ODOT letting results, July 31, 2025
19 contracts let by Ohio DOT on July 31, 2025, $36,101,334 in low bids, a median of 4 bidders per contract. On the 19 with an engineer's estimate, the low bid came in under it 11 times; median low bid -4.0% against the estimate.
- Owner
- Ohio DOT
- Contracts
- 19
- Low bids, total
- $36,101,334
- Data through
- 12 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 250347 | POR-IR 76-09.73 (FOUR LANE RESURFACING) | POR | 4 | Shelly & Sands Inc | $9,962,306 | $10,011,386 | 0.0% | +43% | ODOT |
| 250357 | HAM-IR 275-25.45 (FOUR LANE RESURFACING) | HAM | 2 | John R Jurgensen Company | $8,957,176 | $10,500,000 | +17% | +28% | ODOT |
| 250366 | WAY-SR 302-03.82 (TWO LANE RESURFACING) | WAY | 4 | Kokosing Construction Company Inc | $4,175,327 | $4,226,926 | +1.0% | -8.0% | ODOT |
| 250367 | WIL-US 20-00.00 Resurfacing (TWO LANE RESURFACING) | WIL | 1 | Gerken Paving Inc | $3,795,093 | -3.0% | ODOT | ||
| 250370 | D06-Bridge Pier Encasements (BRIDGE REPAIR) | District 6 | 6 | Ohio Concrete Maintenance LLC | $1,599,921 | $1,772,480 | +11% | +33% | ODOT |
| 250364 | TRU-SR 193-17.77 (TWO LANE RESURFACING) | TRU | 4 | Shelly & Sands Inc | $1,511,607 | $1,575,000 | +4.0% | -30% | ODOT |
| 250359 | JAC-SR 93-04.67 (TWO LANE RESURFACING) | JAC | 3 | Fillmore Construction | $946,580 | $1,018,109 | +8.0% | -8.0% | ODOT |
| 250358 | HAS-SR 149-01.17 (CULVERT REPLACEMENT) | HAS | 5 | Tucson Inc | $711,194 | $712,356 | 0.0% | -12% | ODOT |
| 250360 | LAW-SR 522-00.00 (CHIP SEAL) | LAW | 2 | Shelly Company | $656,919 | $867,958 | +32% | -4.0% | ODOT |
| 250373 | LUC-/OTT-SR 65/SR 163 FY2026 Oper (MISCELLANEOUS) | LUC | 1 | Dependable Tree and Maintenance Services LLC | $644,470 | -6.0% | ODOT | ||
| 250368 | ATB-LG FY2026 (SIGNALIZATION) | ATB | 4 | Cornerstone Electric Inc | $467,436 | $562,357 | +20% | -19% | ODOT |
| 250362 | MED-IR 271-05.64 (SLIDE REPAIR) | MED | 4 | Great Lakes Construction Co | $448,589 | $515,639 | +15% | +10% | ODOT |
| 258020 | LOR-US 6-09.67 Span Locks (BRIDGE REPAIR) | LOR | 1 | Ruhlin Company | $388,774 | +69% | ODOT | ||
| 250361 | MAD-US 42/CR 40/West Ave-Sidewalks (SIDEWALK) | MAD | 4 | Cap-Stone & Associates Inc | $365,885 | $411,826 | +13% | +10% | ODOT |
| 250369 | CLA-/MOT CR/BH FY26 (CULVERT REPLACEMENT) | CLA | 3 | Sunesis Construction Co | $365,504 | $656,797 | +80% | +43% | ODOT |
| 250363 | PAU-US 127-10.23 (BRIDGE REPAIR) | PAU | 6 | Catts Construction Inc | $328,707 | $331,187 | +1.0% | -32% | ODOT |
| 250365 | TUS-IR 77-01.21 (CULVERT REPLACEMENT) | TUS | 4 | Geotech Services Inc | $298,236 | $395,573 | +33% | -12% | ODOT |
| 250371 | FRA-US 33-28.61 (INTERSECTION) | FRA | 5 | Shelly & Sands Inc | $255,800 | $255,964 | 0.0% | +2.0% | ODOT |
| 250372 | HAN-SR 15-20.26 (INTERSECTION) | HAN | 3 | Advanced Excavating & Demolition LLC | $221,810 | $263,543 | +19% | -19% | ODOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.