ODOT contract 260110 bid tabulation

PIC-US 23-18.52 (SPOT SAFETY). Let by Ohio DOT on February 19, 2026, PIC. 5 bids received; low bid $302,122 by Shelly & Sands Inc, +0.4% against the engineer's estimate of $301,000.

Owner
Ohio DOT
Letting
19 FEB 2026
Pay items
58
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Shelly & Sands Inc$302,122Low0.0%
2Strawser Paving Co Inc$350,475+16%+16%
3Shelly Company$350,809+16%+17%
4Axis Civil Construction LLC$392,118+30%+30%
5Fillmore Construction$449,864+49%+49%
ODOT contract 260110: bids by rank

Engineer's estimate: $301,000.

Bid tabulation

LinePay itemUnitQuantity1. Shelly & Sands Inc2. Strawser Paving Co Inc3. Shelly Company4. Axis Civil Construction LLC5. Fillmore Construction
1Clearing and grubbing (201E11000)LS1$5,000.00$500.00$13,500$10,000$3,500.00
2Pavement removed (202E23000)SY278$26.00$33.00$40.00$60.00$20.00
3Excavation (203E10000)CY633$35.00$104.00$61.75$52.00$38.00
4Embankment (203E20000)CY172$25.00$30.00$40.75$52.00$54.00
5Subgrade compaction (204E10000)SY1,026$6.00$2.50$1.60$4.00$5.00
6Proof rolling (204E45000)HR1$300.00$225.00$260.00$300.00$250.00
7Tied concrete block mat with type 1 underlayment (601E21050)SY8$150.00$190.00$245.00$300.00$200.00
8Rock channel protection, type C with filter (601E32200)CY5$240.00$220.00$475.00$275.00$500.00
9Topsoil (659E00300)CY183$25.00$37.00$90.00$70.00$50.00
10Seeding and mulching (659E10000)SY1,641$1.95$1.95$2.45$1.95$3.00
11Repair seeding and mulching (659E14000)SY83$1.95$1.95$2.00$1.95$5.00
12Inter-seeding (659E15000)SY83$1.95$1.95$0.75$1.95$5.00
13Commercial fertilizer (659E20000)TON0.23$1,250.00$1,250.00$800.00$1,250.00$1,400.00
14Lime (659E31000)ACRE0.34$150.00$150.00$1.00$150.00$1,400.00
15Water (659E35000)MGAL5$1.00$1.00$0.50$1.00$10.00
166" unclassified pipe underdrains (605E13300)FT234$25.00$25.00$19.00$22.50$30.00
176" base pipe underdrains (605E14000)FT357$27.50$25.00$19.00$18.00$30.00
18Aggregate drains (605E31100)FT50$30.00$20.00$14.00$15.00$100.00
196" conduit, type F for underdrain outlets (611E00510)FT30$30.00$32.00$95.00$26.00$50.00
206" conduit, type B (611E00900)FT25$20.00$20.00$30.00$55.00$50.00
216" conduit, type E (611E01400)FT50$20.00$20.00$30.00$20.00$30.00
226" conduit, type F (611E01500)FT50$20.00$20.00$30.00$18.00$40.00
23Precast reinforced concrete outlet (611E99710)EACH4$650.00$150.00$445.00$600.00$500.00
24Asphalt concrete base, PG64-22, (449) (301E56000)CY244$195.00$205.00$221.50$240.00$214.00
25Aggregate base (304E20000)CY170$95.00$120.00$101.50$150.00$100.00
26Non-tracking tack coat (407E20000)GAL156$3.50$4.40$4.10$4.50$5.00
27Asphalt concrete surface course, 12.5 MM, type A (449) (442E22100)CY40$325.00$340.00$315.00$450.00$400.00
28Asphalt concrete intermediate course, 19 MM, type A (449) (442E22400)CY46$285.00$320.00$290.00$360.00$380.00
29Rumble strips, shoulder (asphalt concrete) (618E40100)FT357$11.00$12.00$11.00$16.50$30.00
30Remove and reerect existing light pole, as per plan (625E35011)EACH1$15,000$15,000$15,000$15,000$10,000
31Ground mounted support, no. 2 post (630E02100)FT41.50$25.00$25.00$25.00$22.50$23.95
32Sign post reflector (630E08600)EACH2$50.00$50.00$50.00$120.00$75.56
33Sign support assembly, pole mounted (630E79500)EACH1$200.00$200.00$200.00$180.00$153.56
34Sign, flat sheet (630E80100)SF10$28.00$28.00$28.00$36.00$27.94
35Removal of ground mounted sign and disposal (630E84900)EACH2$25.00$25.00$25.00$45.00$16.56
36Removal of ground mounted sign and reerection (630E85100)EACH4$150.00$150.00$150.00$135.00$84.87
37Removal of ground mounted post support and disposal (630E86002)EACH8$25.00$25.00$25.00$45.00$22.08
38Removal of ground mounted pipe support and disposal (630E86272)EACH1$400.00$400.00$400.00$135.00$100.00
39Edge line, 6" (644E00104)MI0.07$9,630.00$9,630.00$9,630.00$9,630.00$20,000
40Channelizing line, 12" (644E00404)FT287$3.35$3.35$3.35$3.35$10.00
41Lane arrow (644E01300)EACH3$120.00$120.00$120.00$120.00$175.00
42ITS device, misc.:, vehicle detector assembly (809E65990)EACH1$16,000$16,000$16,000$16,000$5,000.00
43Law enforcement officer with patrol car for assistance (614E11110)HR80$85.00$91.00$82.00$80.00$150.00
44Increased barrier delineation (614E11630)FT500$1.00$2.00$1.75$2.50$2.06
45Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380)EACH2$2,200.00$2,285.00$2,200.00$1,500.00$2,017.42
46Barrier reflector, type 1, one-way (614E13310)EACH10$12.00$12.00$32.00$8.00$12.73
47Object marker, one way (614E13350)EACH2$24.00$20.00$50.00$40.00$20.23
48Work zone edge line, class I, 4", 642 paint (614E22100)MI0.48$2,550.00$1,275.00$2,550.00$1,275.00$3,300.00
49Water (616E10000)MGAL1$500.00$100.00$1.00$1.00$10.00
50Portable barrier, unanchored (622E41100)FT850$28.00$36.00$32.00$15.00$36.73
51Premium for contract performance bond and for payment bond (103E05000)LS1$2,985.60$7,500.00$3,500.00$2,500.00$10,000
52Maintaining traffic (614E11000)LS1$15,550$17,500$15,000$40,000$84,400
53Field office, type A (619E16000)MNTH4$3,000.00$1,500.00$2,000.00$2,800.00$1,500.00
54Construction layout stakes and surveying (623E10000)LS1$11,000$5,000.00$7,500.00$9,500.00$7,500.00
55Mobilization (624E10000)LS1$10,000$10,000$13,000$25,000$50,000
100Pipe removed, 24" and under (202E35100)FT80$15.00$17.00$57.75$45.00$30.00
101Ground mounted support, no. 6 post (630E06100)FT68$30.00$30.00$30.00$32.00$32.00
102Removal of pavement marking (644E30000)FT63$10.00$10.00$10.00$10.00$40.00
ODOT contract 260110: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of February 19, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy