $26.00 | $25.00 |
| 54 | Sealing of concrete surfaces (non-epoxy) (512E10050) | SY | 584 | $15.00 | $17.00 | $12.50 | $13.00 | $15.00 |
| 55 | Sealing concrete bridge decks with HMWM resin (512E10300) | SY | 8 | $225.00 | $50.00 | $98.00 | $40.00 | $75.00 |
| 56 | Type 2 waterproofing (512E33000) | SY | 23 | $190.00 | $25.00 | $35.00 | $40.00 | $40.00 |
| 57 | Draped strand prestressed concrete bridge I-beam members, level 3, type WF42-49 (515E15080) | EACH | 5 | $115,000 | $91,200 | $72,000 | $74,464 | $69,000 |
| 58 | Intermediate diaphragms (515E20000) | EACH | 12 | $1,250.00 | $1,850.00 | $1,700.00 | $4,130.00 | $1,550.00 |
| 59 | 1" preformed expansion joint filler (516E13600) | SF | 72 | $4.00 | $15.00 | $10.00 | $8.00 | $12.00 |
| 60 | 2" preformed expansion joint filler (516E13900) | SF | 301 | $3.50 | $25.00 | $12.00 | $8.00 | $16.00 |
| 61 | Semi-integral abutment expansion joint seal (516E14020) | FT | 186 | $10.00 | $47.50 | $40.00 | $45.00 | $30.00 |
| 62 | Elastomeric bearing with internal laminates and load plate (516E44100) | EACH | 10 | $2,500.00 | $3,000.00 | $3,000.00 | $2,950.00 | $2,700.00 |
| 63 | Railing (twin steel tube), as per plan (517E70001) | FT | 139 | $360.00 | $340.00 | $340.00 | $285.00 | $340.00 |
| 64 | Railing (concrete parapet with twin steel tube railing) (517E75120) | FT | 136 | $190.00 | $320.00 | $385.00 | $254.00 | $380.00 |
| 65 | Prefabricated geocomposite drain (518E20000) | SY | 93 | $80.00 | $45.00 | $32.00 | $36.00 | $35.00 |
| 66 | Porous backfill with geotextile fabric (518E21200) | CY | 82 | $150.00 | $120.00 | $170.00 | $148.00 | $140.00 |
| 67 | Special - steel drip strip (518E22300) | FT | 116 | $20.00 | $20.00 | $16.00 | $17.00 | $25.00 |
| 68 | 6" perforated corrugated plastic pipe (518E40000) | FT | 120 | $20.00 | $20.00 | $12.00 | $6.00 | $17.00 |
| 69 | 6" non-perforated corrugated plastic pipe, including specials, as per plan (518E40011) | FT | 25 | $20.00 | $70.00 | $65.00 | $22.00 | $25.00 |
| 70 | Drilled shafts, 42" diameter, into bedrock, as per plan (524E94805) | FT | 180 | $450.00 | $550.00 | $575.00 | $643.00 | $840.00 |
| 71 | Drilled shafts, 48" diameter above bedrock, as per plan (524E94903) | FT | 98 | $550.00 | $510.00 | $210.00 | $758.00 | $315.00 |
| 72 | Reinforced concrete approach slabs (T=15") (526E25000) | SY | 178 | $300.00 | $300.00 | $450.00 | $527.00 | $440.00 |
| 73 | Type A installation (526E90010) | FT | 69 | $150.00 | $225.00 | $300.00 | $225.00 | $255.00 |
| 74 | Rock channel protection, type C with filter (601E32200) | CY | 181 | $120.00 | $100.00 | $110.00 | $100.00 | $110.00 |
| 75 | Thermal integrity profiling (tip) test (894E10000) | EACH | 2 | $4,500.00 | $5,000.00 | $6,500.00 | $3,185.00 | $3,400.00 |
| 76 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $15,000 | $39,000 | $10,000 | $12,847 | $16,000 |
| 77 | Maintaining traffic (614E11000) | LS | 1 | $22,000 | $20,500 | $8,000.00 | $4,000.00 | $17,000 |
| 78 | Field office, type A (619E16000) | MNTH | 8 | $1,200.00 | $750.00 | $1,650.00 | $3,253.00 | $1,800.00 |
| 79 | Construction layout stakes and surveying (623E10000) | LS | 1 | $25,000 | $10,000 | $14,500 | $32,527 | $15,000 |
| 80 | Mobilization (624E10000) | LS | 1 | $56,000 | $30,000 | $100,000 | $119,542 | $100,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 22, 2025. Compiled by Mirage Metrics.