ODOT contract 250368 bid tabulation

ATB-LG FY2026 (SIGNALIZATION). Let by Ohio DOT on July 31, 2025, ATB. 4 bids received; low bid $467,436 by Cornerstone Electric Inc, -19% against the engineer's estimate of $578,000.

Owner
Ohio DOT
Letting
31 JUL 2025
Pay items
31
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Cornerstone Electric Inc$467,436Low-19%
2Miller Cable Company$562,357+20%-3.0%
3Ruhlin Company$576,852+23%0.0%
4Perram Electric Inc$627,810+34%+9.0%
ODOT contract 250368: bids by rank

Engineer's estimate: $578,000.

Bid tabulation

LinePay itemUnitQuantity1. Cornerstone Electric Inc2. Miller Cable Company3. Ruhlin Company4. Perram Electric Inc
1Clearing and grubbing (201E11000)LS1$1,000.00$1,200.00$11,000$3,290.00
2Special - as-built construction plans (690E91000)LS1$1,000.00$2,820.00$400.00$1,000.00
3Special - survey control verification (690E98400)LS1$3,600.00$3,580.00$900.00$675.00
44" conduit, type C (611E00200)FT120$10.00$9.00$15.00$9.55
5Precast reinforced concrete outlet (611E99710)EACH12$350.00$475.00$500.00$505.00
6Connection, unfused permanent (625E00480)EACH48$125.00$100.00$225.00$148.00
7Light tower, BBB100 (625E12200)EACH6$24,000$28,100$27,550$26,310
8Light tower foundation, 36" X 25' deep (625E15200)EACH6$9,500.00$15,000$13,125$19,455
9No. 4 AWG 2400 volt distribution cable (625E23200)FT2,109$3.50$3.85$4.00$3.48
101-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320)FT2,691$10.50$13.00$16.50$12.70
11Conduit, jacked or drilled, 725.04, 4" (625E25902)FT633$70.00$55.00$68.00$70.60
12Luminaire, high mast, solid state (LED) (70000-850 (625E26262)EACH6$1,250.00$1,250.00$1,420.00$1,230.00
13Luminaire, high mast, solid state (LED) (70000-850 (625E26262)EACH12$1,250.00$1,265.00$1,420.00$1,230.00
14Trench (625E29000)FT2,581$8.00$7.00$9.00$18.14
15Pull box, 725.08, 24" (625E30706)EACH12$1,500.00$1,250.00$1,450.00$2,065.00
16Pull box removed (625E31510)EACH6$200.00$250.00$240.00$103.00
17Ground rod (625E32000)EACH6$800.00$1,200.00$350.00$330.00
18Power service, as per plan (625E34001)EACH1$10,000$10,500$10,200$11,500
19Underground warning/marking tape, as per plan (625E36011)FT2,581$0.50$2.00$0.70$1.49
20Special - maintain existing lighting (625E40000)LS1$500.00$2,500.00$2,950.00$1,235.00
21Special - replacement of existing lighting unit (625E40010)EACH2$50.00$1,700.00$100.00$250.00
22Light tower removed (625E75350)EACH12$1,000.00$3,200.00$2,150.00$2,520.00
23Light tower foundation removed (625E75540)EACH7$750.00$450.00$600.00$820.00
24Light tower foundation removed, as per plan (625E75541)EACH5$1,500.00$3,500.00$1,700.00$5,345.00
25Arc flash calculations and label (CC) (625E76000)EACH1$500.00$3,000.00$500.00$1,800.00
26Law enforcement officer with patrol car for assistance (614E11110)HR100$75.00$40.00$90.00$100.00
27Premium for contract performance bond and for payment bond (103E05000)LS1$5,000.00$3,400.00$2,700.00$9,872.15
28Maintaining traffic (614E11000)LS1$10,000$15,000$14,700$7,775.00
29Field office, type B (619E16010)MNTH12$1,500.00$100.00$2,250.00$1,635.00
30Construction layout stakes and surveying (623E10000)LS1$4,700.00$15,000$1,735.00$2,550.00
31Mobilization (624E10000)LS1$20,000$20,000$27,000$20,000
ODOT contract 250368: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of July 31, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy