ODOT contract 250285 bid tabulation
SEN-SR 4/SR 18-07.52/15.39 Resurf (TWO LANE RESURFACING). Let by Ohio DOT on May 22, 2025, SEN. 4 bids received; low bid $3,740,212 by Kokosing Construction Company Inc, -13% against the engineer's estimate of $4,319,000.
- Owner
- Ohio DOT
- Letting
- 22 MAY 2025
- Pay items
- 61
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Kokosing Construction Company Inc | $3,740,212 | Low | -13% |
| 2 | M & B Asphalt Co Inc | $3,811,122 | +2.0% | -12% |
| 3 | Erie Blacktop Inc | $3,815,956 | +2.0% | -12% |
| 4 | Gerken Paving Inc | $3,968,977 | +6.0% | -8.0% |
Engineer's estimate: $4,319,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Kokosing Construction Company Inc | 2. M & B Asphalt Co Inc | 3. Erie Blacktop Inc | 4. Gerken Paving Inc |
|---|---|---|---|---|---|---|---|
| 1 | Pavement removed (202E23000) | SY | 10.40 | $225.00 | $50.00 | $330.00 | $385.00 |
| 2 | Guardrail removed (202E38000) | FT | 1,550 | $2.00 | $2.00 | $2.10 | $2.00 |
| 3 | Anchor assembly removed, type A (202E42000) | EACH | 10 | $295.00 | $295.00 | $310.00 | $295.00 |
| 4 | Anchor assembly removed, type E (202E42010) | EACH | 15 | $145.00 | $145.00 | $155.00 | $145.00 |
| 5 | Anchor assembly removed, type T (202E42040) | EACH | 2 | $95.00 | $95.00 | $100.00 | $95.00 |
| 6 | Reshaping under guardrail (209E15000) | STA | 37 | $30.00 | $30.00 | $31.50 | $30.00 |
| 7 | Linear grading (209E60500) | MI | 16 | $1,700.00 | $1,200.00 | $1,750.00 | $2,800.00 |
| 8 | Preparing subgrade for shoulder paving (209E72050) | MI | 16.48 | $215.00 | $1,000.00 | $1,800.00 | $340.00 |
| 9 | Guardrail, type MGS (606E15050) | FT | 1,250 | $19.20 | $19.20 | $20.00 | $19.20 |
| 10 | Anchor assembly, MGS type E, MASH 2016 (606E26150) | EACH | 25 | $2,380.00 | $2,380.00 | $2,500.00 | $2,380.00 |
| 11 | Anchor assembly, MGS type T (606E26550) | EACH | 2 | $1,365.00 | $1,365.00 | $1,435.00 | $1,365.00 |
| 12 | Monument assembly adjusted to grade (623E39500) | EACH | 1 | $1,900.00 | $1,800.00 | $1,300.00 | $1,110.00 |
| 13 | Seeding and mulching (659E10000) | SY | 355 | $6.50 | $6.50 | $6.85 | $6.50 |
| 14 | Commercial fertilizer (659E20000) | TON | 0.05 | $710.00 | $710.00 | $745.00 | $710.00 |
| 15 | Water (659E35000) | MGAL | 2 | $1.00 | $1.00 | $1.05 | $1.00 |
| 16 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 17 | Catch basin adjusted to grade (611E98630) | EACH | 1 | $1,100.00 | $1,250.00 | $1,200.00 | $1,800.00 |
| 18 | Catch basin reconstructed to grade (611E98634) | EACH | 1 | $2,000.00 | $1,500.00 | $2,100.00 | $2,300.00 |
| 19 | Inlet adjusted to grade (611E99150) | EACH | 1 | $1,150.00 | $1,250.00 | $1,400.00 | $2,250.00 |
| 20 | Inlet reconstructed to grade (611E99154) | EACH | 1 | $2,500.00 | $1,600.00 | $2,200.00 | $2,850.00 |
| 21 | Manhole adjusted to grade (611E99654) | EACH | 1 | $1,000.00 | $1,250.00 | $1,200.00 | $1,750.00 |
| 22 | Manhole reconstructed to grade (611E99660) | EACH | 1 | $1,500.00 | $1,600.00 | $2,200.00 | $2,250.00 |
| 23 | Pavement repair (253E02000) | CY | 3,635 | $200.00 | $190.00 | $180.00 | $206.00 |
| 24 | Pavement planing, asphalt concrete, 3" (254E01000) | SY | 40,164 | $0.91 | $3.00 | $1.75 | $3.80 |
| 25 | Pavement planing, asphalt concrete, 3.25" (254E01000) | SY | 84,690 | $1.20 | $3.40 | $1.40 | $3.30 |
| 26 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 5.20 | $800.00 | $500.00 | $800.00 | $750.00 |
| 27 | Tack coat (407E10000) | GAL | 17,582 | $2.75 | $2.50 | $2.55 | $2.25 |
| 28 | Fine graded polymer asphalt concrete, type B, (448), as per plan (424E14001) | CY | 1,175.60 | $250.00 | $245.00 | $268.00 | $240.00 |
| 29 | Asphalt concrete intermediate course, type 2, (446) (441E10200) | CY | 2,232 | $165.00 | $161.00 | $168.00 | $174.00 |
| 30 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 20 | $225.00 | $400.00 | $320.00 | $725.00 |
| 31 | Asphalt concrete surface course, 9.5 MM, type A (4 (442E00200) | CY | 3,643.30 | $205.00 | $200.00 | $222.00 | $195.00 |
| 32 | Asphalt concrete intermediate course, 12.5 MM, type A (446) (442E10080) | CY | 4,117 | $180.00 | $177.00 | $175.00 | $170.00 |
| 33 | Compacted aggregate (617E10100) | CY | 1,703 | $36.00 | $65.00 | $72.00 | $64.00 |
| 34 | Longitudinal joint adhesive (875E10000) | LB | 9,762 | $0.55 | $0.60 | $2.25 | $1.75 |
| 35 | Valve box adjusted to grade (638E10800) | EACH | 1 | $700.00 | $250.00 | $850.00 | $950.00 |
| 36 | RPM (621E00100) | EACH | 537 | $38.50 | $40.00 | $41.50 | $39.50 |
| 37 | Raised pavement marker removed (621E54000) | EACH | 103 | $3.00 | $7.00 | $8.00 | $7.00 |
| 38 | Barrier reflector, type 5, BI-directional (626E00116) | EACH | 45 | $12.00 | $12.00 | $12.60 | $12.00 |
| 39 | Removal of ground mounted sign and reerection (630E85100) | EACH | 8 | $75.00 | $265.00 | $78.00 | $265.00 |
| 40 | Edge line, 6", type 1 (642E00104) | MI | 16.52 | $800.00 | $900.00 | $840.00 | $900.00 |
| 41 | Center line, type 1 (642E00300) | MI | 8.26 | $800.00 | $850.00 | $840.00 | $850.00 |
| 42 | Stop line (644E00500) | FT | 13 | $15.00 | $25.00 | $15.75 | $20.00 |
| 43 | Railroad symbol marking (644E01000) | EACH | 1 | $550.00 | $1,000.00 | $575.00 | $1,000.00 |
| 44 | Speed measurement marking (644E40000) | EACH | 10 | $250.00 | $250.00 | $360.00 | $150.00 |
| 45 | Work zone marking sign (614E12460) | EACH | 18 | $85.00 | $130.00 | $89.00 | $115.00 |
| 46 | Replacement sign (614E12500) | EACH | 5 | $192.00 | $100.00 | $200.00 | $100.00 |
| 47 | Replacement drum (614E12600) | EACH | 5 | $56.00 | $50.00 | $59.00 | $65.00 |
| 48 | Work zone center line, class I (614E21000) | MI | 16.52 | $1,000.00 | $850.00 | $1,050.00 | $850.00 |
| 49 | Work zone center line, class III, 642 paint (614E21550) | MI | 8.26 | $850.00 | $850.00 | $895.00 | $850.00 |
| 50 | Pavement planing, asphalt concrete, 1.5" (254E01000) | SY | 98 | $1.20 | $6.00 | $2.55 | $6.00 |
| 51 | Special - sawing and sealing bituminous concrete joints (516E31200) | FT | 88 | $22.98 | $23.00 | $24.25 | $22.98 |
| 52 | Pavement planing, asphalt concrete, 1.5" (254E01000) | SY | 274 | $1.20 | $6.00 | $2.55 | $6.00 |
| 53 | Special - sawing and sealing bituminous concrete joints (516E31200) | FT | 150 | $22.98 | $23.00 | $24.25 | $22.98 |
| 54 | Pavement planing, asphalt concrete, 1" (254E01000) | SY | 419 | $0.91 | $6.00 | $2.80 | $6.00 |
| 55 | Special - sawing and sealing bituminous concrete joints (516E31200) | FT | 170 | $22.98 | $23.00 | $24.25 | $22.98 |
| 56 | Pavement planing, asphalt concrete, 1" (254E01000) | SY | 413 | $0.91 | $6.00 | $2.80 | $6.00 |
| 57 | Special - sawing and sealing bituminous concrete joints (516E31200) | FT | 176 | $22.98 | $23.00 | $24.25 | $22.98 |
| 58 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $15,000 | $20,000 | $20,000 | $17,500 |
| 59 | Maintaining traffic (614E11000) | LS | 1 | $202,500 | $60,000 | $75,000 | $122,000 |
| 60 | Construction layout stakes and surveying (623E10000) | LS | 1 | $2,500.00 | $6,000.00 | $12,500 | $12,075 |
| 61 | Mobilization (624E10000) | LS | 1 | $142,070 | $100,000 | $165,000 | $100,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 22, 2025. Compiled by Mirage Metrics.