HAM-SR 264-10.42 (RELOCATION). Let by Ohio DOT on May 22, 2025, HAM. 5 bids received; low bid $2,212,186 by KT Holden Construction LLC, -14% against the engineer's estimate of $2,577,000.

Owner
Ohio DOT
Letting
22 MAY 2025
Pay items
111
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1KT Holden Construction LLC$2,212,186Low-14%
2Great Lakes Construction Co$2,294,651+4.0%-11%
3Eagle Bridge Co$2,305,951+4.0%-11%
4Sunesis Construction Co$2,591,780+17%+1.0%
5John R Jurgensen Company$2,845,185+29%+10%
ODOT contract 250277: bids by rank

Engineer's estimate: $2,577,000.

Bid tabulation

LinePay itemUnitQuantity1. KT Holden Construction LLC2. Great Lakes Construction Co3. Eagle Bridge Co4. Sunesis Construction Co5. John R Jurgensen Company
1Clearing and grubbing (201E11000)LS1$15,000$10,000$12,500$6,730.05$7,368.75
2Headwall removed (202E20010)EACH2$800.00$235.00$1,000.00$302.31$1,425.15
3Pavement removed (202E23000)SY53$73.50$55.00$85.00$63.20$78.86
4Walk removed (202E30000)SF377$4.75$3.25$4.00$4.52$8.68
5Curb removed (202E32000)FT158$11.00$3.75$10.00$9.29$16.02
6Pipe removed, 24" and under (202E35100)FT56$38.00$23.50$20.00$28.75$49.63
7Pipe removed, over 24" diameter (202E35200)FT58$39.00$40.50$30.00$37.01$52.57
8Guardrail removed (202E38000)FT301$2.00$2.00$2.00$7.50$7.50
9Anchor assembly removed, type T (202E42040)EACH2$160.00$160.00$160.00$150.00$150.00
10Bridge terminal assembly removed (202E47000)EACH4$140.00$140.00$140.00$200.00$200.00
11Catch basin removed (202E58100)EACH4$660.00$300.00$325.00$604.63$1,147.22
12Fence removed (202E75000)FT136$4.50$4.50$10.00$10.00$10.00
13Removal misc.: rock channel protection (202E98000)LS1$1,500.00$1,700.00$1,500.00$3,060.00$2,779.38
14Excavation (203E10000)CY271$29.00$27.00$23.00$21.90$35.13
15Embankment (203E20000)CY3,885$30.00$24.00$35.00$41.13$45.07
16Embankment, as per plan (203E20001)CY6,524$48.70$80.00$67.00$122.80$53.52
17Subgrade compaction (204E10000)SY1,435$2.50$4.25$5.00$4.02$3.18
18Excavation of subgrade (204E13000)CY180$50.00$55.00$16.00$39.42$62.07
19Granular material, type C (204E30020)CY558$75.00$80.00$90.00$85.27$95.76
20Proof rolling (204E45000)HR1$320.00$300.00$150.00$395.98$248.26
21Geotextile fabric (204E50000)SY1,435$1.10$1.90$2.00$2.96$2.38
22Guardrail, type MGS with long posts (606E15100)FT288$33.40$33.40$33.40$33.00$33.00
235" concrete walk (608E12000)SF2,166$11.00$12.50$12.00$15.20$13.75
24Monument assembly, type C (623E38500)EACH5$2,000.00$1,900.00$1,750.00$1,294.05$1,492.57
25Special - consultant for concrete quality control (690E98400)LS1$6,480.00$6,500.00$7,500.00$740.00$10,582
26Inspection and compaction testing of unbound materials (878E25000)LS1$21,811$46,500$70,000$46,158$52,454
27Water (616E10000)MGAL41$22.50$50.00$20.00$4.07$47.54
28Topsoil (659E00300)CY109$62.50$75.00$65.00$68.41$40.66
29Seeding and mulching (659E10000)SY980$5.00$5.00$5.00$3.64$3.65
30Repair seeding and mulching (659E14000)SY49$1.00$1.00$3.00$0.28$3.65
31Commercial fertilizer (659E20000)TON0.13$1,500.00$1,500.00$1,750.00$1,400.00$1,000.00
32Lime (659E31000)ACRE0.20$200.00$200.00$10.00$200.00$100.00
33Water (659E35000)MGAL5.40$1.00$1.00$15.00$1.39$10.00
34Erosion control (832E30000)EACH10,000$1.00$1.00$1.00$1.00$1.00
35Paved gutter, type 1-2 (601E37500)FT113$100.00$72.00$100.00$65.00$74.87
36Paved gutter, type 1-2, as per plan (601E37501)FT35$97.00$88.00$100.00$75.00$88.34
374" base pipe underdrains (605E06000)FT285$12.00$15.00$25.00$18.93$30.27
384" conduit, type F for underdrain outlet (611E00410)FT40$37.00$18.00$20.00$29.36$30.23
3912" conduit, type B (611E04400)FT108$175.00$160.00$115.00$111.01$113.71
43Catch basin, no. 3A (611E98180)EACH5$3,700.00$5,400.00$3,750.00$2,840.25$2,429.10
44Catch basin, no. 2-2B (611E98470)EACH2$1,890.00$3,550.00$2,150.00$1,765.40$1,829.21
45Catch basin, no. 2-4 (611E98540)EACH1$18,500$15,000$17,500$15,853$8,747.65
46Catch basin grate (611E98644)EACH1$400.00$525.00$400.00$821.74$471.02
47Manhole, no. 3 (611E99574)EACH2$9,425.00$11,250$8,750.00$6,656.55$11,091
48Asphalt concrete base, PG64-22, (449) (301E56000)CY320$261.84$298.00$298.00$255.00$320.00
49Aggregate base (304E20000)CY234$103.00$110.00$110.00$123.94$122.09
50Non-tracking tack coat (407E20000)GAL254$10.27$3.00$3.00$10.00$5.50
51Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000)CY61$492.87$410.00$410.00$480.00$545.00
52Asphalt concrete intermediate course, type 2, (448) (441E50300)CY67$462.07$370.00$370.00$450.00$560.00
53Curb, type 6 (609E26000)FT591$34.00$48.00$37.00$33.02$33.86
54RPM (621E00100)EACH47$88.80$88.80$88.80$81.96$88.80
55Raised pavement marker removed (621E54000)EACH47$18.00$12.50$15.00$81.96$27.06
56Light pole removed (625E75400)EACH1$11,000$8,750.00$8,750.00$34,571$8,750.00
57Barrier reflector, type 2, (one-way) (626E00110)EACH3$15.60$15.60$15.60$15.00$15.00
58Lane line, 4" (644E00200)MI0.27$2,145.00$2,145.00$2,145.00$4,166.00$2,145.00
59Center line (644E00300)MI0.17$10,420$10,420$10,420$16,000$10,420
60Channelizing line, 8" (644E00400)FT227$2.40$2.40$2.40$2.50$2.40
61Stop line (644E00500)FT110$15.40$15.40$15.40$7.00$15.40
62Lane arrow (644E01300)EACH2$150.00$150.00$150.00$200.00$150.00
63Dotted line, 4" (644E01500)FT228$1.30$1.30$1.30$2.00$1.30
64Dotted line, 4", as per plan (644E01501)FT91$1.55$1.55$1.55$4.00$1.55
65Law enforcement officer with patrol car for assistance (614E11110)HR160$80.00$104.70$135.00$110.00$120.90
66Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384)EACH8$1,897.96$1,897.96$1,898.00$1,897.96$1,897.96
67Barrier reflector, type 1, (BI-directional) (614E13310)EACH23$11.64$11.64$12.00$11.64$11.64
68Object marker, one way (614E13350)EACH23$20.23$20.23$20.00$20.23$20.23
69Work zone lane line, class III, 4", 642 paint (614E20550)MI0.27$2,175.00$2,175.00$2,175.00$2,500.00$2,175.00
70Work zone center line, class I, 740.06, type I (614E21200)MI0.29$12,377$12,377$12,377$34,145$12,377
71Work zone center line, class III, 642 paint (614E21550)MI0.17$3,780.00$3,780.00$3,780.00$7,500.00$3,780.00
72Work zone edge line, class I, 4", 740.06, type I (614E22200)MI0.69$8,697.58$8,697.58$8,697.58$17,060$8,697.58
73Work zone channelizing line, class I, 12" (614E23010)FT377$2.87$2.87$2.87$1.00$2.87
74Work zone channelizing line, class III, 12", 642 paint (614E23690)FT120$0.95$0.95$0.95$2.00$0.95
75Work zone dotted line, class I, 4", 740.06, type I (614E24400)FT980$1.23$1.23$1.23$1.10$1.23
76Work zone dotted line, class III, 4", 642 paint (614E24610)FT319$0.85$0.85$0.85$1.00$0.85
77Work zone stop line, class I, 740.06, type I (614E26400)FT44$6.38$6.38$6.38$10.30$6.38
78Work zone stop line, class III, 642 paint (614E26610)FT110$4.50$4.50$4.50$3.00$4.50
79Pavement for maintaining traffic, class B (615E25000)SY255$190.00$110.00$120.00$176.82$120.00
80Portable barrier, unanchored (622E41100)FT413$27.00$22.50$34.00$27.05$27.15
81Cofferdams and excavation bracing (503E11100)LS1$1.00$15,000$1.00$341.02$12,994
82Special - misc.: work invloving asbestos containin (690E98400)LS1$420.00$250.00$150.00$500.00$4,800.00
84Sealing of concrete surfaces (epoxy-urethane), as per plan (512E10101)SY444$25.00$25.00$25.00$28.00$28.00
85Vandal protection fence, 6' straight, coated fabric (607E39900)FT159$132.00$136.00$132.00$193.00$193.00
86Mechanically stabilized earth wall, as per plan (840E20001)SF3,988$71.00$50.00$60.00$69.02$71.99
87Wall excavation (840E21000)CY652$26.00$32.00$20.00$26.54$49.52
88Foundation preparation, as per plan (840E22001)SY336$54.00$60.00$65.00$81.76$66.71
896" drainage pipe, perforated (840E25010)FT323$9.60$9.00$12.00$6.48$41.85
906" drainage pipe, non-perforated (840E25020)FT2.50$142.00$100.00$25.00$115.36$255.51
91Concrete coping (840E26000)FT159$240.00$275.00$230.00$239.73$561.79
92Aesthetic surface treatment (840E26050)SF3,988$1.00$10.25$3.00$0.02$1.34
93On-site assistance (840E27000)DAY5$1,000.00$250.00$750.00$1,226.53$537.34
94Temporary wire faced mechanically stabilized earth wall, as per plan (867E00101)LS1$102,515$90,000$80,000$125,871$95,384
95Portions of structure removed, over 20 foot span, as per plan (202E11203)LS1$182,250$150,000$210,000$146,311$375,000
96Approach slab removed (202E22900)SY396$88.00$70.00$45.00$43.40$140.00
97Wearing course removed (202E23500)SY396$6.40$12.00$20.00$6.23$25.00
98Bridge railing removed, as per plan (202E38501)FT286$39.00$12.00$25.00$13.93$25.00
99Cofferdams and excavation bracing, as per plan (503E11101)LS1$57,100$11,000$25,000$13,785$55,000
100Unclassified excavation (503E21300)LS1$46,100$7,500.00$30,000$18,205$15,000
101Sealing of concrete surfaces (non-epoxy) (512E10050)SY355$15.00$15.00$15.00$12.00$12.00
102Removal of existing coatings from concrete surfaces (512E74000)SY71$36.50$36.50$36.50$30.00$30.00
1031/2" preformed expansion joint filler (516E13200)SF8$9.00$15.00$7.00$7.30$40.00
105Premium for contract performance bond and for payment bond (103E05000)LS1$30,960$20,000$25,000$14,077$21,334
106Maintaining traffic (614E11000)LS1$69,250$121,000$75,000$15,251$249,802
107Construction layout stakes and surveying (623E10000)LS1$10,300$20,000$20,000$10,800$10,332
108Mobilization (624E10000)LS1$108,385$114,000$110,000$86,293$140,000
20012" conduit, type B (611E04400)FT105$128.00$160.00$140.00$111.29$129.26
20136" conduit, type B (611E16400)FT4$2,700.00$1,300.00$1,000.00$2,451.44$1,676.58
20236" conduit, type B (611E16400)FT6$1,230.00$1,000.00$850.00$770.08$923.51
20336" conduit, type B (611E16400)FT65$332.00$340.00$350.00$648.57$407.24
204Roads for maintaining traffic (615E10000)LS1$8,400.00$2,000.00$15,000$4,068.63$6,058.78
205Special - settlement platform (203E65000)EACH3$2,970.00$1,750.00$2,000.00$1,552.30$3,185.98
206Portable barrier, anchored (622E41110)FT798$30.00$35.00$35.00$30.42$29.25
300Sealing of concrete surfaces, as per plan (512E10001)SY444$25.00$25.00$25.00$20.00$20.00
ODOT contract 250277: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of May 22, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy