ODOT contract 250361 bid tabulation
MAD-US 42/CR 40/West Ave-Sidewalks (SIDEWALK). Let by Ohio DOT on July 31, 2025, MAD. 4 bids received; low bid $365,885 by Cap-Stone & Associates Inc, +9.5% against the engineer's estimate of $334,000.
- Owner
- Ohio DOT
- Letting
- 31 JUL 2025
- Pay items
- 59
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Cap-Stone & Associates Inc | $365,885 | Low | +10% |
| 2 | Strawser Paving Co Inc | $411,826 | +13% | +23% |
| 3 | Double Z Construction Company | $444,130 | +21% | +33% |
| 4 | Complete General Construction Company | $532,221 | +45% | +59% |
Engineer's estimate: $334,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Cap-Stone & Associates Inc | 2. Strawser Paving Co Inc | 3. Double Z Construction Company | 4. Complete General Construction Company |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $3,500.00 | $2,500.00 | $5,000.00 | $6,400.00 |
| 2 | Headwall removed (202E20010) | EACH | 1 | $550.00 | $990.00 | $250.00 | $300.00 |
| 3 | Pavement removed (202E23000) | SY | 39 | $35.00 | $51.00 | $24.00 | $70.00 |
| 4 | Curb removed (202E32000) | FT | 17 | $34.00 | $47.50 | $15.00 | $45.00 |
| 5 | Pipe removed, 24" and under (202E35100) | FT | 36 | $32.00 | $33.40 | $20.00 | $45.00 |
| 6 | Catch basin removed (202E58100) | EACH | 1 | $850.00 | $1,202.50 | $500.00 | $500.00 |
| 7 | Removal misc.: stepping stones removed (202E98000) | LS | 1 | $600.00 | $690.50 | $150.00 | $300.00 |
| 8 | Removal misc.: pedestrian bridge (202E98100) | EACH | 1 | $625.00 | $1,590.00 | $800.00 | $1,000.00 |
| 9 | Removal misc.: posts and chain removed (202E98100) | EACH | 1 | $685.00 | $690.50 | $250.00 | $500.00 |
| 10 | Removal misc.: sprinkler system removed (202E98100) | EACH | 10 | $44.00 | $276.20 | $50.00 | $500.00 |
| 11 | Excavation (203E10000) | CY | 123 | $95.00 | $150.00 | $60.00 | $60.00 |
| 12 | Embankment (203E20000) | CY | 117 | $205.00 | $100.00 | $60.00 | $40.00 |
| 13 | Subgrade compaction (204E10000) | SY | 256 | $4.50 | $7.60 | $15.00 | $8.00 |
| 14 | 5" concrete walk (608E12000) | SF | 8,207 | $10.00 | $11.15 | $16.00 | $15.00 |
| 15 | Curb ramp (608E52000) | SF | 623 | $14.75 | $17.50 | $24.00 | $42.00 |
| 16 | Detectable warning (608E53020) | SF | 16 | $48.00 | $22.00 | $55.00 | $40.00 |
| 17 | Special - mailbox removed and reset (690E50350) | EACH | 3 | $250.00 | $1,389.00 | $250.00 | $300.00 |
| 18 | Topsoil (659E00300) | CY | 129 | $115.00 | $75.00 | $75.00 | $60.00 |
| 19 | Seeding and mulching (659E10000) | SY | 1,157 | $3.00 | $3.00 | $6.00 | $4.25 |
| 20 | Repair seeding and mulching (659E14000) | SY | 58 | $3.00 | $3.00 | $3.00 | $6.25 |
| 21 | Inter-seeding (659E15000) | SY | 58 | $3.00 | $3.00 | $3.00 | $6.25 |
| 22 | Commercial fertilizer (659E20000) | TON | 0.15 | $1,250.00 | $1,250.00 | $1,250.00 | $700.00 |
| 23 | Lime (659E31000) | ACRE | 0.24 | $150.00 | $150.00 | $150.00 | $50.00 |
| 24 | Water (659E35000) | MGAL | 6.40 | $1.00 | $1.00 | $1.00 | $1.00 |
| 25 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 26 | Class QC1 concrete, headwall (511E46610) | CY | 1 | $2,000.00 | $3,045.00 | $2,500.00 | $1,500.00 |
| 27 | 12" conduit, type C, as per plan (611E04601) | FT | 26 | $125.00 | $215.00 | $150.00 | $120.00 |
| 28 | 15" conduit, type C, as per plan (611E06101) | FT | 51 | $135.00 | $148.00 | $160.00 | $130.00 |
| 29 | 14" X 23" conduit, type B, 706.04, as per plan (611E52203) | FT | 76 | $225.00 | $183.00 | $220.00 | $200.00 |
| 30 | Catch basin, no. 2-2B (611E98470) | EACH | 2 | $1,900.00 | $2,619.00 | $3,000.00 | $3,700.00 |
| 31 | Catch basin adjusted to grade (611E98630) | EACH | 2 | $350.00 | $767.00 | $800.00 | $1,400.00 |
| 32 | Manhole, no. 3 (611E99574) | EACH | 1 | $2,750.00 | $6,655.00 | $3,500.00 | $6,000.00 |
| 33 | Aggregate base (304E20000) | CY | 34 | $225.00 | $223.00 | $140.00 | $120.00 |
| 34 | 7" non-reinforced concrete pavement, class QC 1P (452E11010) | SY | 154 | $125.00 | $190.00 | $155.00 | $150.00 |
| 35 | Fire hydrant extended and adjusted to grade (638E10300) | EACH | 1 | $2,500.00 | $8,358.00 | $900.00 | $5,000.00 |
| 36 | Service box adjusted to grade (638E10900) | EACH | 1 | $365.00 | $585.00 | $300.00 | $460.00 |
| 37 | Removal of ground mounted sign and disposal (630E84900) | EACH | 2 | $15.51 | $125.00 | $50.00 | $25.00 |
| 38 | Removal of ground mounted sign and reerection (630E85100) | EACH | 10 | $125.99 | $250.00 | $200.00 | $345.00 |
| 39 | Removal of ground mounted post support and disposal (630E86002) | EACH | 2 | $20.68 | $125.00 | $50.00 | $30.00 |
| 40 | Removal of ground mounted post support and reerection (630E86010) | EACH | 5 | $231.42 | $250.00 | $200.00 | $420.00 |
| 41 | Signing, misc.: solar powered rectangular rapid FL (630E97700) | EACH | 2 | $10,048 | $10,050 | $10,169 | $12,000 |
| 42 | Crosswalk line, 12" (644E00620) | FT | 102 | $3.70 | $3.70 | $3.70 | $3.70 |
| 43 | Crosswalk line, 24" (644E00630) | FT | 480 | $6.65 | $6.65 | $6.65 | $6.65 |
| 44 | Yield line (644E20800) | FT | 27 | $12.50 | $12.50 | $12.50 | $12.50 |
| 45 | Removal of pavement marking (644E30000) | FT | 54 | $12.50 | $12.50 | $12.50 | $12.50 |
| 46 | Conduit, 3", 725.04 (625E25500) | FT | 111 | $84.00 | $84.40 | $85.44 | $40.00 |
| 47 | Pull box, 725.08, 24" (625E30706) | EACH | 5 | $1,261.00 | $1,261.00 | $1,276.19 | $1,700.00 |
| 48 | Pedestrian signal head (LED), type D2, countdown, as per plan (632E20731) | EACH | 8 | $786.50 | $786.50 | $795.98 | $1,200.00 |
| 49 | Accessible pedestrian pushbutton (632E20750) | EACH | 8 | $1,005.00 | $1,005.00 | $1,017.11 | $1,400.00 |
| 50 | Signal cable, 2 conductor, no. 14 AWG (632E40200) | FT | 1,839 | $3.10 | $3.10 | $3.11 | $2.75 |
| 51 | Signal cable, 5 conductor, no. 14 AWG (632E40500) | FT | 1,879 | $3.50 | $3.50 | $3.51 | $3.50 |
| 52 | Pedestal foundation (632E64020) | EACH | 8 | $2,101.50 | $2,101.50 | $2,126.82 | $4,500.00 |
| 53 | Pedestal, 11' (632E89700) | EACH | 8 | $785.00 | $785.00 | $794.46 | $1,200.00 |
| 54 | Signalization, misc.: unlash and relash messenger (632E90500) | FT | 342 | $4.65 | $4.60 | $4.67 | $8.00 |
| 55 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 16 | $95.00 | $75.00 | $60.00 | $120.00 |
| 56 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $1,200.00 | $2,640.00 | $4,500.00 | $2,520.00 |
| 57 | Maintaining traffic (614E11000) | LS | 1 | $17,500 | $37,980 | $50,000 | $65,000 |
| 58 | Construction layout stakes and surveying (623E10000) | LS | 1 | $6,500.00 | $4,100.00 | $6,000.00 | $25,000 |
| 59 | Mobilization (624E10000) | LS | 1 | $10,000 | $3,550.00 | $12,000 | $27,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of July 31, 2025. Compiled by Mirage Metrics.