ODOT contract 254017 bid tabulation
WAY-US 250-27.50 (Culvert Replacement). Let by Ohio DOT on May 22, 2025, WAY. 3 bids received; low bid $210,450 by Crawford Construction Company Inc, +24% against the engineer's estimate of $170,000.
- Owner
- Ohio DOT
- Letting
- 22 MAY 2025
- Pay items
- 33
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Crawford Construction Company Inc | $210,450 | Low | +24% |
| 2 | Craig Edward Susany Inc | $298,128 | +42% | +75% |
| 3 | Madex Construction Co | $352,875 | +68% | +108% |
Engineer's estimate: $170,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Crawford Construction Company Inc | 2. Craig Edward Susany Inc | 3. Madex Construction Co |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $2,300.00 | $100.00 | $2,781.27 |
| 2 | Headwall removed (202E20010) | EACH | 2 | $1,500.00 | $1,000.00 | $1,890.93 |
| 3 | Pipe removed, over 24" diameter (202E35200) | FT | 16 | $112.00 | $200.00 | $395.22 |
| 4 | Guardrail removed for reuse, as per plan (202E38201) | FT | 100 | $33.00 | $200.00 | $60.04 |
| 5 | Special - fill and plug existing conduit (202E70000) | FT | 77 | $230.00 | $190.00 | $245.55 |
| 6 | Fence removed (202E75000) | FT | 109 | $11.00 | $10.00 | $17.37 |
| 7 | Removal misc.: fence post (202E98100) | EACH | 1 | $120.00 | $100.00 | $578.95 |
| 8 | Excavation (203E10000) | CY | 8 | $185.00 | $100.00 | $57.89 |
| 9 | Embankment (203E20000) | CY | 44 | $100.00 | $100.00 | $90.15 |
| 10 | Monument assembly, type C (623E38500) | EACH | 2 | $1,800.00 | $2,000.00 | $2,227.19 |
| 11 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $851.00 | $7,500.00 | $2,894.74 |
| 12 | Post construction survey monument verification and report (623E51000) | LS | 1 | $851.00 | $2,500.00 | $2,894.74 |
| 13 | Riprap, type D (601E11000) | SY | 4 | $980.00 | $500.00 | $953.44 |
| 14 | Rock channel protection, type B with filter (601E32100) | CY | 4 | $430.00 | $400.00 | $291.47 |
| 15 | Soil analysis test (659E00100) | EACH | 2 | $175.00 | $25.00 | $289.47 |
| 16 | Topsoil (659E00300) | CY | 20 | $111.00 | $100.00 | $92.63 |
| 17 | Seeding and mulching (659E10000) | SY | 182 | $12.40 | $9.00 | $17.37 |
| 18 | Repair seeding and mulching (659E14000) | SY | 9 | $1.00 | $9.00 | $17.37 |
| 19 | Inter-seeding (659E15000) | SY | 9 | $1.00 | $6.00 | $17.37 |
| 20 | Commercial fertilizer (659E20000) | TON | 0.02 | $1,200.00 | $1,000.00 | $5,789.50 |
| 21 | Lime (659E31000) | ACRE | 0.04 | $440.00 | $600.00 | $1,158.00 |
| 22 | Water (659E35000) | MGAL | 0.98 | $12.00 | $1.00 | $75.26 |
| 23 | Slope erosion protection mat, type C (670E00530) | SY | 154 | $26.00 | $10.00 | $9.26 |
| 24 | Erosion control (832E30000) | EACH | 3,000 | $1.00 | $1.00 | $1.00 |
| 25 | Conduit, bored or jacked, 30", 748.06 (0.500) (611E96600) | FT | 104 | $955.00 | $1,100.00 | $2,101.26 |
| 26 | Aggregate base (304E20000) | CY | 2 | $840.00 | $200.00 | $335.79 |
| 27 | Portable changeable message sign, as per plan (614E18601) | SNMT | 2 | $1,800.00 | $1,000.00 | $1,621.05 |
| 28 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $7,000.00 | $50,000 | $6,739.20 |
| 29 | Concrete masonry (602E20000) | CY | 1.20 | $5,400.00 | $5,000.00 | $5,370.35 |
| 30 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $3,025.00 | $11,000 | $11,989 |
| 31 | Maintaining traffic (614E11000) | LS | 1 | $8,700.00 | $25,000 | $12,190 |
| 32 | Construction layout stakes and surveying (623E10000) | LS | 1 | $3,000.00 | $7,000.00 | $3,194.74 |
| 33 | Mobilization (624E10000) | LS | 1 | $19,500 | $10,000 | $19,382 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 22, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.