ODOT contract 250279 bid tabulation
JAC-SR 139/SR 776/SR 788-11.35/00.00/02.36 (TWO LANE RESURFACING). Let by Ohio DOT on May 22, 2025, JAC. 2 bids received; low bid $1,885,831 by Shelly & Sands Inc, -8.9% against the engineer's estimate of $2,071,000.
- Owner
- Ohio DOT
- Letting
- 22 MAY 2025
- Pay items
- 31
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly & Sands Inc | $1,885,831 | Low | -9.0% |
| 2 | Fillmore Construction | $2,078,076 | +10% | 0.0% |
Engineer's estimate: $2,071,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly & Sands Inc | 2. Fillmore Construction |
|---|---|---|---|---|---|
| 1 | Linear grading (209E60500) | MI | 1.94 | $4,650.00 | $7,000.00 |
| 2 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 |
| 3 | Partial depth pavement repair (441), as per plan (251E01001) | SY | 4,500 | $30.00 | $37.50 |
| 4 | Pavement planing, asphalt concrete, 1.5" (254E01000) | SY | 125,787 | $2.10 | $1.50 |
| 5 | Pavement planing, portland cement concrete, 1.5" (254E01010) | SY | 185 | $2.10 | $50.00 |
| 6 | Patching planed surface (254E01600) | SY | 25,199 | $3.15 | $2.50 |
| 7 | Tack coat, 702.13 (407E13900) | GAL | 13 | $3.50 | $3.00 |
| 8 | Non-tracking tack coat (407E20000) | GAL | 11,320 | $3.50 | $3.00 |
| 9 | Asphalt concrete surface course, type 1, (448), as per plan (441E50101) | CY | 5,249 | $190.00 | $204.00 |
| 10 | Compacted aggregate (617E10100) | CY | 188 | $135.00 | $100.00 |
| 11 | Rumble strips, transverse (asphalt concrete) (618E39000) | EACH | 18 | $285.00 | $1,000.00 |
| 12 | RPM (621E00100) | EACH | 855 | $32.00 | $34.00 |
| 13 | Raised pavement marker removed (621E54000) | EACH | 1,255 | $5.00 | $10.00 |
| 14 | Edge line, 6" (644E00104) | MI | 19.02 | $3,438.00 | $4,300.00 |
| 15 | Center line (644E00300) | MI | 9.51 | $4,260.00 | $5,236.00 |
| 16 | Stop line (644E00500) | FT | 27 | $11.95 | $20.00 |
| 17 | Crosswalk line, 12" (644E00620) | FT | 52 | $8.00 | $10.00 |
| 18 | Railroad symbol marking (644E01000) | EACH | 2 | $830.00 | $1,107.00 |
| 19 | Edge line, 6" (646E10010) | MI | 0.03 | $42,800 | $120,318 |
| 20 | Center line (646E10200) | MI | 0.02 | $65,800 | $160,424 |
| 21 | Work zone marking sign (614E12460) | EACH | 60 | $88.00 | $88.00 |
| 22 | Work zone center line, class III, 642 paint (614E21550) | MI | 19.12 | $985.00 | $1,175.00 |
| 23 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 38.24 | $835.00 | $925.00 |
| 24 | Work zone stop line, class III, 642 paint (614E26610) | FT | 54 | $9.50 | $9.50 |
| 25 | Joint sealer, as per plan (516E31001) | FT | 56 | $52.00 | $100.00 |
| 26 | Sawing and sealing asphalt concrete pavement joints (409E30000) | FT | 72 | $50.00 | $100.00 |
| 27 | Premium on railroads' protective public liability and property damage liability insurance (100E00300) | LS | 1 | $2,000.00 | $5,500.00 |
| 28 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $2,000.34 | $12,000 |
| 29 | Maintaining traffic (614E11000) | LS | 1 | $83,300 | $100,000 |
| 30 | Construction layout stakes and surveying (623E10000) | LS | 1 | $3,500.00 | $5,000.00 |
| 31 | Mobilization (624E10000) | LS | 1 | $31,000 | $110,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 22, 2025. Compiled by Mirage Metrics.