ODOT contract 250370 bid tabulation

D06-Bridge Pier Encasements (BRIDGE REPAIR). Let by Ohio DOT on July 31, 2025, District 6. 6 bids received; low bid $1,599,921 by Ohio Concrete Maintenance LLC, +33% against the engineer's estimate of $1,203,000.

Owner
Ohio DOT
Letting
31 JUL 2025
Pay items
54
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Ohio Concrete Maintenance LLC$1,599,921Low+33%
2Complete General Construction Company$1,772,480+11%+47%
3BCC Ohio Inc$2,330,861+46%+94%
4S E T Inc$2,711,891+70%+125%
5Ruhlin Company$2,806,820+75%+133%
6Double Z Construction Company$2,992,373+87%+149%
ODOT contract 250370: bids by rank

Engineer's estimate: $1,203,000.

Bid tabulation

LinePay itemUnitQuantity1. Ohio Concrete Maintenance LLC2. Complete General Construction Company3. BCC Ohio Inc4. S E T Inc5. Ruhlin Company6. Double Z Construction Company
1Clearing and grubbing (201E11000)LS1$12,000$21,000$50,430$50,000$120,000$65,000
2Topsoil (659E00300)CY122$75.00$35.00$70.80$100.00$270.00$245.00
3Seeding and mulching (659E10000)SY1,100$6.00$6.45$6.77$3.75$26.00$50.00
4Repair seeding and mulching (659E14000)SY55$8.00$3.60$3.78$4.00$7.00$1.00
5Inter-seeding (659E15000)SY55$10.00$0.10$0.11$4.00$7.00$0.01
6Commercial fertilizer (659E20000)TON0.15$1,000.00$650.00$682.53$1,400.00$700.00$1,500.00
7Lime (659E31000)ACRE0.23$1,000.00$100.00$105.00$800.00$100.00$200.00
8Water (659E35000)MGAL6$20.00$1.00$1.05$15.00$1.00$1.00
9Erosion control (832E30000)EACH16,500$1.00$1.00$1.00$1.00$1.00$1.00
10Cofferdams and excavation bracing (503E11100)LS1$23,000$95,000$32,844$70,000$1.00$118,000
11Unclassified excavation (503E21300)LS1$15,000$10,000$8,173.44$20,000$20,000$21,000
12Special - pile encasement (507E71200)FT162$297.00$250.00$379.70$350.00$400.00$310.00
13Structural steel members, level UF (513E10200)LB1,526$18.00$30.00$35.48$36.00$45.00$30.00
14Cofferdams and excavation bracing (503E11100)LS1$25,000$60,000$54,600$69,000$1.00$115,000
15Unclassified excavation (503E21300)LS1$15,000$9,000.00$42,000$23,000$25,000$25,000
16Special - pile encasement (507E71200)FT252$297.00$135.00$315.00$285.00$400.00$280.00
17Structural steel members, level UF (513E10200)LB2,289$18.00$30.00$38.05$36.00$45.00$30.00
18Cofferdams and excavation bracing (503E11100)LS1$25,000$60,000$50,400$70,000$1.00$130,000
19Unclassified excavation (503E21300)LS1$15,000$9,000.00$36,750$16,000$25,000$17,000
20Special - pile encasement (507E71200)FT171$297.00$135.00$393.75$300.00$400.00$285.00
21Structural steel members, level UF (513E10200)LB2,289$18.00$30.00$38.05$36.00$45.00$30.00
22Cofferdams and excavation bracing (503E11100)LS1$25,000$58,000$36,948$61,000$1.00$95,000
23Unclassified excavation (503E21300)LS1$15,000$9,000.00$9,987.00$20,000$30,000$17,000
24Special - pile encasement (507E71200)FT152$315.00$135.00$382.44$315.00$400.00$280.00
25Structural steel members, level UF (513E10200)LB2,035$18.00$30.00$34.05$36.00$45.00$30.00
26Cofferdams and excavation bracing (503E11100)LS1$23,000$75,000$39,000$70,000$1.00$130,000
27Unclassified excavation (503E21300)LS1$15,000$9,000.00$18,162$35,000$50,000$48,000
28Special - pile encasement (507E71200)FT252$295.00$135.00$370.75$320.00$400.00$270.00
29Cofferdams and excavation bracing (503E11100)LS1$23,000$55,000$34,896$52,000$1.00$110,000
30Unclassified excavation (503E21300)LS1$15,000$9,000.00$9,081.00$16,000$20,000$21,000
31Special - pile encasement (507E71200)FT119$325.00$135.00$386.46$340.00$400.00$255.00
32Cofferdams and excavation bracing (503E11100)LS1$23,000$50,000$26,640$35,000$1.00$90,000
33Unclassified excavation (503E21300)LS1$15,000$9,000.00$9,081.00$16,000$20,000$19,000
34Special - pile encasement (507E71200)FT95$325.00$135.00$472.54$300.00$400.00$260.00
35Structural steel members, level UF (513E10200)LB1,272$18.00$30.00$38.47$36.00$45.00$30.00
36Cofferdams and excavation bracing (503E11100)LS1$23,000$50,000$39,000$38,000$1.00$115,000
37Unclassified excavation (503E21300)LS1$15,000$9,000.00$7,038.00$16,000$20,000$19,000
38Special - pile encasement (507E71200)FT70$325.00$135.00$429.43$435.00$400.00$270.00
39Cofferdams and excavation bracing (503E11100)LS1$23,000$95,000$50,400$65,000$1.00$140,000
40Unclassified excavation (503E21300)LS1$15,000$10,000$36,750$17,000$25,000$21,000
41Special - pile encasement (507E71200)FT96$325.00$250.00$462.00$395.00$400.00$270.00
42Structural steel members, level UF (513E10200)LB1,526$18.00$30.00$38.05$36.00$45.00$30.00
43Portions of structure removed, over 20 foot span, as per plan (202E11203)LS1$35,000$20,000$36,960$75,000$70,000$30,000
44Cofferdams and excavation bracing (503E11100)LS1$32,000$95,000$90,000$93,000$1.00$165,000
45Unclassified excavation (503E21300)LS1$25,000$15,000$14,304$27,000$35,000$28,000
46Special - pile encasement (507E71200)FT324$300.00$135.00$411.90$310.00$400.00$240.00
47Portions of structure removed, over 20 foot span, as per plan (202E11203)LS1$65,000$45,000$27,930$175,000$135,000$90,000
48Cofferdams and excavation bracing (503E11100)LS1$20,000$95,000$39,000$50,000$1.00$140,000
49Unclassified excavation (503E21300)LS1$12,000$9,000.00$9,081.00$16,000$25,000$23,000
50Special - pile encasement (507E71200)FT270$295.00$135.00$371.35$290.00$400.00$240.00
51Premium for contract performance bond and for payment bond (103E05000)LS1$36,000$12,000$28,776$50,000$13,000$17,000
52Maintaining traffic (614E11000)LS1$50,000$20,000$152,802$55,000$632,500$125,000
53Construction layout stakes and surveying (623E10000)LS1$8,000.00$21,000$30,167$10,000$45,000$6,000.00
54Mobilization (624E10000)LS1$130,000$87,500$113,310$350,000$140,000$100,000
ODOT contract 250370: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of July 31, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy