ODOT contract 250368 bid tabulation
ATB-LG FY2026 (SIGNALIZATION). Let by Ohio DOT on July 31, 2025, ATB. 4 bids received; low bid $467,436 by Cornerstone Electric Inc, -19% against the engineer's estimate of $578,000.
- Owner
- Ohio DOT
- Letting
- 31 JUL 2025
- Pay items
- 31
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Cornerstone Electric Inc | $467,436 | Low | -19% |
| 2 | Miller Cable Company | $562,357 | +20% | -3.0% |
| 3 | Ruhlin Company | $576,852 | +23% | 0.0% |
| 4 | Perram Electric Inc | $627,810 | +34% | +9.0% |
Engineer's estimate: $578,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Cornerstone Electric Inc | 2. Miller Cable Company | 3. Ruhlin Company | 4. Perram Electric Inc |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $1,000.00 | $1,200.00 | $11,000 | $3,290.00 |
| 2 | Special - as-built construction plans (690E91000) | LS | 1 | $1,000.00 | $2,820.00 | $400.00 | $1,000.00 |
| 3 | Special - survey control verification (690E98400) | LS | 1 | $3,600.00 | $3,580.00 | $900.00 | $675.00 |
| 4 | 4" conduit, type C (611E00200) | FT | 120 | $10.00 | $9.00 | $15.00 | $9.55 |
| 5 | Precast reinforced concrete outlet (611E99710) | EACH | 12 | $350.00 | $475.00 | $500.00 | $505.00 |
| 6 | Connection, unfused permanent (625E00480) | EACH | 48 | $125.00 | $100.00 | $225.00 | $148.00 |
| 7 | Light tower, BBB100 (625E12200) | EACH | 6 | $24,000 | $28,100 | $27,550 | $26,310 |
| 8 | Light tower foundation, 36" X 25' deep (625E15200) | EACH | 6 | $9,500.00 | $15,000 | $13,125 | $19,455 |
| 9 | No. 4 AWG 2400 volt distribution cable (625E23200) | FT | 2,109 | $3.50 | $3.85 | $4.00 | $3.48 |
| 10 | 1-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320) | FT | 2,691 | $10.50 | $13.00 | $16.50 | $12.70 |
| 11 | Conduit, jacked or drilled, 725.04, 4" (625E25902) | FT | 633 | $70.00 | $55.00 | $68.00 | $70.60 |
| 12 | Luminaire, high mast, solid state (LED) (70000-850 (625E26262) | EACH | 6 | $1,250.00 | $1,250.00 | $1,420.00 | $1,230.00 |
| 13 | Luminaire, high mast, solid state (LED) (70000-850 (625E26262) | EACH | 12 | $1,250.00 | $1,265.00 | $1,420.00 | $1,230.00 |
| 14 | Trench (625E29000) | FT | 2,581 | $8.00 | $7.00 | $9.00 | $18.14 |
| 15 | Pull box, 725.08, 24" (625E30706) | EACH | 12 | $1,500.00 | $1,250.00 | $1,450.00 | $2,065.00 |
| 16 | Pull box removed (625E31510) | EACH | 6 | $200.00 | $250.00 | $240.00 | $103.00 |
| 17 | Ground rod (625E32000) | EACH | 6 | $800.00 | $1,200.00 | $350.00 | $330.00 |
| 18 | Power service, as per plan (625E34001) | EACH | 1 | $10,000 | $10,500 | $10,200 | $11,500 |
| 19 | Underground warning/marking tape, as per plan (625E36011) | FT | 2,581 | $0.50 | $2.00 | $0.70 | $1.49 |
| 20 | Special - maintain existing lighting (625E40000) | LS | 1 | $500.00 | $2,500.00 | $2,950.00 | $1,235.00 |
| 21 | Special - replacement of existing lighting unit (625E40010) | EACH | 2 | $50.00 | $1,700.00 | $100.00 | $250.00 |
| 22 | Light tower removed (625E75350) | EACH | 12 | $1,000.00 | $3,200.00 | $2,150.00 | $2,520.00 |
| 23 | Light tower foundation removed (625E75540) | EACH | 7 | $750.00 | $450.00 | $600.00 | $820.00 |
| 24 | Light tower foundation removed, as per plan (625E75541) | EACH | 5 | $1,500.00 | $3,500.00 | $1,700.00 | $5,345.00 |
| 25 | Arc flash calculations and label (CC) (625E76000) | EACH | 1 | $500.00 | $3,000.00 | $500.00 | $1,800.00 |
| 26 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 100 | $75.00 | $40.00 | $90.00 | $100.00 |
| 27 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $5,000.00 | $3,400.00 | $2,700.00 | $9,872.15 |
| 28 | Maintaining traffic (614E11000) | LS | 1 | $10,000 | $15,000 | $14,700 | $7,775.00 |
| 29 | Field office, type B (619E16010) | MNTH | 12 | $1,500.00 | $100.00 | $2,250.00 | $1,635.00 |
| 30 | Construction layout stakes and surveying (623E10000) | LS | 1 | $4,700.00 | $15,000 | $1,735.00 | $2,550.00 |
| 31 | Mobilization (624E10000) | LS | 1 | $20,000 | $20,000 | $27,000 | $20,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of July 31, 2025. Compiled by Mirage Metrics.