ODOT contract 250282 bid tabulation
PIK-SR 124-14.96 (MINOR RECONSTRUCTION). Let by Ohio DOT on May 22, 2025, PIK. 4 bids received; low bid $1,944,512 by Allard Excavation LLC, -30% against the engineer's estimate of $2,770,000.
- Owner
- Ohio DOT
- Letting
- 22 MAY 2025
- Pay items
- 85
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Allard Excavation LLC | $1,944,512 | Low | -30% |
| 2 | Fillmore Construction | $1,978,551 | +2.0% | -29% |
| 3 | Shelly & Sands Inc | $2,691,938 | +38% | -3.0% |
| 4 | Axis Civil Construction LLC | $2,873,151 | +48% | +4.0% |
Engineer's estimate: $2,770,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Allard Excavation LLC | 2. Fillmore Construction | 3. Shelly & Sands Inc | 4. Axis Civil Construction LLC |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $30,000 | $10,000 | $60,000 | $20,000 |
| 2 | Pavement removed (202E23000) | SY | 4,434 | $6.00 | $5.00 | $6.50 | $13.00 |
| 3 | Pipe removed, 24" and under (202E35100) | FT | 156 | $10.00 | $10.00 | $28.00 | $25.00 |
| 4 | Guardrail removed (202E38000) | FT | 341 | $4.00 | $3.50 | $3.50 | $5.00 |
| 5 | Fence removed (202E75000) | FT | 183 | $2.00 | $10.00 | $5.00 | $5.00 |
| 6 | Excavation (203E10000) | CY | 1,881 | $20.00 | $30.00 | $17.00 | $32.00 |
| 7 | Embankment (203E20000) | CY | 3,679 | $17.00 | $50.00 | $19.00 | $32.00 |
| 8 | Subgrade compaction (204E10000) | SY | 7,157 | $3.00 | $3.00 | $2.50 | $3.00 |
| 9 | Excavation of subgrade (204E13000) | CY | 3,644 | $14.00 | $20.00 | $30.00 | $32.00 |
| 10 | Embankment (204E20000) | CY | 6,331 | $13.00 | $30.00 | $25.50 | $55.00 |
| 11 | Granular material, type B (204E30010) | CY | 100 | $83.00 | $120.00 | $73.00 | $84.00 |
| 12 | Proof rolling (204E45000) | HR | 4 | $263.00 | $125.00 | $271.00 | $200.00 |
| 13 | Guardrail, type MGS with long posts (606E15100) | FT | 50 | $83.00 | $75.00 | $75.00 | $75.00 |
| 14 | Anchor assembly, MGS type E (MASH 2016) (606E26150) | EACH | 1 | $2,400.00 | $2,850.00 | $2,850.00 | $2,850.00 |
| 15 | Monument assembly, type C (623E38500) | EACH | 7 | $1,758.00 | $3,500.00 | $2,113.00 | $2,400.00 |
| 16 | Right-of-way monument, type B (623E40520) | EACH | 18 | $669.00 | $1,500.00 | $198.00 | $650.00 |
| 17 | Special - mailbox removed and reset (690E50350) | EACH | 1 | $120.00 | $200.00 | $200.00 | $200.00 |
| 18 | Rock channel protection, type B with geotextile fabric (601E32104) | CY | 44 | $87.00 | $200.00 | $112.00 | $80.00 |
| 19 | Topsoil (659E00300) | CY | 1,299 | $28.00 | $30.00 | $20.00 | $52.00 |
| 20 | Seeding and mulching (659E10000) | SY | 9,575 | $0.85 | $1.00 | $1.00 | $0.85 |
| 21 | Commercial fertilizer (659E20000) | TON | 1.29 | $1,250.00 | $1,400.00 | $1,250.00 | $1,250.00 |
| 22 | Lime (659E31000) | ACRE | 1.98 | $120.00 | $450.00 | $150.00 | $150.00 |
| 23 | Water (659E35000) | MGAL | 52 | $1.00 | $10.00 | $1.00 | $1.00 |
| 24 | Slope erosion protection (670E00500) | SY | 2,121 | $2.00 | $2.00 | $2.00 | $2.00 |
| 25 | Erosion control mat (671E14000) | SY | 283 | $3.00 | $2.00 | $2.50 | $2.50 |
| 26 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,011.00 | $5,000.00 | $2,750.00 | $2,500.00 |
| 27 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $9,828.00 | $10,000 | $7,000.00 | $17,500 |
| 28 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $9,755.00 | $10,000 | $9,000.00 | $8,000.00 |
| 29 | Erosion control (832E30000) | EACH | 49,521 | $1.00 | $1.00 | $1.00 | $1.00 |
| 30 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $88,500 | $10,000 | $635,425 | $750,000 |
| 31 | Unclassified excavation (503E21100) | CY | 117 | $38.00 | $140.00 | $51.00 | $75.00 |
| 32 | Epoxy coated steel reinforcement (509E10000) | LB | 3,103 | $3.00 | $2.50 | $4.00 | $4.00 |
| 33 | Class QC1 concrete, retaining/wingwall not including footing (511E46010) | CY | 8 | $2,491.00 | $1,500.00 | $5,600.00 | $2,750.00 |
| 34 | Class QC1 concrete, footing (511E46510) | CY | 23 | $1,664.00 | $1,000.00 | $1,500.00 | $670.00 |
| 35 | Class QC1 concrete, headwall (511E46610) | CY | 1 | $1,204.00 | $2,000.00 | $3,025.00 | $1,700.00 |
| 36 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 30 | $40.00 | $80.00 | $86.00 | $75.00 |
| 37 | Type 2 waterproofing (512E33000) | SY | 199 | $60.00 | $30.00 | $28.00 | $25.00 |
| 38 | 1" preformed expansion joint filler (516E13600) | SF | 26 | $3.00 | $10.00 | $2.00 | $10.00 |
| 39 | Porous backfill with geotextile fabric (518E21200) | CY | 6 | $142.00 | $140.00 | $450.00 | $280.00 |
| 40 | Concrete masonry (602E20000) | CY | 3.10 | $3,279.00 | $2,000.00 | $2,700.00 | $3,400.00 |
| 41 | Aggregate drains (605E31100) | FT | 549 | $23.00 | $10.00 | $14.00 | $20.00 |
| 42 | 6" conduit, type E (611E01400) | FT | 50 | $54.00 | $50.00 | $23.00 | $20.00 |
| 43 | 6" conduit, type F (611E01500) | FT | 50 | $54.00 | $60.00 | $23.00 | $20.00 |
| 44 | 12" conduit, type D (611E04900) | FT | 30 | $99.00 | $80.00 | $90.00 | $50.00 |
| 45 | 18" conduit, type D (611E07900) | FT | 59 | $110.00 | $140.00 | $79.00 | $50.00 |
| 46 | 24" conduit, type C (611E10600) | FT | 60 | $124.00 | $200.00 | $151.00 | $75.00 |
| 47 | 48" conduit, type A (see sheet for allow (611E20700) | FT | 86 | $323.00 | $500.00 | $405.00 | $265.00 |
| 48 | 8' X 4' conduit, type A, 706.05 (611E94800) | FT | 86 | $1,700.00 | $1,800.00 | $1,478.00 | $1,450.00 |
| 49 | Pavement planing, asphalt concrete (1.5") (254E01000) | SY | 255 | $30.00 | $10.00 | $29.50 | $30.00 |
| 50 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 1,615 | $177.00 | $192.00 | $160.00 | $177.00 |
| 51 | Aggregate base (304E20000) | CY | 1,205 | $61.00 | $68.00 | $73.00 | $64.00 |
| 52 | Tack coat (407E10000) | GAL | 1,132 | $2.50 | $3.00 | $3.50 | $2.50 |
| 53 | Traffic compacted surface, type A or B (410E12000) | CY | 25 | $56.00 | $100.00 | $120.00 | $85.00 |
| 54 | Traffic compacted surface, type C (410E13000) | CY | 15 | $57.00 | $120.00 | $125.00 | $85.00 |
| 55 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 531 | $215.00 | $224.00 | $205.00 | $215.00 |
| 56 | RPM (621E00100) | EACH | 19 | $200.00 | $200.00 | $200.00 | $200.00 |
| 57 | Raised pavement marker removed (621E54000) | EACH | 19 | $12.00 | $10.00 | $14.00 | $40.00 |
| 58 | Barrier reflector, type 3 (BI-directional) (626E00112) | EACH | 2 | $15.00 | $15.00 | $15.00 | $15.00 |
| 59 | Ground mounted support, no. 2 post (630E02100) | FT | 8.50 | $14.00 | $25.00 | $25.00 | $25.00 |
| 60 | Ground mounted support, no. 3 post (630E03100) | FT | 12 | $15.00 | $28.00 | $28.00 | $28.00 |
| 61 | Sign, flat sheet (630E80100) | SF | 10 | $30.00 | $30.00 | $30.00 | $30.00 |
| 62 | Removal of ground mounted sign and disposal (630E84900) | EACH | 10 | $30.00 | $25.00 | $25.00 | $25.00 |
| 63 | Removal of ground mounted sign and reerection (630E85100) | EACH | 1 | $60.00 | $175.00 | $175.00 | $175.00 |
| 64 | Removal of ground mounted post support and disposal (630E86002) | EACH | 10 | $30.00 | $25.00 | $25.00 | $25.00 |
| 65 | Edge line, 6", type 1 (642E00104) | MI | 0.60 | $1,975.00 | $1,975.00 | $1,975.00 | $1,975.00 |
| 66 | Center line, type 1 (642E00300) | MI | 0.29 | $3,525.00 | $3,525.00 | $3,525.00 | $3,525.00 |
| 67 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 16 | $85.00 | $100.00 | $120.00 | $70.00 |
| 68 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 10 | $2,008.00 | $2,008.00 | $2,400.00 | $2,100.00 |
| 69 | Barrier reflector, type 1 (BI-directional) (614E13310) | EACH | 73 | $30.00 | $30.00 | $9.00 | $12.00 |
| 70 | Barrier reflector, type 3 (BI-directional) (614E13314) | EACH | 5 | $50.00 | $50.00 | $25.00 | $18.00 |
| 71 | Object marker, two way (614E13360) | EACH | 78 | $32.00 | $32.00 | $18.00 | $18.00 |
| 72 | Work zone edge line, class I, 6", 740.06, type I (614E22210) | MI | 1.36 | $10,125 | $10,125 | $10,125 | $10,125 |
| 73 | Work zone stop line, class I, 740.06, type I (614E26400) | FT | 24 | $14.00 | $14.00 | $14.00 | $14.00 |
| 74 | Roads for maintaining traffic (615E10000) | LS | 1 | $6,853.00 | $5,000.00 | $10,000 | $2,500.00 |
| 75 | Pavement for maintaining traffic, class A (615E20000) | SY | 145 | $147.00 | $165.00 | $125.00 | $100.00 |
| 76 | Water (616E10000) | MGAL | 52 | $1.00 | $10.00 | $45.00 | $1.00 |
| 77 | Portable barrier, unanchored (622E41100) | FT | 1,790 | $23.00 | $22.35 | $6.00 | $22.50 |
| 78 | Portable barrier, anchored (622E41110) | FT | 1,630 | $27.00 | $26.72 | $41.00 | $27.00 |
| 79 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $14,000 | $25,000 | $20,000 | $20,000 |
| 80 | Maintaining traffic (614E11000) | LS | 1 | $250,000 | $70,000 | $250,004 | $140,000 |
| 81 | Field office, type A (619E16000) | MNTH | 5 | $1,800.00 | $1,100.00 | $5,500.00 | $1,950.00 |
| 82 | Construction layout stakes and surveying (623E10000) | LS | 1 | $50,000 | $10,000 | $50,000 | $25,000 |
| 83 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $3,372.00 | $10,000 | $3,000.00 | $1,600.00 |
| 84 | Post construction survey monument verification and report (623E51000) | LS | 1 | $3,011.00 | $10,000 | $3,000.00 | $1,600.00 |
| 85 | Mobilization (624E10000) | LS | 1 | $90,000 | $75,000 | $130,000 | $80,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 22, 2025. Compiled by Mirage Metrics.