ODOT contract 250299 bid tabulation
WAY-SR 3/SR 301-07.15/01.60 (CULVERT REPLACEMENT). Let by Ohio DOT on May 22, 2025, WAY. 2 bids received; low bid $523,203 by Eclipse Co LLC, -11% against the engineer's estimate of $585,000.
- Owner
- Ohio DOT
- Letting
- 22 MAY 2025
- Pay items
- 78
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Eclipse Co LLC | $523,203 | Low | -11% |
| 2 | Adena Corporation | $586,064 | +12% | 0.0% |
Engineer's estimate: $585,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Eclipse Co LLC | 2. Adena Corporation |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $10,453 | $11,625 |
| 2 | Pavement removed (202E23000) | SY | 297 | $17.00 | $13.23 |
| 3 | Pipe removed, 24" and under (202E35100) | FT | 110 | $20.50 | $1.65 |
| 4 | Guardrail removed (202E38000) | FT | 400 | $4.00 | $5.45 |
| 5 | Anchor assembly removed, type A (202E42000) | EACH | 3 | $208.00 | $90.91 |
| 6 | Anchor assembly removed, type T (202E42040) | EACH | 1 | $234.50 | $90.91 |
| 7 | Special - pipe cleanout, 24" and under (202E70110) | FT | 56 | $30.00 | $65.02 |
| 8 | Fence removed (202E75000) | FT | 105 | $7.50 | $1.00 |
| 9 | Removal misc.: concrete pad (202E98000) | LS | 1 | $482.00 | $379.97 |
| 10 | Removal misc.: boulder (202E98100) | EACH | 4 | $97.50 | $45.45 |
| 11 | Excavation (203E10000) | CY | 529 | $20.50 | $8.24 |
| 12 | Embankment (203E20000) | CY | 786 | $33.50 | $8.32 |
| 13 | Subgrade compaction (204E10000) | SY | 310 | $3.00 | $4.69 |
| 14 | Guardrail, type MGS with long posts (606E15100) | FT | 562.50 | $19.50 | $22.84 |
| 15 | Anchor assembly, MGS type E, MASH 2016 (606E26150) | EACH | 7 | $2,475.00 | $2,884.76 |
| 16 | Anchor assembly, MGS type T (606E26550) | EACH | 1 | $1,350.00 | $1,573.50 |
| 17 | Fence, misc.: temporary fencing (607E98000) | FT | 112 | $52.50 | $3.00 |
| 18 | Monument assembly, type C (623E38500) | EACH | 4 | $1,014.00 | $1,922.01 |
| 19 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $1,000.00 | $1,573.50 |
| 20 | Post construction survey monument verification and report (623E51000) | LS | 1 | $1,000.00 | $1,573.50 |
| 21 | Special - mailbox support system, double (690E50200) | EACH | 1 | $445.00 | $285.56 |
| 22 | Riprap, type D (601E11000) | SY | 15.20 | $201.00 | $420.52 |
| 23 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 32 | $95.50 | $73.28 |
| 24 | Rock channel protection, type A with filter (601E32000) | CY | 21 | $219.50 | $194.92 |
| 25 | Rock channel protection, type B with filter (601E32100) | CY | 4 | $137.00 | $182.99 |
| 26 | Commercial fertilizer (654E11000) | TON | 0.34 | $891.50 | $1,199.85 |
| 27 | Soil analysis test (659E00100) | EACH | 2 | $125.00 | $100.00 |
| 28 | Topsoil (659E00300) | CY | 272 | $60.50 | $22.89 |
| 29 | Seeding and mulching (659E10000) | SY | 2,453 | $2.50 | $2.43 |
| 30 | Repair seeding and mulching (659E14000) | SY | 123 | $1.00 | $1.00 |
| 31 | Inter-seeding (659E15000) | SY | 123 | $1.00 | $1.00 |
| 32 | Lime (659E31000) | ACRE | 0.51 | $155.51 | $411.37 |
| 33 | Water (659E35000) | MGAL | 13.58 | $1.00 | $1.00 |
| 34 | Slope erosion protection mat, type C (670E00530) | SY | 1,671 | $2.00 | $1.85 |
| 35 | Aggregate drains (605E31100) | FT | 40 | $39.00 | $9.26 |
| 36 | 12" conduit, type D (611E04900) | FT | 45 | $70.50 | $49.16 |
| 37 | 18" conduit, type C (611E07600) | FT | 95 | $88.00 | $67.24 |
| 38 | 24" conduit, type A (611E10200) | FT | 22 | $477.00 | $437.61 |
| 39 | 60" conduit, type A, 706.02, 707.33, 707.02 (0.168 (611E23600) | FT | 85 | $357.00 | $854.08 |
| 40 | Conduit, misc.: internal joint seal (611E97200) | EACH | 7 | $2,125.00 | $6,864.16 |
| 41 | Conduit, misc.: video log (611E97400) | FT | 56 | $10.00 | $23.47 |
| 42 | Catch basin, no. 5 (611E98300) | EACH | 1 | $5,202.50 | $4,354.54 |
| 43 | Pavement planing, asphalt concrete (3.0") (254E01000) | SY | 230 | $32.00 | $36.71 |
| 44 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 73 | $345.00 | $329.85 |
| 45 | Aggregate base (304E20000) | CY | 35 | $118.00 | $153.05 |
| 46 | Aggregate base (304E20000) | CY | 51 | $119.00 | $155.49 |
| 47 | Aggregate base (304E20000) | CY | 16 | $119.00 | $206.30 |
| 48 | Tack coat (407E10000) | GAL | 76 | $3.00 | $6.41 |
| 49 | Prime coat, as per plan (408E10001) | GAL | 140 | $5.00 | $19.81 |
| 50 | Asphalt concrete surface course, 9.5 MM, type A (4 (442E22001) | CY | 44 | $400.00 | $655.04 |
| 51 | Barrier reflector, type 2 (BI-directional) (614E13312) | EACH | 6 | $12.50 | $23.31 |
| 52 | RPM (621E00100) | EACH | 6 | $720.00 | $751.78 |
| 53 | Raised pavement marker removed (621E54000) | EACH | 6 | $20.50 | $10.00 |
| 54 | Edge line, 6", type 1 (642E00104) | MI | 0.29 | $11,220 | $7,601.48 |
| 55 | Center line, type 1 (642E00300) | MI | 0.15 | $14,960 | $13,981 |
| 56 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 4 | $2,202.00 | $2,885.93 |
| 57 | Detour signing (614E12420) | LS | 1 | $8,569.50 | $5,447.83 |
| 58 | Barrier reflector, type 1 (BI-directional) (614E13310) | EACH | 20 | $12.00 | $23.31 |
| 59 | Object marker, two way (614E13360) | EACH | 20 | $21.00 | $29.13 |
| 60 | Portable changeable message sign (614E18600) | SNMT | 4 | $1,141.50 | $1,517.56 |
| 61 | Work zone center line, class I, 740.06, type I (614E21200) | MI | 0.20 | $25,658 | $36,377 |
| 62 | Work zone edge line, class I, 6", 740.06, type I (614E22210) | MI | 0.20 | $12,829 | $21,042 |
| 63 | Work zone edge line, class I, 6", 740.06, type I (614E22210) | MI | 0.35 | $10,793 | $11,010 |
| 64 | Work zone stop line, class I, 740.06, type I (614E26400) | FT | 40 | $7.00 | $19.11 |
| 65 | Pavement for maintaining traffic, class B (615E25000) | SY | 217 | $110.00 | $120.49 |
| 66 | Portable barrier, unanchored (622E41100) | FT | 490 | $36.00 | $77.05 |
| 67 | Structure removed, as per plan (202E11001) | LS | 1 | $14,428 | $22,136 |
| 68 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $18,086 | $14,714 |
| 69 | Concrete masonry (602E20000) | CY | 4.57 | $1,678.50 | $2,067.40 |
| 70 | Structure removed, as per plan (202E11001) | LS | 1 | $1,678.50 | $14,570 |
| 71 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $16,116 | $14,714 |
| 72 | Concrete masonry (602E20000) | CY | 1.81 | $1,907.00 | $1,890.65 |
| 73 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $7,402.00 | $4,720.52 |
| 74 | Maintaining traffic (614E11000) | LS | 1 | $20,665 | $25,724 |
| 75 | Field office, type A (619E16000) | MNTH | 4 | $700.00 | $500.00 |
| 76 | Construction layout stakes and surveying (623E10000) | LS | 1 | $9,872.00 | $9,441.05 |
| 77 | Mobilization (624E10000) | LS | 1 | $55,129 | $14,516 |
| 100 | Erosion control (832E30000) | EACH | 500 | $1.00 | $1.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 22, 2025. Compiled by Mirage Metrics.